Aurora Technology v. Labedz

30 Neb. Ct. App. 33, 964 N.W.2d 474
CourtNebraska Court of Appeals
DecidedJune 29, 2021
DocketA-20-846
StatusPublished
Cited by1 cases

This text of 30 Neb. Ct. App. 33 (Aurora Technology v. Labedz) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aurora Technology v. Labedz, 30 Neb. Ct. App. 33, 964 N.W.2d 474 (Neb. Ct. App. 2021).

Opinion

Nebraska Supreme Court Online Library www.nebraska.gov/apps-courts-epub/ 07/13/2021 08:08 AM CDT

- 33 - Nebraska Court of Appeals Advance Sheets 30 Nebraska Appellate Reports AURORA TECHNOLOGY v. LABEDZ Cite as 30 Neb. App. 33

Aurora Technology, Inc., appellant, v. Frank Labedz and Sherri Labedz, appellees. ___ N.W.2d ___

Filed June 29, 2021. No. A-20-846.

1. Summary Judgment: Appeal and Error. An appellate court will affirm a lower court’s grant of summary judgment if the pleadings and admit- ted evidence show that there is no genuine issue as to any material facts or as to the ultimate inferences that may be drawn from the facts and that the moving party is entitled to judgment as a matter of law. 2. ____: ____. In reviewing a summary judgment, an appellate court views the evidence in the light most favorable to the party against whom the judgment was granted, and gives that party the benefit of all reasonable inferences deducible from the evidence. 3. Limitations of Actions. Which statute of limitations applies is a ques- tion of law. 4. Judgments: Appeal and Error. An appellate court reaches a con- clusion regarding questions of law independently of the trial court’s conclusion. 5. Contracts: Proof: Limitations of Actions. A contract is unwritten if it cannot be wholly proved by a writing or writings. If the contract is partly oral and partly written or if a written agreement is so indefinite as to necessitate a resort to parol testimony to make it complete, the statute of limitations concerning contracts not in writing would be applicable just as though the contract had rested entirely in parol. 6. Contracts. Parol acceptance of an offer in writing does not give rise to an agreement or contract in writing within the purview of Neb. Rev. Stat. § 25-205 (Reissue 2016). 7. Summary Judgment. In the summary judgment context, a fact is mate- rial only if it would affect the outcome of the case. - 34 - Nebraska Court of Appeals Advance Sheets 30 Nebraska Appellate Reports AURORA TECHNOLOGY v. LABEDZ Cite as 30 Neb. App. 33

Appeal from the District Court for Douglas County: Timothy P. Burns, Judge. Affirmed. Kathryn J. Derr, of Berkshire & Burmeister, for appellant.

Craig Martin and Daniel J. Hassing, of Lamson, Dugan & Murray, L.L.P., for appellees.

Riedmann, Arterburn, and Welch, Judges.

Riedmann, Judge. INTRODUCTION Aurora Technology, Inc. (Aurora), appeals the order of the district court for Douglas County granting summary judgment in favor of Frank Labedz and Sherri Labedz (collectively Labedz) on the basis that the 4-year statute of limitations for oral contracts barred Aurora’s breach of contract and unjust enrichment claims. We find that the district court did not err in its decision and therefore affirm.

BACKGROUND Aurora is a Nebraska corporation formed in 2004. In late 2011, Labedz began communicating with Aurora for the pur- pose of having Aurora install an “intelligent home system” in Labedz’ condominium. On March 19, 2012, Aurora and Labedz signed a contract. Under the heading “Scope of Contract,” the document states that Aurora will “provide the design, equip- ment, and labor required to complete [the] project to the specifications & descriptions agreed upon in the documents, attached hereto and incorporated herein.” The contract does not contain any further details outlining the work Aurora agreed to complete for Labedz nor does it include any costs associated with the work. There were no documents attached to the con- tract or specifically incorporated into it. The contract also includes a section regarding change orders, describing that a change order is “work that is added - 35 - Nebraska Court of Appeals Advance Sheets 30 Nebraska Appellate Reports AURORA TECHNOLOGY v. LABEDZ Cite as 30 Neb. App. 33

to or deleted from the original scope of work of a contract, which alters the original contract amount or completion date.” The contract also provides that all change orders will be “writ- ten or electronic” and that verbal change requests will not be acted upon without written or electronic documentation. There were no change orders completed on this project. Christopher Tyler is the president of Aurora. At Tyler’s deposition, he described the written contract as the “begin- ning contract, the initial contract” and testified that it partially controlled the relationship between Aurora and Labedz but that there were also “a lot of oral discussions” between the parties throughout the duration of the project. Tyler explained that his purpose in drafting the contract was to give Aurora and Labedz “a starting point of what may be done.” According to Tyler, at the time the parties signed the contract, he also provided Labedz with a proposal for the equipment and labor involved for lighting work and for win- dow shade work. Neither of these proposals, which are both dated March 19, 2012, is signed by either party. The total ­projected cost for the work contained in these two proposals was $29,972.71. The record also includes five proposals dated June 11, 2012; one proposal dated July 27, 2012; and two proposals dated October 15, 2014, that Aurora created for vari- ous aspects of the Labedz project. Tyler testified that Labedz approved some of these proposals, modified some of them, and rejected some of them. Tyler was unable to recall if he ever presented one of the June proposals to Labedz. At Frank’s deposition, he was asked whether, over time, he received cer- tain written proposals from Aurora. He recalled “getting a set of documents in conjunction with the contract” that detailed certain work. Tyler explained that, generally speaking, he would usu- ally communicate with his clients via verbal discussions and receive verbal approval for certain work. With respect to Labedz, Tyler acknowledged that a lot of the work he did for - 36 - Nebraska Court of Appeals Advance Sheets 30 Nebraska Appellate Reports AURORA TECHNOLOGY v. LABEDZ Cite as 30 Neb. App. 33

this project was done pursuant to an oral acceptance from Labedz. He described numerous parts of the project that were done pursuant to oral agreements between Aurora and Labedz, including, for example, installation of a curved television, set- ting up cable products and services, troubleshooting certain issues, unloading a mirror, “fish[ing] wires” for an office tele- vision, and moving and installing “therm/HVAC.” Throughout the project, Aurora periodically requested pay- ments, and Labedz generally made payments as requested. In total, Labedz paid more than $200,000 to Aurora. Ultimately, Aurora submitted invoices to Labedz indicating that there was a total remaining unpaid balance of $125,232.10. Labedz declined to pay the remaining balance, and the parties agree that their relationship terminated by February 13, 2015. On May 1, 2019, Aurora filed a complaint in the district court against Labedz alleging breach of contract and unjust enrichment. Labedz filed an answer and asserted, as an affirmative defense, that Aurora’s claims were barred by the statute of limitations. Labedz thereafter filed a motion for sum- mary judgment. After holding a hearing on the motion, the district court entered a written order. The court recognized that the parties agree that Aurora’s claims accrued no later than February 13, 2015, and that the action was commenced on May 1, 2019, which is more than 4 years but less than 5 years after the par- ties’ relationship ended; therefore, the question of whether Aurora’s claims were barred by the statute of limitations depends upon which statute applies. Neb. Rev. Stat. § 25-206

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
30 Neb. Ct. App. 33, 964 N.W.2d 474, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aurora-technology-v-labedz-nebctapp-2021.