OPINION
SHWARTZ, Circuit Judge.
International Procurement and Contracting Group, LLC (“IPCG”) appeals from the District Court’s order granting summary judgment for Audubon Engineering Company, LLC and Audubon Engineering Solutions, LLC (collectively, “Audubon”) on Audubon’s breach of contract claim arising from IPCG’s failure to pay for services Audubon rendered. We will affirm.
I
IPCG is a U.S. headquartered company that connects U.S. suppliers of goods and services with “clients in the Middle East.” App. 273. Audubon is an American engi
neering firm. IPCG and Audubon entered into an agreement with each other to provide engineering design services to North Refineries Company (“NRC”) in connection with the construction of a liquefied petroleum gas (“LPG”) unit in Iraq (the “LPG Project”). IPCG filed suit against Audubon in the United States District Court for the Eastern District of Michigan, alleging that Audubon breached the agreement.
See
Compl.,
Int’l Procurement & Contracting Grp., LLC v. Audubon Eng’g Co., LLC,
No. 5:11-cv-14740 (E.D. Mich. Oct. 27, 2011), ECF No. 1.
IPCG and Audubon entered into a Settlement Agreement and Mutual Release (the “Agreement”) resolving that case, pursuant to which Audubon agreed to perform certain engineering and design services for the LPG Project. The Agreement makes clear that “[t]he payment terms, dates, and services to be performed [by Audubon]” are governed by a proposal (the “Proposal”) attached to the Agreement. App. 67. The Proposal sets forth a “Milestone Payment Schedule,” which includes three separate “Contracts,” each of which is divided into several “Milestones.” App. 90. Each Milestone includes a series of discrete tasks, the completion of which entitles Audubon to partial payment of its total fee.
IPCG awarded Audubon the first Contract described in the Proposal — “Contract # 1” — but reserved the right to deny Audubon subsequent Contracts. App. 67. Consistent with the terms of the Proposal, IPCG paid Audubon for completing “Milestone # 1,” which Audubon accomplished simply by obtaining Contract # 1. App. 90. The instant dispute relates to the second and third Milestones under Contract # 1, which required Audubon to furnish engineering drawings depicting the layout of the LPG unit’s piping, electrical wiring, and instrumentation, among other components (“Milestone # 2”), and to prepare “bid packages” to enable NRC to solicit bids from third-party vendors for construction materials and equipment (“Milestone # 3”). App. 90,163,464.
Audubon submitted a series of Milestone #2 drawings to IPCG. In response, and although not required by that Milestone, IPCG requested that Audubon provide “native,” or changeable, versions of the drawings, and modify the designs to include international rather than English-style units of measurement. App. 140. Audubon refused to provide IPCG with native versions, citing intellectual property concerns. For an additional fee, however, Audubon agreed to modify the designs to include international units of measurement, as memorialized in a “Change Order” signed by both parties. App. 164. After issuing the updated drawings, Audubon submitted an invoice to IPCG for Milestone #2, which IPCG paid in full a few weeks later.
Audubon then provided the Milestone # 3 bid packages to IPCG and submitted an invoice in the amount of $560,320.00 (the “Invoice”), reflecting its fee for the Change Order and Milestone # 3. IPCG indicated that it would not pay the Invoice until Audubon provided native versions of the Milestone # 2 drawings, as it had previously requested. Audubon agreed to provide the native versions if IPCG signed a liability release form that Audubon provided. IPCG never signed the release, Audubon did not provide the native drawings, and IPCG did not pay the Invoice.
Audubon filed suit against IPCG in the Delaware Superior Court for breach of contract, seeking payment of the Invoice plus interest and attorneys’ fees. After IPCG removed the case to the District Court and the parties completed discovery, Audubon moved for summary judgment. The District Court granted Audubon’s mo
tion, concluding that IPCG “raised no genuine dispute of material fact as to whether Audubon performed its obligations under the Agreement” and holding that IPCG breached its obligation to pay for Audubon’s services. App. 8. IPCG appeals.
II
The District Court correctly concluded that-there are no genuine disputes of material fact with respect to Audubon’s performance of the Change Order and Milestone # 3 and that IPCG breached its obligation to pay for these services. To begin, IPCG does not dispute that it authorized the Change Order and received updated drawings consistent with its terms. There is also no dispute that Audubon provided the Milestone #3 bid packages to IPCG, nor is there any. contemporaneous evidence that IPCG or NRC believed the bid packages to be incomplete.
IPCG maintains that there exists a genuine dispute of material fact with respect to Audubon’s performance of Milestone #3 notwithstanding this failure of proof, citing the deposition testimony of its former Chairman, Shakir Alkhafaji. Alk-hafaji, deposed two years after the fact, testified that “whatever Audubon gave [IPCG], NRC rejected it as incomplete.” App. 350. Alkhafaji also testified that “Audubon did not complete [its] work,” causing “NRC to reject it and ask for ... more documents.” App. 363. While this testimony suggests that IPCG and NRC were dissatisfied with Audubon’s work product, we agree with the District Court that, in context, it is clear Alkhafaji was referring to 'the production of the Milestone # 2 engineering drawings, for which IPCG paid Audubon in full, or other work unrelated to the Milestone #3 bid packages.
