AURORA PUMP, ETC. v. Goulds Pumps, Inc.

424 So. 2d 70
CourtDistrict Court of Appeal of Florida
DecidedDecember 14, 1982
DocketAO-212
StatusPublished
Cited by3 cases

This text of 424 So. 2d 70 (AURORA PUMP, ETC. v. Goulds Pumps, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AURORA PUMP, ETC. v. Goulds Pumps, Inc., 424 So. 2d 70 (Fla. Ct. App. 1982).

Opinion

424 So.2d 70 (1982)

AURORA PUMP, DIVISION OF GENERAL SIGNAL CORPORATION, a New York Corporation, Appellant,
v.
GOULDS PUMPS, INC., a Corporation and Jacksonville Electric Authority, a Body Politic and Corporate, Appellees.

No. AO-212.

District Court of Appeal of Florida, First District.

December 14, 1982.

*71 Charles T. Boyd, Jr., of Boyd, Jenerette, Leemis & Staas, P.A., Jacksonville, for appellant.

John B. Macdonald, of Franson, Brant, Dearing & Moore, Jacksonville, for appellee Goulds Pumps, Inc.

No appearance for appellee Jacksonville Elec. Authority.

WIGGINTON, Judge.

This appeal follows the final judgment of the lower court permanently enjoining Jacksonville Electric Authority (JEA) from entering into any contract for the work described as the St. Johns River Power Park General Centrifugal Pumps and arising out of its Invitation for Bids, and directing JEA, should it wish to proceed, to resubmit an invitation for bids with rules and regulations made equally applicable to all present and subsequent bidders. We affirm.

JEA promulgated and issued the Invitation for Bids and Instructions to Bidders in July, 1981, inviting bids for the manufacture of the general centrifugal pumps to be installed in the St. Johns River Power Park Units 1 and 2. Pursuant to the invitation, eligibility for bidding on the contract was limited to a list of seven pump manufacturers prequalified by JEA and included on JEA's "responsible bidder list." Bids were ultimately submitted by five bidders: appellee Goulds Pumps, Inc., appellant Aurora Pump, Worthington Pump Company, Allis-Chalmers Corporation, and Ingersole-Rand Corporation (whose bid was later declared non-responsive).

The bidding documents set forth the framework for a two-step bidding procedure. The instructions provided that the initial bids were to be submitted in two separate documents, a technical proposal and a cost proposal. As provided by paragraph M[1] of the instructions, the bidders' technical proposals would be opened first to permit evaluation of their content. Subsequent negotiations would then commence between JEA and each bidder regarding exceptions taken by the bidder to the technical and commercial terms of the proposed contract. During the evaluation and negotiation period the cost proposals would remain unopened. The Invitation for Bids further provided that bidders would be afforded an opportunity to submit plus and minus price adjustments to their still unopened cost proposals occasioned as a result of the negotiations on their exceptions to the technical and commercial terms of the proposed contract. Following the completion of technical evaluations and negotiations on the bidders' exceptions, the sealed cost proposals retained by JEA would then be opened, and the contract would be awarded to the lowest responsible bidder whose now opened cost proposal, plus or minus additions or deductions submitted in connection with the negotiations, offered the lowest fully evaluated cost for the contract.

The only published procedures and guidelines available to the bidders governing the manner by which bids were to be submitted, received, evaluated, or modified were contained in the Invitation for Bids and Instructions to Bidders, as supplemented by Ordinance 80-113-169 of the City of Jacksonville and JEA Procedure No. MD311. Although the invitation specified the date by which the initial technical and cost proposals were to be submitted, which as amended was September 29, 1981, neither it, the instructions, nor any other published material set forth the actual procedures utilized by JEA for conduct of the negotiations *72 regarding bidders' exceptions; methods by which the bidders could submit plus or minus price adjustments occasioned by those negotiations; or, most important, as we finally conclude, any deadline after which price adjustments could no longer be submitted. According to John Cole, JEA's project administrator responsible for the contract, the submission of price adjustments was governed by unwritten procedures based only on the customary practices of JEA.

Goulds, through one of its regional salesmen, Ernest Lary, prepared and submitted a bid before the initial "bid opening date" on September 29, 1981. At that time, Goulds' original cost proposal of $1,195,356 for Units 1 and 2 represented its most competitive price possible, considering the commercial terms of the contract initially proposed by JEA. Those initial terms required the bidders to be exposed to substantial financial risks should any one of them be awarded the contract. Although Goulds' initial cost proposal was computed assuming that the contract would be awarded on the terms proposed by JEA, in its technical proposal Goulds took exception to certain commercial contractual terms. Goulds' initial cost proposal included a cushion to compensate it for the financial risk it perceived those contractual terms would entail in the event Goulds was awarded the contract.

Subsequent to opening of the technical proposals on September 29, 1981, JEA's consulting engineers for the St. Johns River Power Park Project, Ebasco Services, Inc., commenced evaluation of the respective technical proposals and the bidders' exceptions to the original technical and commercial terms proposed by JEA. Negotiations between Ebasco and the respective bidders commenced informally in November, 1981, culminating in formal private negotiation meetings between JEA, Ebasco, and each respective bidder on December 15 through 17, 1981. As a result of communications with Ebasco, Goulds had resolved all of its exceptions to the technical specifications of the contract by the time of the formal meeting on December 16, 1981. However, its exceptions to the proposed commercial terms of the contract, which exceptions were included in the technical portion of the proposal, had not yet been resolved by that date.

Occasioned by the formal negotiations held on December 16, substantial changes to the proposed commercial terms of the contract were agreed upon by the parties, eliminating much of the previous financial risk to the ultimate contractor. Both JEA and Ebasco understood that as a result of the commercial changes Goulds was afforded an opportunity to assess the impact of such changes on its financial analysis of the proposed contract and to submit any resulting price modification to its cost proposal. Aurora, Allis-Chalmers, and Worthington all similarly understood that they were afforded the opportunity to submit price additions or deductions resulting from alteration of any commercial terms during their individual negotiations with JEA and Ebasco. However, Goulds interpreted the instructions to bidders, particularly paragraph J(1),[2] to provide for submission of price modifications so long as negotiations regarding the contract were continuing, but in any event before the cost proposals were opened.

The representatives of all bidders, including Goulds, knew that Ebasco would prepare a preliminary evaluation of the respective bids and transmit it to JEA. Computer projections based on the information contained in the preliminary evaluation would permit each bidder to estimate within a reasonable degree of certainty the amount of its competitors' respective cost proposals. Accordingly, JEA intended that all cost adjustments *73 were to be submitted no later than the date of the preliminary evaluation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fairview Properties v. Pate Const. Co.
638 So. 2d 998 (District Court of Appeal of Florida, 1994)
MID-AM WASTE SYSTEMS OF FLA., INC. v. City of Jacksonville
596 So. 2d 1187 (District Court of Appeal of Florida, 1992)
Caber Systems, Inc. v. Department of General Services
530 So. 2d 325 (District Court of Appeal of Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
424 So. 2d 70, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aurora-pump-etc-v-goulds-pumps-inc-fladistctapp-1982.