NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED
IN THE DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT
AUSTIN COMMERCIAL, L.P., a ) Delaware limited partnership, ) ) Appellant, ) ) v. ) Case No. 2D18-1051 ) L.M.C.C. SPECIALTY CONTRACTORS, ) INC., d/b/a MIMS CONSTRUCTION ) COMPANY, a Florida corporation, ) ) Appellee. ) ___________________________________)
Opinion filed April 10, 2019.
Appeal from the Circuit Court for Hillsborough County; Paul L. Huey, Judge.
Aaron H. Reichelson, Marie Tomassi, and Patrick J. Poff of Trenam, Kemker, Scharf, Barkin, Frye, O'Neill & Mullis, P.A., Tampa, for Appellant.
Douglas A. Wallace and Joseph T. Eagleton of Brannock & Humphries, Tampa; and Derin Parks of Grimes Goebel Grimes Hawkins Gladfelter & Galvano, P.L., Bradenton, for Appellee.
BADALAMENTI, Judge.
Austin Commercial, L.P. (Austin) appeals from a nonfinal order denying its
motion to compel arbitration of its dispute with L.M.C.C. Specialty Contractors, Inc.,
d/b/a Mims Construction Company (Mims). We hold that Austin and Mims entered into a valid contract mandating arbitration of the underlying lawsuit initiated by Mims. We
thus reverse the trial court's order denying Austin's motion to compel arbitration and
remand for entry of an order granting Austin's motion to compel arbitration.
The Hillsborough County Aviation Authority (HCAA) awarded a contract to
Austin for construction of a consolidated rental car facility and automated people mover
at the Tampa International Airport. The project proceeded in two parts: the design
phase (Part 1) and the construction phase (Part 2). Mims served as one of Austin's
subcontractors on both phases of the project. For each of the two phases, Austin
entered into a contract with the HCAA (the prime contracts). The prime contracts state
that any action initiated by either party, HCAA or Austin, would be resolved in state
court as follows: "Any action initiated by either party associated with a claim or dispute,
and the exclusive venue and jurisdiction for any such action, will be brought in the
appropriate State Court in and for Hillsborough County, Florida."
After entering into the prime contract for Part 1 with HCAA, Austin
executed a "Consultant Agreement" with Mims that served as Austin and Mims's
subcontract for the design phase. Section 19.1 of the subcontract between Austin and
Mims contained the following provision:
Any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be subject to the dispute resolution procedures, if any, set out in the Prime Contract between Austin and the [HCAA]. Should the Prime Contract contain no specific requirement for the resolution of disputes or should the [HCAA] not be involved in the dispute, any such controversy or claim shall be resolved by arbitration pursuant to the Construction Industry Rules of the American Arbitration Association then prevailing, and judgment upon the award by the Arbitrator(s) shall be entered in any Court having jurisdiction thereof.
-2- Austin subsequently executed the "Part 2 Contract" with HCAA governing
the construction phase of the project. Thereafter, and consistent with a Memorandum
of Understanding between Austin and Mims attached to the Consultant Agreement,
Austin executed a Work Order with Mims that extended Mims's work on the airport
project to the second phase of the project. The Work Order incorporated the terms and
conditions of the Consultant Agreement (including the dispute resolution provision) and
served as Austin and Mims's subcontract for the construction phase.
After Mims completed its construction work for Part 2 of the project, Mims
filed an amended complaint in Hillsborough County state court for, among other things,
breach of contract against Austin under quasi-contractual and equitable theories. It
further requested a declaration that it was not required to arbitrate its claims against
Austin. HCAA is not a party to the lawsuit. The gravamen of Mims's lawsuit is that
Austin did not pay Mims for the services it had provided after it received full payment for
the project from HCAA. Mims further alleged that Austin did not employ Mims for all
services for the project it had promised to Mims. Austin subsequently filed an amended
motion to stay and compel arbitration of the claims.
During the hearing on the motion, Austin argued that Mims agreed to
arbitrate the dispute because "the dispute resolution provision [in the Consultant
Agreement] says if the owner is not involved in the dispute, you don't go to their dispute
resolution procedure, but instead do arbitration." The trial court, however, construed the
arbitration clause contained in the Consultant Agreement—and incorporated by
reference into the Work Order for Part 2—to deny Austin's motion to compel arbitration.
The trial court reasoned that because the prime contract between HCAA and Austin
-3- contained a dispute resolution provision providing for litigation of disputes, Austin and
Mims were required to litigate their dispute. Austin appeals, arguing that the trial court
erred in its interpretation of the Consultant Agreement's dispute resolution provision.
