Aultman & Taylor MacHinery Co. v. Cappleman

81 S.W. 1243, 36 Tex. Civ. App. 523, 1904 Tex. App. LEXIS 279
CourtCourt of Appeals of Texas
DecidedJuly 1, 1904
StatusPublished
Cited by7 cases

This text of 81 S.W. 1243 (Aultman & Taylor MacHinery Co. v. Cappleman) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aultman & Taylor MacHinery Co. v. Cappleman, 81 S.W. 1243, 36 Tex. Civ. App. 523, 1904 Tex. App. LEXIS 279 (Tex. Ct. App. 1904).

Opinion

STEPHENS, Associate Justice.

The following case was made by the pleadings: Appellee purchased of appellant a steam thresher to be delivered to him at Jolly, Texas, by June 10, 1903, but which was not delivered till June 24, 1903. Besides guaranteeing the delivery by June 10, 1903, appellant warranted the capacity of the thresher to be 2000 bushels of wheat per day, and warranted that the machinery would be constructed of first-class material and in a first-class manner, and agreed to properly set up and train the thresher and to furnish feed boards and repairs free during the first year. For breaches of these covenants damages were claimed as follows: $500 to cover what could have been made during the fifteen days of delay; $700 to cover what could have been made if the thresher had had the capacity warranted; $725 to cover the difference in value of the thresher delivered and the one contracted for; and $65 to cover the lack of feed boards and repairs.

The answer was a general denial. The judgment in favor of appellee for $1000, from which this appeal is prosecuted, rests on a special ver *524 diet, finding the covenants to have made and broken substantially as alleged, and assessing the damages as follows: “32. Q: Is the plaintiff entitled to any damages by reason of the delay in the delivery of said machine on the 10th day of June, 1903, at Jolly, Texas, to plaintiff? Answer: Yes. 33. Q: What amount, if any, was plaintiff damaged by the delay of said machinery? Answer: $400. 34. Q: Is the plaintiff entitled to any damage by reason of the diminished capacity of said machine; if so, how much? Answer: Yes; $400. 35. Q: Is there any difference between the market value of the separator that was delivered to plaintiff and such separator as defendant agreed to deliver; if so, how much? Answer: Yes; $200. This amount is not considered a damage.”

In response to other special issues—there being forty-two in all—the jury made, among others, the following findings: On March 13, 1903, appellant’s agent, J. J. Cunningham, representing himself as the State agent, took from appellee a written order for the thresher in question, to be delivered about the 1st of May of that year, but it was not delivered under this order; on May 22, 1903, a verbal contract was made with said agent, which was “a separate and distinct sale,” for the delivery of said machine, “properly constructed and put together,” on June 10th, but it was not delivered until June 24th; Cunningham as agent for the appellant agreed to put “in good running order and properly test and train said machinery upon its arrival,” which was not done; Cunningham represented that said machinery had the capacity of threshing from 1500 to 2000 bushels of wheat per day, when it only had the capacity of threshing 1100 bushels; Cunningham was acting within the apparent scope of his authority when he made these representations, which were relied on by appellee; appellee had engaged grain to thresh for the season of 1903 and informed appellant’s said agent of this fact prior to the purchase of the thresher, which was operated forty-eight days during that season; appellee had a competent crew of men in charge of the machinery a part of the time and a part of the time he did not; he probably could not have obtained a competent machinist at that season of the year to train the machihery and put it in good running order; the thresher was operated at an expense of $50 per day, appellee charging toll at the rate of 10 cents per bushel for wheat and 6 cents per bushel for oats in the shock, and 6 cents for wheat and 3 cents for oats in the stack) the wheat averaging that year from fifteen to eighteen bushels and oats thirty bushels per acre.

Error is assigned to "the judgment on the following grounds, among others: First, because the special findings are “inconsistent, indefinite and uncertain, and do not support the judgment;” second, because the answers to questions 32, 33 and 34, quoted above, are mere legal conclusions of the jury and not findings of fact on which the court could render judgment; third, because the answer to the thirty-fourth question is uncertain and does not show what character of damages was intended to be included; fourth, “because the plaintiff having sued for and recov *525 ered the difference between the value of the machinery agreed to be delivered and the value of the machinery that was delivered, is not entitled to recover any further damages for the diminished capacity of said machinery;” fifth, because the verdict shows that the diminished capacity of the machinery in controversy was due in part, at least, to the incompetency of the crew which appellee had in charge of same.

As to tile contention urged under these assignments, and the eases cited to sustain it, that every fact necessary to support the judgment must appear in the special verdict, it is sufficient to say that this rule' was changed by the amendment of 1897, and that the cases cited arose prior thereto. Sayles’ Civ. Stats., art. 1331. This change in the law treats as harmless mere omissions in the verdict where the evidence supplies them, unless the party complaining requests the submission of issues so omitted, which was not done in this instance. However, the effect of this change must not be carried too far, and in construing the amended statute we must not lose sight of the mischief intended to be corrected by the amendment, as reflected in the decisions cited by appellant. For instance, it could hardly have been the purpose of the Legislature in amending this statute, so as to avoid reversals for mere omissions in the verdict of facts clearly proved, to authorize the court to assess unliquidated damages in a case tried by a jury. A verdict which does not in some way fix the amount of recovery in such case should perhaps not be treated as a verdict at all. But however this may be, we have reached the conclusion that the verdict in question is defective. It seems from the last sentence of their answer to the thirty-fifth question that the jury did not intend to include the item of $300 as a part of the damages assessed by them in addition to the other items, if at all, and yet it seems to be the established general rule in the law of damages to measure the loss in such cases by the difference in value between the machinery furnished and the machinery contracted for. The rule is thus stated and illustrated in Mechem on Sales, see. 817: “Where the article furnished by the seller is not such in kind, quality or condition as it was expressly or impliedly warranted to be, the direct and natural loss to the buyer who keeps it is obviously the difference between the value of an article of the kind he was thus entitled to receive and the value of the article which he has in fact received. For this loss he is entitled to compensation. There may, of course, be other losses resulting from the seller’s default, and these will be considered later; but the direct and immediate loss will be at least this difference in value. For the breach of warranty, then, as to kind, quality or condition, the measure of the buyer’s injury will be the difference between the value of the article of the kind warranted and the value of the article actually delivered; and for this difference the buyer may recover damages.” See.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Humble Oil & Refining Co. v. Pritchett
25 S.W.2d 909 (Court of Appeals of Texas, 1930)
Garlitz v. International-Great Northern Ry. Co.
11 S.W.2d 591 (Court of Appeals of Texas, 1928)
Pecos & N. T. Ry. Co. v. Railroad Commission
193 S.W. 770 (Court of Appeals of Texas, 1917)
Grand Prairie Gravel Co. v. Joe B. Wills Co.
188 S.W. 680 (Court of Appeals of Texas, 1916)
Southern Gas & Gasoline Engine Co. v. Adams
169 S.W. 1143 (Court of Appeals of Texas, 1914)
Naylor v. Parker
139 S.W. 93 (Court of Appeals of Texas, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
81 S.W. 1243, 36 Tex. Civ. App. 523, 1904 Tex. App. LEXIS 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aultman-taylor-machinery-co-v-cappleman-texapp-1904.