AUSTIN COMMERCIAL, L. P. v. L. M. C. C. SPECIALITY CONTRACTORS, INC.

268 So. 3d 215
CourtDistrict Court of Appeal of Florida
DecidedApril 10, 2019
Docket18-1051
StatusPublished
Cited by3 cases

This text of 268 So. 3d 215 (AUSTIN COMMERCIAL, L. P. v. L. M. C. C. SPECIALITY CONTRACTORS, INC.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AUSTIN COMMERCIAL, L. P. v. L. M. C. C. SPECIALITY CONTRACTORS, INC., 268 So. 3d 215 (Fla. Ct. App. 2019).

Opinion

NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED

IN THE DISTRICT COURT OF APPEAL OF FLORIDA SECOND DISTRICT

AUSTIN COMMERCIAL, L.P., a ) Delaware limited partnership, ) ) Appellant, ) ) v. ) Case No. 2D18-1051 ) L.M.C.C. SPECIALTY CONTRACTORS, ) INC., d/b/a MIMS CONSTRUCTION ) COMPANY, a Florida corporation, ) ) Appellee. ) ___________________________________)

Opinion filed April 10, 2019.

Appeal from the Circuit Court for Hillsborough County; Paul L. Huey, Judge.

Aaron H. Reichelson, Marie Tomassi, and Patrick J. Poff of Trenam, Kemker, Scharf, Barkin, Frye, O'Neill & Mullis, P.A., Tampa, for Appellant.

Douglas A. Wallace and Joseph T. Eagleton of Brannock & Humphries, Tampa; and Derin Parks of Grimes Goebel Grimes Hawkins Gladfelter & Galvano, P.L., Bradenton, for Appellee.

BADALAMENTI, Judge.

Austin Commercial, L.P. (Austin) appeals from a nonfinal order denying its

motion to compel arbitration of its dispute with L.M.C.C. Specialty Contractors, Inc.,

d/b/a Mims Construction Company (Mims). We hold that Austin and Mims entered into a valid contract mandating arbitration of the underlying lawsuit initiated by Mims. We

thus reverse the trial court's order denying Austin's motion to compel arbitration and

remand for entry of an order granting Austin's motion to compel arbitration.

The Hillsborough County Aviation Authority (HCAA) awarded a contract to

Austin for construction of a consolidated rental car facility and automated people mover

at the Tampa International Airport. The project proceeded in two parts: the design

phase (Part 1) and the construction phase (Part 2). Mims served as one of Austin's

subcontractors on both phases of the project. For each of the two phases, Austin

entered into a contract with the HCAA (the prime contracts). The prime contracts state

that any action initiated by either party, HCAA or Austin, would be resolved in state

court as follows: "Any action initiated by either party associated with a claim or dispute,

and the exclusive venue and jurisdiction for any such action, will be brought in the

appropriate State Court in and for Hillsborough County, Florida."

After entering into the prime contract for Part 1 with HCAA, Austin

executed a "Consultant Agreement" with Mims that served as Austin and Mims's

subcontract for the design phase. Section 19.1 of the subcontract between Austin and

Mims contained the following provision:

Any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be subject to the dispute resolution procedures, if any, set out in the Prime Contract between Austin and the [HCAA]. Should the Prime Contract contain no specific requirement for the resolution of disputes or should the [HCAA] not be involved in the dispute, any such controversy or claim shall be resolved by arbitration pursuant to the Construction Industry Rules of the American Arbitration Association then prevailing, and judgment upon the award by the Arbitrator(s) shall be entered in any Court having jurisdiction thereof.

-2- Austin subsequently executed the "Part 2 Contract" with HCAA governing

the construction phase of the project. Thereafter, and consistent with a Memorandum

of Understanding between Austin and Mims attached to the Consultant Agreement,

Austin executed a Work Order with Mims that extended Mims's work on the airport

project to the second phase of the project. The Work Order incorporated the terms and

conditions of the Consultant Agreement (including the dispute resolution provision) and

served as Austin and Mims's subcontract for the construction phase.

After Mims completed its construction work for Part 2 of the project, Mims

filed an amended complaint in Hillsborough County state court for, among other things,

breach of contract against Austin under quasi-contractual and equitable theories. It

further requested a declaration that it was not required to arbitrate its claims against

Austin. HCAA is not a party to the lawsuit. The gravamen of Mims's lawsuit is that

Austin did not pay Mims for the services it had provided after it received full payment for

the project from HCAA. Mims further alleged that Austin did not employ Mims for all

services for the project it had promised to Mims. Austin subsequently filed an amended

motion to stay and compel arbitration of the claims.

During the hearing on the motion, Austin argued that Mims agreed to

arbitrate the dispute because "the dispute resolution provision [in the Consultant

Agreement] says if the owner is not involved in the dispute, you don't go to their dispute

resolution procedure, but instead do arbitration." The trial court, however, construed the

arbitration clause contained in the Consultant Agreement—and incorporated by

reference into the Work Order for Part 2—to deny Austin's motion to compel arbitration.

The trial court reasoned that because the prime contract between HCAA and Austin

-3- contained a dispute resolution provision providing for litigation of disputes, Austin and

Mims were required to litigate their dispute. Austin appeals, arguing that the trial court

erred in its interpretation of the Consultant Agreement's dispute resolution provision.

Because the trial court's order denying the motion to compel arbitration is

based entirely on its construction of the contract documents, our standard of review is

de novo. SCG Harbourwood, LLC v. Hanyan, 93 So. 3d 1197, 1199 (Fla. 2d DCA

2012). In ruling on a motion to compel arbitration of a given dispute, courts must

consider three elements: "(1) whether a valid written agreement to arbitrate exists; (2)

whether an arbitrable issue exists; and (3) whether the right to arbitration was waived."

Seifert v. U.S. Home Corp., 750 So. 2d 633, 636 (Fla. 1999). Here, the only element in

dispute is whether the parties executed a valid written agreement to arbitrate their

claims.

As an initial matter, we reject Mims's argument that it did not enter into a

subcontract with Austin for Part 2 of the project. The trial court necessarily determined

that there was a valid contract for Part 2 of the project. That is, the trial court relied on

language incorporated into the Work Order, the agreement between Austin and Mims

for Part 2 of the project, in denying Austin's motion despite Mims's argument at the

hearing that the parties did not enter into a contract for Part 2. If the parties never

entered into a valid contract, there would have been no need for the trial court to

interpret and apply the arbitration clause. Thus, necessary and implicit to its ruling that

the agreement between Austin and Mims did not compel arbitration is a finding that the

parties did indeed execute a valid subcontract for Part 2.

-4- "It is a generally accepted rule of contract law that, where a writing

expressly refers to and sufficiently describes another document, that other document, or

so much of it as is referred to, is to be interpreted as part of the writing." OBS Co. v.

Pace Const. Corp., 558 So. 2d 404, 406 (Fla. 1990). With this in mind, we hold the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
268 So. 3d 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-commercial-l-p-v-l-m-c-c-speciality-contractors-inc-fladistctapp-2019.