Because the trial court's order denying the motion to compel arbitration is
based entirely on its construction of the contract documents, our standard of review is
de novo. SCG Harbourwood, LLC v. Hanyan, 93 So. 3d 1197, 1199 (Fla. 2d DCA
2012). In ruling on a motion to compel arbitration of a given dispute, courts must
consider three elements: "(1) whether a valid written agreement to arbitrate exists; (2)
whether an arbitrable issue exists; and (3) whether the right to arbitration was waived."
Seifert v. U.S. Home Corp., 750 So. 2d 633, 636 (Fla. 1999). Here, the only element in
dispute is whether the parties executed a valid written agreement to arbitrate their
claims.
As an initial matter, we reject Mims's argument that it did not enter into a
subcontract with Austin for Part 2 of the project. The trial court necessarily determined
that there was a valid contract for Part 2 of the project. That is, the trial court relied on
language incorporated into the Work Order, the agreement between Austin and Mims
for Part 2 of the project, in denying Austin's motion despite Mims's argument at the
hearing that the parties did not enter into a contract for Part 2. If the parties never
entered into a valid contract, there would have been no need for the trial court to
interpret and apply the arbitration clause. Thus, necessary and implicit to its ruling that
the agreement between Austin and Mims did not compel arbitration is a finding that the
parties did indeed execute a valid subcontract for Part 2.
-4- "It is a generally accepted rule of contract law that, where a writing
expressly refers to and sufficiently describes another document, that other document, or
so much of it as is referred to, is to be interpreted as part of the writing." OBS Co. v.
Pace Const. Corp., 558 So. 2d 404, 406 (Fla. 1990). With this in mind, we hold the
Free access — add to your briefcase to read the full text and ask questions with AI
NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED
IN THE DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT
AUSTIN COMMERCIAL, L.P., a ) Delaware limited partnership, ) ) Appellant, ) ) v. ) Case No. 2D18-1051 ) L.M.C.C. SPECIALTY CONTRACTORS, ) INC., d/b/a MIMS CONSTRUCTION ) COMPANY, a Florida corporation, ) ) Appellee. ) ___________________________________)
Opinion filed April 10, 2019.
Appeal from the Circuit Court for Hillsborough County; Paul L. Huey, Judge.
Aaron H. Reichelson, Marie Tomassi, and Patrick J. Poff of Trenam, Kemker, Scharf, Barkin, Frye, O'Neill & Mullis, P.A., Tampa, for Appellant.
Douglas A. Wallace and Joseph T. Eagleton of Brannock & Humphries, Tampa; and Derin Parks of Grimes Goebel Grimes Hawkins Gladfelter & Galvano, P.L., Bradenton, for Appellee.
BADALAMENTI, Judge.
Austin Commercial, L.P. (Austin) appeals from a nonfinal order denying its
motion to compel arbitration of its dispute with L.M.C.C. Specialty Contractors, Inc.,
d/b/a Mims Construction Company (Mims). We hold that Austin and Mims entered into a valid contract mandating arbitration of the underlying lawsuit initiated by Mims. We
thus reverse the trial court's order denying Austin's motion to compel arbitration and
remand for entry of an order granting Austin's motion to compel arbitration.
The Hillsborough County Aviation Authority (HCAA) awarded a contract to
Austin for construction of a consolidated rental car facility and automated people mover
at the Tampa International Airport. The project proceeded in two parts: the design
phase (Part 1) and the construction phase (Part 2). Mims served as one of Austin's
subcontractors on both phases of the project. For each of the two phases, Austin
entered into a contract with the HCAA (the prime contracts). The prime contracts state
that any action initiated by either party, HCAA or Austin, would be resolved in state
court as follows: "Any action initiated by either party associated with a claim or dispute,
and the exclusive venue and jurisdiction for any such action, will be brought in the
appropriate State Court in and for Hillsborough County, Florida."
After entering into the prime contract for Part 1 with HCAA, Austin
executed a "Consultant Agreement" with Mims that served as Austin and Mims's
subcontract for the design phase. Section 19.1 of the subcontract between Austin and
Mims contained the following provision:
Any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be subject to the dispute resolution procedures, if any, set out in the Prime Contract between Austin and the [HCAA]. Should the Prime Contract contain no specific requirement for the resolution of disputes or should the [HCAA] not be involved in the dispute, any such controversy or claim shall be resolved by arbitration pursuant to the Construction Industry Rules of the American Arbitration Association then prevailing, and judgment upon the award by the Arbitrator(s) shall be entered in any Court having jurisdiction thereof.