See
App. 349-50 (Alkhafaji discussing Audubon’s failure to provide “amine unit” designs and conceding that he is “not aware of engineering stuff’ immediately
before stating that NRC rejected Audubon’s work as incomplete), 363 (Alkhafaji stating that Audubon did not accomplish the “first milestone,” related to “engineering drawings,” before stating that Audubon did not complete its work). Because the relevant issue here is Audubon’s performance of the Change Order and Milestone # 3, Alkhafaji’s testimony does not create a genuine dispute of material fact concerning Audubon’s entitlement to payment for that work.
IPCG’s expert witness report also fails to present a genuine dispute of material fact. As the District Court correctly concluded, the report “falls well short of complying with the requirements of [Fed. R.Civ.P.] 26(a)(2)(B).” App. 7. Among its many deficiencies, the report fails to set forth the “facts or data considered by” IPCG’s expert in forming his opinions. Fed.R.Civ.P. 26(a)(2)(B)(ii). This is a material omission as it deprives Audubon of the means to determine the foundation for the opinion.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
SHWARTZ, Circuit Judge.
International Procurement and Contracting Group, LLC (“IPCG”) appeals from the District Court’s order granting summary judgment for Audubon Engineering Company, LLC and Audubon Engineering Solutions, LLC (collectively, “Audubon”) on Audubon’s breach of contract claim arising from IPCG’s failure to pay for services Audubon rendered. We will affirm.
I
IPCG is a U.S. headquartered company that connects U.S. suppliers of goods and services with “clients in the Middle East.” App. 273. Audubon is an American engi
neering firm. IPCG and Audubon entered into an agreement with each other to provide engineering design services to North Refineries Company (“NRC”) in connection with the construction of a liquefied petroleum gas (“LPG”) unit in Iraq (the “LPG Project”). IPCG filed suit against Audubon in the United States District Court for the Eastern District of Michigan, alleging that Audubon breached the agreement.
See
Compl.,
Int’l Procurement & Contracting Grp., LLC v. Audubon Eng’g Co., LLC,
No. 5:11-cv-14740 (E.D. Mich. Oct. 27, 2011), ECF No. 1.
IPCG and Audubon entered into a Settlement Agreement and Mutual Release (the “Agreement”) resolving that case, pursuant to which Audubon agreed to perform certain engineering and design services for the LPG Project. The Agreement makes clear that “[t]he payment terms, dates, and services to be performed [by Audubon]” are governed by a proposal (the “Proposal”) attached to the Agreement. App. 67. The Proposal sets forth a “Milestone Payment Schedule,” which includes three separate “Contracts,” each of which is divided into several “Milestones.” App. 90. Each Milestone includes a series of discrete tasks, the completion of which entitles Audubon to partial payment of its total fee.
IPCG awarded Audubon the first Contract described in the Proposal — “Contract # 1” — but reserved the right to deny Audubon subsequent Contracts. App. 67. Consistent with the terms of the Proposal, IPCG paid Audubon for completing “Milestone # 1,” which Audubon accomplished simply by obtaining Contract # 1. App. 90. The instant dispute relates to the second and third Milestones under Contract # 1, which required Audubon to furnish engineering drawings depicting the layout of the LPG unit’s piping, electrical wiring, and instrumentation, among other components (“Milestone # 2”), and to prepare “bid packages” to enable NRC to solicit bids from third-party vendors for construction materials and equipment (“Milestone # 3”). App. 90,163,464.
Audubon submitted a series of Milestone #2 drawings to IPCG. In response, and although not required by that Milestone, IPCG requested that Audubon provide “native,” or changeable, versions of the drawings, and modify the designs to include international rather than English-style units of measurement. App. 140. Audubon refused to provide IPCG with native versions, citing intellectual property concerns. For an additional fee, however, Audubon agreed to modify the designs to include international units of measurement, as memorialized in a “Change Order” signed by both parties. App. 164. After issuing the updated drawings, Audubon submitted an invoice to IPCG for Milestone #2, which IPCG paid in full a few weeks later.
Audubon then provided the Milestone # 3 bid packages to IPCG and submitted an invoice in the amount of $560,320.00 (the “Invoice”), reflecting its fee for the Change Order and Milestone # 3. IPCG indicated that it would not pay the Invoice until Audubon provided native versions of the Milestone # 2 drawings, as it had previously requested. Audubon agreed to provide the native versions if IPCG signed a liability release form that Audubon provided. IPCG never signed the release, Audubon did not provide the native drawings, and IPCG did not pay the Invoice.
Audubon filed suit against IPCG in the Delaware Superior Court for breach of contract, seeking payment of the Invoice plus interest and attorneys’ fees. After IPCG removed the case to the District Court and the parties completed discovery, Audubon moved for summary judgment. The District Court granted Audubon’s mo
tion, concluding that IPCG “raised no genuine dispute of material fact as to whether Audubon performed its obligations under the Agreement” and holding that IPCG breached its obligation to pay for Audubon’s services. App. 8. IPCG appeals.
