Austin Traffic Signal Construction Co., L.P., D/B/A ATS Electrical Contractors' Cajun Constructors, Inc. Liberty Mutual Insurance Company And Fidelity and Guaranty Insurance Underwriters, Inc. v. Transdyn Controls, Inc.

CourtCourt of Appeals of Texas
DecidedAugust 24, 2010
Docket03-06-00655-CV
StatusPublished

This text of Austin Traffic Signal Construction Co., L.P., D/B/A ATS Electrical Contractors' Cajun Constructors, Inc. Liberty Mutual Insurance Company And Fidelity and Guaranty Insurance Underwriters, Inc. v. Transdyn Controls, Inc. (Austin Traffic Signal Construction Co., L.P., D/B/A ATS Electrical Contractors' Cajun Constructors, Inc. Liberty Mutual Insurance Company And Fidelity and Guaranty Insurance Underwriters, Inc. v. Transdyn Controls, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Austin Traffic Signal Construction Co., L.P., D/B/A ATS Electrical Contractors' Cajun Constructors, Inc. Liberty Mutual Insurance Company And Fidelity and Guaranty Insurance Underwriters, Inc. v. Transdyn Controls, Inc., (Tex. Ct. App. 2010).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-06-00655-CV

Austin Traffic Signal Construction Co., L.P., d/b/a ATS Electrical Contractors; Cajun Constructors, Inc.; Liberty Mutual Insurance Company; and Fidelity and Guaranty Insurance Underwriters, Inc., Appellants

v.

Transdyn Controls, Inc., Appellee

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 201ST JUDICIAL DISTRICT NO. D-1-GN-02-002371, HONORABLE LORA J. LIVINGSTON, JUDGE PRESIDING

MEMORANDUM OPINION

This case involves a contract between an equipment supplier and an electrical

subcontractor on a City of Austin construction project. Transdyn Controls, the equipment supplier,

sued subcontractor Austin Traffic Signal Construction Co., L.P. (“ATS”) for failing to pay for the

equipment Transdyn had supplied for the construction project. Transdyn also sued Cajun

Constructors, Inc., Liberty Mutual Insurance Company, and Fidelity and Guaranty Insurance

Underwriters, Inc., alleging that they were responsible for Transdyn’s damages because they had

provided payment bonds on the project. ATS filed a counterclaim against Transdyn, asserting that

Transdyn had breached the parties’ equipment-supply contract by providing defective equipment and

by failing to complete other obligations under the parties’ contract. After a bench trial, the trial court

rendered judgment in favor of Transdyn. In six issues, ATS asserts that the trial court erred by (1) admitting certain witness testimony into evidence, (2) failing to award ATS an offset for training

fees it had incurred as a result of Transdyn’s breach, and (3) awarding “incidental delay damages”

to Transdyn. We affirm the trial court’s judgment.

BACKGROUND

In September 2000, the City of Austin entered into a construction contract with Cajun

Contractors, as general contractor, to build the Walnut Creek Wastewater Treatment Plant in Austin

(“Walnut Creek project”).1 Cajun, in turn, entered into a $3.7 million subcontract with ATS to

provide the electrical and instrumentation work on the Walnut Creek project. ATS’s scope of work

under its subcontract included providing “all labor, materials, and equipment to design, furnish,

install, calibrate, test, adjust, and place in operation the facility monitoring and control

system”—also known as the process instrumentation and control system (“PICS”). PICS includes

the sensors and instruments used to monitor and control the facility and permit remote access and

control of those sensors and instruments.

Although ATS was responsible for PICS under its subcontract with Cajun, the

specifications for the Walnut Creek project required that the City of Austin approve the PICS

supplier and installer. ATS asked Transdyn, one of four city-qualified PICS suppliers, to submit a

proposal to supply the PICS for the Walnut Creek project. ATS told Transdyn, and the project

specifications provided, that the Walnut Creek project was scheduled to be completed 360 days after

construction began. Transdyn’s representative also testified that ATS’s representative told Transdyn

1 The facts recited in this opinion are taken from the testimony and exhibits admitted at trial.

2 that ATS’s PICS budget was $1,000,000. ATS also sent Transdyn the project specifications

covering PICS.

Based on all the information it had received from ATS, Transdyn submitted a

$1,000,000 proposal “for furnishing, but not installing, portions of the [PICS] for the subject project

as defined in [the sections of the project plans and specifications ATS] provided.” The proposal also

specified that Transdyn would provide certain training. The PICS section of the project plans, which

were incorporated by reference into the proposal, included the following payment terms for the PICS

part of the project:

Partial Payment Limits:

A. Partial payments for Work required under PICS Subsystems is shown as a percent of Lump Sum Item amount:

1. Submittals, not including PICS O&M manuals, 15 percent maximum,

2. Performance Acceptance Tests PAT, 20 percent, minimum.

3. Reliability Acceptance Tests RAT, 20 percent, minimum.

4. PICS O&M manuals, 5 percent, minimum.

(Emphasis in original). Transdyn’s proposal stated that payment would be according to “mutually

agreeable payment terms resulting in neutral cash flow for the project.”2 ATS accepted Transdyn’s

proposal and authorized Transdyn to begin work on the project on September 14, 2000.