-2- Austin subsequently executed the "Part 2 Contract" with HCAA governing
the construction phase of the project. Thereafter, and consistent with a Memorandum
of Understanding between Austin and Mims attached to the Consultant Agreement,
Austin executed a Work Order with Mims that extended Mims's work on the airport
project to the second phase of the project. The Work Order incorporated the terms and
conditions of the Consultant Agreement (including the dispute resolution provision) and
served as Austin and Mims's subcontract for the construction phase.
After Mims completed its construction work for Part 2 of the project, Mims
filed an amended complaint in Hillsborough County state court for, among other things,
breach of contract against Austin under quasi-contractual and equitable theories. It
further requested a declaration that it was not required to arbitrate its claims against
Austin. HCAA is not a party to the lawsuit. The gravamen of Mims's lawsuit is that
Austin did not pay Mims for the services it had provided after it received full payment for
the project from HCAA. Mims further alleged that Austin did not employ Mims for all
services for the project it had promised to Mims. Austin subsequently filed an amended
motion to stay and compel arbitration of the claims.
During the hearing on the motion, Austin argued that Mims agreed to
arbitrate the dispute because "the dispute resolution provision [in the Consultant
Agreement] says if the owner is not involved in the dispute, you don't go to their dispute
resolution procedure, but instead do arbitration." The trial court, however, construed the
arbitration clause contained in the Consultant Agreement—and incorporated by
reference into the Work Order for Part 2—to deny Austin's motion to compel arbitration.
The trial court reasoned that because the prime contract between HCAA and Austin
-3- contained a dispute resolution provision providing for litigation of disputes, Austin and
Mims were required to litigate their dispute. Austin appeals, arguing that the trial court
erred in its interpretation of the Consultant Agreement's dispute resolution provision.
Because the trial court's order denying the motion to compel arbitration is
based entirely on its construction of the contract documents, our standard of review is
de novo. SCG Harbourwood, LLC v. Hanyan, 93 So. 3d 1197, 1199 (Fla. 2d DCA
2012). In ruling on a motion to compel arbitration of a given dispute, courts must
consider three elements: "(1) whether a valid written agreement to arbitrate exists; (2)
whether an arbitrable issue exists; and (3) whether the right to arbitration was waived."
Seifert v. U.S. Home Corp., 750 So. 2d 633, 636 (Fla. 1999). Here, the only element in
dispute is whether the parties executed a valid written agreement to arbitrate their
claims.
As an initial matter, we reject Mims's argument that it did not enter into a
subcontract with Austin for Part 2 of the project. The trial court necessarily determined
that there was a valid contract for Part 2 of the project. That is, the trial court relied on
language incorporated into the Work Order, the agreement between Austin and Mims
for Part 2 of the project, in denying Austin's motion despite Mims's argument at the
hearing that the parties did not enter into a contract for Part 2. If the parties never
entered into a valid contract, there would have been no need for the trial court to
interpret and apply the arbitration clause. Thus, necessary and implicit to its ruling that
the agreement between Austin and Mims did not compel arbitration is a finding that the
parties did indeed execute a valid subcontract for Part 2.
-4- "It is a generally accepted rule of contract law that, where a writing
expressly refers to and sufficiently describes another document, that other document, or
so much of it as is referred to, is to be interpreted as part of the writing." OBS Co. v.
Pace Const. Corp., 558 So. 2d 404, 406 (Fla. 1990). With this in mind, we hold the
existence of a subcontract between Austin and Mims for Part 2 is supported by the
language of and attachments to the Work Order. The Work Order, which incorporated
Part 1's Consultant Agreement, contained the phrase "MIMS PART 2" on the top of
every page. The Work Order is signed by representatives of both Austin and Mims.
Under a section labeled "SCOPE OF WORK," Austin and Mims agreed that "[t]he Work
covered by this Work Order will be performed under the terms and conditions of the Part
1 Consultant Agreement." (Emphasis added.) The parties further agreed that "[t]he
Scope of Sublet Work shall be also defined by the Part 2 Contract Documents as
contained in the Exhibits listed below and attached hereto by reference, the Austin Part
2 Contract with attachments and Part 2 Supplemental Agreement with attachments as if
attached hereto." Exhibit A of the Work Order, consistent with the Memorandum of
Understanding appended to the Consultant Agreement, expanded the scope of Mims's
services by adding, among other positions, an Assistant Superintendent and Project
Engineer to facilitate Part 2 of the project.