II
The District Court correctly concluded that-there are no genuine disputes of material fact with respect to Audubon’s performance of the Change Order and Milestone # 3 and that IPCG breached its obligation to pay for these services. To begin, IPCG does not dispute that it authorized the Change Order and received updated drawings consistent with its terms. There is also no dispute that Audubon provided the Milestone #3 bid packages to IPCG, nor is there any. contemporaneous evidence that IPCG or NRC believed the bid packages to be incomplete.
IPCG maintains that there exists a genuine dispute of material fact with respect to Audubon’s performance of Milestone #3 notwithstanding this failure of proof, citing the deposition testimony of its former Chairman, Shakir Alkhafaji. Alk-hafaji, deposed two years after the fact, testified that “whatever Audubon gave [IPCG], NRC rejected it as incomplete.” App. 350. Alkhafaji also testified that “Audubon did not complete [its] work,” causing “NRC to reject it and ask for ... more documents.” App. 363. While this testimony suggests that IPCG and NRC were dissatisfied with Audubon’s work product, we agree with the District Court that, in context, it is clear Alkhafaji was referring to 'the production of the Milestone # 2 engineering drawings, for which IPCG paid Audubon in full, or other work unrelated to the Milestone #3 bid packages.
See
App. 349-50 (Alkhafaji discussing Audubon’s failure to provide “amine unit” designs and conceding that he is “not aware of engineering stuff’ immediately
before stating that NRC rejected Audubon’s work as incomplete), 363 (Alkhafaji stating that Audubon did not accomplish the “first milestone,” related to “engineering drawings,” before stating that Audubon did not complete its work). Because the relevant issue here is Audubon’s performance of the Change Order and Milestone # 3, Alkhafaji’s testimony does not create a genuine dispute of material fact concerning Audubon’s entitlement to payment for that work.
IPCG’s expert witness report also fails to present a genuine dispute of material fact. As the District Court correctly concluded, the report “falls well short of complying with the requirements of [Fed. R.Civ.P.] 26(a)(2)(B).” App. 7. Among its many deficiencies, the report fails to set forth the “facts or data considered by” IPCG’s expert in forming his opinions. Fed.R.Civ.P. 26(a)(2)(B)(ii). This is a material omission as it deprives Audubon of the means to determine the foundation for the opinion. Thus, even absent bad faith, this blatant non-compliance with Rule 26 justified the District Court’s exercise of its discretion to decline to consider the report.
See Caver v. City of Trenton,
420 F.3d 243, 265-66 (3d Cir.2005).
Moreover, nothing in the report reveals that the expert reviewed the Milestone #3 requirements or addressed the packages that are the subject of Milestone # 3. This Milestone requires Audubon to “[i]ssu[e] ... Major Equipment Procurement Packages for [IPCG’s] [p]urchase.” App. 90. Elsewhere, in a section titled “Procurement,” the Proposal states that Audubon is “to provide engineering and procurement services for [the] development of procurement packages to [IPCG]” for it to send to vendors. App. 83. Thus, Milestone # 3 addresses services associated with securing materials from vendors. Nothing in the expert’s opinion discusses this subject and IPCG’s assertion in its brief that “the discussion of ‘package’ in the [expert’s] report is a reference to the bid packages,” IPCG Br. 19, is neither evidential nor supported by the four corners of the report. Rather, the expert’s reference to “package” is a reference to an attachment labeled “Basic Engineering Design Package,” which lists engineering tasks a contractor would complete. App. 472. IPCG has identified nothing in that attachment as corresponding with the bid packages referenced in Milestone # 3. Thus, given the absence of any indication the report discusses the Milestone # 3 bid packages and its apparent focus on the native drawings and design materials, it is irrelevant to the instant dispute.
Finally, we address IPCG’s claims about the import of NRC’s role in this case. According to IPCG, Audubon “was heavily invested with, and committed to,” NRC, and thus “[t]his dispute is really between Audubon and ... NRC.” IPCG Br. 7. This argument is unavailing. Under Delaware law,
our role in interpreting a contract “is to effectuate the parties’ intent,” and thus we give “[c]lear and unambiguous language ... its ordinary and usual meaning.”
Lorillard Tobacco Co. v. Am. Legacy Found.,
903 A.2d 728, 739 (Del.2006) (internal quotation marks and citation omitted). The Agreement unambiguously defines only two “Parties” thereto, IPCG ■ and Audubon. App. 65. NRC is not a signatory to the Agreement, and IPCG has adduced no evidence showing that NRC is bound by its terms. In any event, the Agreement’s payment terms make clear that only IPCG is obligated to pay Audubon for its work on the
LPG Project. That IPCG did, in fact, pay Audubon for completing the first two Milestones bolsters this view and further undermines IPCG’s assertion that it is nothing more than a middleman who was not responsible for paying Audubon for its work.
III
For the foregoing reasons, we will affirm the order of the District Court granting summary judgment for Audubon.