2 Transdyn’s representative testified at trial that “neutral cash flow” is “a common term used in the construction industry to indicate pay as you go . . . so as you incur the costs, you receive payment for them.”

3 Approximately two months after construction began on the Walnut Creek project,

Transdyn, ATS, and Cajun agreed on the following payment schedule for Transdyn’s work:

As agreed upon at our partnering meeting, the following table is Transdyn’s revised Milestone/Payment Schedule. Note that the payment dates are the estimated dates for payment of the invoice and are approximately one month after the issuing of the invoice.

Cont. Milestone Payments Amt: $1,000,000 % Retained 5%

Less Expected Milestone % Payment Retainage Pay Date Acceptance of Schedule/Schedule of 5% $50,000.00 $47,500.00 Oct-00 Values/Hardware List Hardware Submittal 10% $100,000.00 $95,000.00 May-01 Approval Hardware Shipped to 40% $400,000.00 $380,000.00 Jan-01 Staging Performance Acceptance Tests 20% $200,000.00 $190,000.00 Aug-01 Complete Reliability Acceptance Tests 20% $200,000.00 $190,000.00 Sep-01 Complete O&M Manual 5% $50,000.00 $47,500.00 Sep.-01 Approved Final Payment $50,000.00 $50,000.00 Sep.-01 100% $1,000,000.00

(hereinafter,“milestone payment schedule”). Transdyn’s representative testified that the purpose of

this agreement was to achieve the “mutually agreeable payment terms resulting in neutral cash flow”

4 described in Transdyn’s original proposal by requiring ATS to pay Transdyn approximately one

month after receiving Transdyn’s invoice for each milestone. ATS’s representative testified that this

agreement meant that Transdyn would be paid a certain amount after each milestone was reached

and final payment after the last milestone was reached, rather than by a date certain or invoice date.

In addition to modifying the contract’s payment terms, ATS and Transdyn also later

agreed to modify the training provisions of their contract. This modification resulted from requests

by the project engineers that Transdyn make certain design changes to the PICS. Transdyn notified

ATS that making the requested changes would require a change-order and an increase of $11,375.61

to the parties’ contract. After negotiations, the parties agreed to incorporate the changes into the

existing contract at no extra charge to ATS and, in exchange, release Transdyn from some of its

obligation to provide post-installation training.

Transdyn made the requested changes to the PICS system, but when PICS was

installed and ATS requested a week of training from Transdyn, the parties realized there was a

misunderstanding about the modification. Transdyn contends that it had agreed to perform the

change-order work—valued at $11,375—in exchange for a release from its entire three-week training

commitment—valued by Transdyn at $12,000. ATS contends that it only agreed to release Transdyn

from two of the three weeks of training and that Transdyn was still required to provide one week of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Wagner & Brown, Ltd. v. Sheppard
282 S.W.3d 419 (Texas Supreme Court, 2008)
City of Beaumont v. Excavators & Constructors, Inc.
870 S.W.2d 123 (Court of Appeals of Texas, 1994)
Malone v. Carl Kisabeth Co., Inc.
726 S.W.2d 188 (Court of Appeals of Texas, 1987)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Interstate Northborough Partnership v. State
66 S.W.3d 213 (Texas Supreme Court, 2001)
Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.
930 S.W.2d 877 (Court of Appeals of Texas, 1996)
Ortiz v. Jones
917 S.W.2d 770 (Texas Supreme Court, 1996)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Strauss v. Continental Airlines, Inc.
67 S.W.3d 428 (Court of Appeals of Texas, 2002)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Downer v. Aquamarine Operators, Inc.
701 S.W.2d 238 (Texas Supreme Court, 1985)
Strickland Transportation Co. v. Ingram
403 S.W.2d 192 (Court of Appeals of Texas, 1966)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
in the Interest of J.P.B., a Child
180 S.W.3d 570 (Texas Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Austin Traffic Signal Construction Co., L.P., D/B/A ATS Electrical Contractors' Cajun Constructors, Inc. Liberty Mutual Insurance Company And Fidelity and Guaranty Insurance Underwriters, Inc. v. Transdyn Controls, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-traffic-signal-construction-co-lp-dba-ats-electrical-texapp-2010.