Accordingly, an examination of the Work Order and its included
attachments confirms that the Work Order served as the subcontract for Mims's work on
the construction phase of the project. See OBS Co., 558 So. 2d at 406. Because the
Work Order served as the subcontract between Austin and Mims for the construction
phase of the project, their dispute arising from Mims's work on that phase is governed
-5- by the Consultant Agreement's dispute resolution provision incorporated into the Work
Order. See Henderson Inv. Corp. v. Int'l Fid. Ins. Co., 575 So. 2d 770, 771-72 (Fla. 5th
DCA 1991) (holding that surety could compel arbitration where it had incorporated an
arbitration clause from the construction contract into its performance bond).
Concluding that Austin and Mims executed a valid subcontract for the
construction phase of the project, we next address whether they agreed to arbitrate their
claims. The Consultant Agreement's dispute resolution provision incorporated into the
contract provides in relevant part:
Any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be subject to the dispute resolution procedures, if any, set out in the Prime Contract between Austin and the [HCAA]. Should the Prime Contract contain no specific requirement for the resolution of disputes or should the [HCAA] not be involved in the dispute, any such controversy or claim shall be resolved by arbitration . . . .
Austin argues that the provision provides for two exceptions to the
applicability of the prime contract's dispute resolution provision but the trial court's
reasoning only addressed one of the exceptions; namely, that the prime contract
"contain[ed] no specific requirement for the resolution of disputes." Mims does not
appear to defend or advance the trial court's ruling that because the prime contract
between HCAA and Austin contained a dispute resolution provision, Mims was not
compelled to arbitrate its claims against Austin. Instead, Mims advances a tipsy-
coachman argument that the Consultant Agreement's dispute resolution provision is
inapplicable because HCAA is "involved" in its dispute with Austin. We disagree with
Mims's contention.
-6- We are mindful that Florida public policy favors arbitration of disputes and
thus "courts should resolve doubts concerning the scope of such agreements in favor of
arbitration." Stinson-Head, Inc. v. City of Sanibel, 661 So. 2d 119, 120 (Fla. 2d DCA
1995). That said, the "determination of whether an arbitration clause requires arbitration
of a particular dispute necessarily 'rests on the intent of the parties.' " MDC 6, LLC v.
NRG Inv. Partners, LLC, 93 So. 3d 1145, 1147 (Fla. 2d DCA 2012) (quoting Seifert, 750
So. 2d at 636). To ascertain the parties' intent, we examine the plain language of the
contract. Id.; see also Bioscience W., Inc. v. Gulfstream Prop. & Cas. Ins. Co., 185 So.
3d 638, 640 (Fla. 2d DCA 2016) (explaining that we are bound by the plain meaning of
a contract's text when interpreting a contract). We construe a contract, "including the
arbitration and the limitation provisions, in a way that gives a reasonable meaning to all
the terms, rather than in a way that will render part of the contract of no effect." Orkin
Exterminating Co. v. Petsch, 872 So. 2d 259, 263 (Fla. 2d DCA 2004).
Turning to the trial court's interpretation of the Consultant Agreement's
arbitration provision, the trial court found that the mere existence of a dispute resolution
provision within the prime contract rendered the Consultant Agreement's arbitration
mandate inapplicable. The trial court's interpretation of the Consultant Agreement's
dispute resolution provision does not give a reasonable meaning to its incorporated
terms from the prime contract; namely, the applicability of the prime contract's dispute
resolution provision. The unambiguous language of the Consultant Agreement's
dispute resolution provision provides for two exceptions to the applicability of the
dispute resolution procedures set out in the prime contract: (1) the prime contract
"contain[s] no specific requirement for the resolution of disputes," or (2) the HCAA is not
-7- "involved in the dispute." If either of these two circumstances exists, the dispute "shall
be resolved by arbitration." As will be explained, the trial court's finding that the mere
existence of a dispute resolution provision within the prime contract, which does not
have bearing on the lawsuit initiated by Mims here, requires litigation of the dispute
between Mims and Austin belies the plain and ordinary language of the prime contract's
dispute resolution provision.
The prime contract, governing Austin and HCAA, requires litigation of
disputes that are "initiated by either party." (Emphasis added.) Thus, if Austin or HCAA
initiates "[a]ny action," "the exclusive venue" of that action is "the appropriate State
Court in and for Hillsborough County, Florida." Reading the dispute resolution provision
of the prime contract together with the dispute resolution provision of the Consultant
Agreement, as we must, leads us to the conclusion that the trial court's finding that the
mere existence of a dispute resolution provision within the prime contract mandated
litigation of Mims's and Austin's dispute was erroneous. This is because the prime
contract's dispute resolution provision is wholly inapplicable to Mims's and Austin's
dispute, as neither HCAA nor Austin initiated the lawsuit at issue here. To hold
otherwise effectively contravenes the plain and ordinary language of the prime
contract's dispute resolution provision, which is only applicable to lawsuits initiated by
HCAA or Austin. Cf. Bioscience W., 185 So. 3d at 640 (instructing courts to construe
contracts as a whole to give meaning to every provision). Because Mims initiated the
underlying action against Austin, the dispute resolution provision found in the prime
contract is inapplicable to the dispute between Mims and Austin.
