Austin Building Co. v. Rago, Ltd.

63 So. 3d 31, 2011 Fla. App. LEXIS 5974
CourtDistrict Court of Appeal of Florida
DecidedApril 27, 2011
Docket3D09-2430, 3D09-2481, 3D09-3238, 3D09-3244
StatusPublished
Cited by1 cases

This text of 63 So. 3d 31 (Austin Building Co. v. Rago, Ltd.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Austin Building Co. v. Rago, Ltd., 63 So. 3d 31, 2011 Fla. App. LEXIS 5974 (Fla. Ct. App. 2011).

Opinion

CORTIÑAS, J.

I. Factual Background

Austin Commercial, L.P. (“ACLP”) and Merrick Trust, LLC (the “Owner”) entered into a contract (the “Prime Contract”) for the construction of a mixed-use commercial and luxury residential condo *33 minium in Coral Gables, Florida (the “Project”). At the time the Prime Contract was executed on March 29, 2005, ACLP was qualified under section 489.119(2), Florida Statutes, to perform construction. The Prime Contract specifically provided that once ACLP’s affiliate, Austin Building Company (“ABC”), obtained state licensing, the Prime Contract and all related documents would be assigned from ACLP to ABC.

After the execution of the Prime Contract, ACLP engaged Rago, Ltd. (“Rago”) to construct the structural concrete components. Rago mobilized to the Project site on March 31, 2005 and commenced work on or about April 4, 2005. ACLP did not learn that Rago was unlicensed until approximately sixteen days after work had commenced. Upon discovering Rago’s unlicensed status, a representative of ACLP confronted Rago and was reassured that Rago would obtain licensure. Approximately four months after the work on the Project commenced, ABC obtained state licensing and formally executed a contract with Rago (the “Subcontract”). Although executed in July 2005, on its face, the Subcontract showed April 1, 2005 as the date of execution. Eventually, ABC terminated Rago after apparent dissatisfaction with delays and defects in its performance. In February 2007, Rago sued ABC, ACLP, and their surety, Federal Insurance Company (“Federal”) for amounts purportedly owed under the Subcontract. ABC, in turn, countersued Rago for damages arising from Rago’s purportedly defective work on the Project and filed a third party complaint against Federal, which was also serving as Rago’s surety. Rago and ABC filed opposing motions for summary judgment, each asserting that the other was an unlicensed contractor under section 489.128, Florida Statutes, and therefore, could not enforce the Subcontract. 1 The trial court granted the motions for summary judgment and entered final judgments as to Federal. This appeal followed.

II. ABC’s Appeal

ABC appeals a final summary judgment in its action against Rago. Our review of the record demonstrates the existence of genuine issues of material fact precluding summary judgment. Accordingly, we reverse.

When the record demonstrates the existence of disputed, material issues of fact, summary judgment is erroneous. Volusia Cnty. v. Aberdeen at Ormond Beach, L.P., 760 So.2d 126 (Fla.2000); Rakusin Law Firm v. Estate of Dennis, 27 So.3d 166 (Fla. 3d DCA 2010); Copeland v. Fla. New Invs. Corp., 905 So.2d 979, 980 (Fla. 3d DCA 2005). “[0]n review of an order granting summary judgment, we are required to review the record de novo and construe all facts in a fashion most favorable to the non-movant.” Ortega v. Eng’g Sys. Tech., Inc., 30 So.3d 525, 527, 530 (Fla. 3d DCA 2010); Interested Underwriters v. SeaFreight Line, Ltd., 971 So.2d 892, 894 (Fla. 3d DCA 2007). In this case, the facts surrounding the assignment of the Prime Contract to ABC, the identity of the actual contractor when work commenced on the Project and when work was performed by Rago, and the parties’ knowledge of each other’s lack of licensure, were disputed, and when viewed in the light most favorable to ABC, present genuine issues of material fact sufficient to preclude summary judgment.

*34 Section 489.128, Florida Statutes (2005) provides:

(1) As a matter of public policy, contracts entered into on or after October 1, 1990, by an unlicensed contractor shall be unenforceable in law or in equity by the unlicensed contractor.
(c) For purposes of this section, a contractor shall be considered unlicensed only if the contractor was unlicensed on the effective date of the original contract for the work, if stated therein, or, if not stated, the date the last party to the contract executed it, if stated therein. If the contract does not establish such a date, the contractor shall be considered unlicensed only if the contractor was unlicensed on the first date upon which the contractor provided labor, services, or materials under the contract.

§ 489.128(l)(c), Fla. Stat. (2005) (emphasis added). Under the statute, the critical dates for determining whether a contractor was unlicensed are 1) the effective date of the original contract, 2) the date the last party to the contract executed it, or 3) the first date upon which the contractor provided services, labor, or materials under the contract. Here, ABC presented evidence that, when viewed in the light most favorable to it, demonstrates that when Rago first began working on the Project, ACLP was the contractor and was properly licensed.

Moreover, while the Subcontract specifically lists ABC as the “Contractor,” Paragraph 1 of the Subcontract provides as follows:

1. The “Prime Contract” is the Contract between the Owner and the Contractor. The construction called for in the Prime Contract is called the “Work.” The term “Prime Contract” includes the Plans, Specifications, General and Special Condition, Addenda, and all other contract documents that are incorporated into this [Subcontract] by its terms. Each Party to this [Subcontract] acknowledges that it is familiar with the terms of the Prime Contract, and agrees that the Prime Contract (including the contract documents incorporated herein) is incorporated herein in its entirety for all purposes as if copied at length and attached hereto.... In the event of a discrepancy between the Prime Contract and this [Subcontract], this [Subcontract] will govern.

(Emphasis added). Although ABC is listed as the contractor, it is undisputed that the Prime Contract was between the Owner and ACLP, as contractor, and was fully incorporated into the Subcontract. It is also undisputed that ACLP was licensed at the time it entered into the Prime Contract. Furthermore, there is record evidence that, in early April 2005, Rago corresponded directly with ACLP, as the apparent contractor, providing an update on its delivery of materials to the jobsite and test reports for approval to begin construction. Under the terms of the Prime Contract, ABC could not have acted as contractor on the Project until such time as it was licensed. Taken in the light most favorable to ABC, Rago’s correspondence with ACLP as well as the language of the Prime Contract and the Subcontract, create a genuine issue of fact as to who was the “contractor” on the Project as of April 1, 2005.

Because the evidence in the record, when viewed in the light most favorable to ABC, shows the existence of genuine issues of material fact, we reverse the entry of summary judgment as to ABC. 2 Ac *35 cordingly, we also reverse the final judgment in favor of Federal as Rago’s surety.

III. Rago’s Cross-Appeal

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Earth Trades, Inc. v. T & G Corp.
108 So. 3d 580 (Supreme Court of Florida, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
63 So. 3d 31, 2011 Fla. App. LEXIS 5974, Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-building-co-v-rago-ltd-fladistctapp-2011.