-8- Turning to the second exception to mandatory arbitration set forth in the
Consultant Agreement, we must decide whether HCAA is "involved" in the lawsuit Mims
initiated against Austin. Mims argues that it qualifies for this exception to the arbitration
mandate because HCAA is "involved" in its dispute with Austin. Mims asserts that even
though it did not name HCAA as a party to the lawsuit, HCAA is nonetheless involved in
the dispute because of HCAA's status as a third-party beneficiary of the subcontract.1
We disagree.
First, such a broad interpretation of the term "involved" would render the
exception superfluous because HCAA, according to the prime contracts, is a third-party
beneficiary to "all agreements, subcontracts and purchase orders of [Austin]."
(Emphasis added.) See Universal Prop. & Cas. Ins. Co. v. Johnson, 114 So. 3d 1031,
1036 (Fla. 1st DCA 2013) ("A contract is not to be read so as to make one section
superfluous, and so '[a]ll the various provisions of a contract must be so construed . . .
as to give effect to each.' " (alteration in original) (quoting Univ. of Miami v. Frank, 920
So. 2d 81, 87 (Fla. 3d DCA 2006))).
Next, Mims's proposed, broad interpretation of "involved" invites an
interpretation contrary to its plain and ordinary meaning. "Involve" is defined, in
pertinent part, as "[t]o relate to or affect" or "[t]o show to be a participant; connect or
implicate." American Heritage Dictionary, 923 (5th ed. 2018); see also Bioscience, 185
So. 3d at 640 (explaining that we may consult dictionaries to discern the plain meaning
of contractual language); State v. Elder, 975 So. 2d 481, 483-84 (Fla. 2d DCA 2007)
1The prime contracts between Austin and the HCAA provide that "[HCAA] will be identified as an intended third party beneficiary of all agreements, subcontracts and purchase orders of [Austin] related to this Agreement."
-9- (" 'Involve' is defined, in pertinent part, as 'to draw in as a participant,' to 'implicate,' 'to
relate closely,' to 'connect,' 'to have an effect on,' to 'concern directly,' to 'affect.' "
(quoting Webster's Third New International Dictionary 1191 (1986))).
Applying these definitions, HCAA is clearly not "drawn in as a participant"
to the lawsuit because it is not a party to the lawsuit and, as such, need not participate
in it. Indeed, the allegations of Mims's operative complaint show that HCAA has paid
Austin "in full for all work performed on the TIA Project." Thus, whether Mims is paid by
Austin does not affect HCAA. The financial dispute Mims has initiated against Austin is
solely between those two parties and does not "involve" HCAA.
Furthermore, one would not ordinarily understand an entity to be
"involved" in a dispute where that entity is neither drawn into the dispute nor affected by
the dispute. Only an impermissible, strained textual interpretation of "involved in the
dispute" would yield a conclusion that HCAA would be affected by a financial dispute
between Austin and Mims. Cf. Bioscience, 185 So. 3d at 641 (explaining that the trial
court's interpretation of a contractual provision was contrary to the contractual
language's plain meaning). Accordingly, supported by the allegations in Mims's
complaint, it is difficult to discern that Mims's dispute with Austin affects or implicates
HCAA.2 See Elder, 975 So. 2d at 483-84. Because HCAA is not "involved" in Mims's
lawsuit initiated against Austin, it does not meet the second exception to the Consultant
Agreement's mandatory arbitration provision. Thus, reading all contractual provisions
as a whole, Mims's dispute with Austin "shall be resolved by arbitration," as provided by
2Thisinterpretation was also favored by the trial court. In its discussion with the parties during the hearing, the court commented that "the owner's not involved [in the dispute]."
- 10 - the dispute resolution provision found in the Consultant Agreement and incorporated
into Austin and Mims's Work Order.
Accordingly, we reverse the trial court's order denying Austin's motion to
compel arbitration and remand for entry of an order granting its motion and referring the
dispute to arbitration. See Orkin, 872 So. 2d at 266.
Reversed; remanded with instructions.
CASANUEVA and ROTHSTEIN-YOUAKIM, JJ., Concur.
- 11 -