Auburn Investments, Inc. v. LYDA Swinerton Builders, Inc. and NSHE TX Gainsville, LLC
Opinion
i i i i i i
MEMORANDUM OPINION
No. 04-08-00067-CV
AUBURN INVESTMENTS, INC., Appellant
v.
LYDA SWINERTON BUILDERS, INC. and NSHE TX GAINSVILLE, LLC, Appellees
From the 37th Judicial District Court, Bexar County, Texas Trial Court No. 2006-CI-11003 Honorable Karen Pozza, Judge Presiding
Opinion by: Sandee Bryan Marion, Justice
Sitting: Catherine Stone, Justice Sandee Bryan Marion, Justice Steven C. Hilbig, Justice
Delivered and Filed: July 30, 2008 AFFIRMED Appellant Auburn Investments, Inc. appeals from the trial court’s denial of its request for a temporary injunction against Lyda Swinerton Builders, Inc. and NSHE TX Gainsville, LLC. Because we cannot conclude the trial court abused its discretion in denying the temporary injunction, we affirm.
FACTUAL AND PROCEDURAL BACKGROUND Auburn Investments, Inc. (“Auburn”) owns the Drury Inn and Suites (“Drury”) in downtown San Antonio. Lyda Swinteron Builders, Inc. (“Lyda”) is constructing a Marriott Courtyard Hotel, next door to the Drury, for appellees NSHE TX Gainsville, LLC (“NSHE TX”). Some portions of the Drury and the Marriott are separated by just seven feet. The construction has created dust, debris, and noise.
Auburn sued Lyda and NSHE TX in July 2006 under theories of trespass, tortious interference with prospective relations, and nuisance. On December 5, 2007, after the construction phase had begun, Auburn filed its Amended Application for Temporary Injunction, alleging trespass, loss of business goodwill, and nuisance. The application asked the court to: 1) halt construction of the Marriot until actions are taken to stop the trespass onto Auburn’s property by “persons, equipment, vehicles, debris, tower cranes, [and] construction materials”; 2) limit construction to the hours between 8 a.m. and 6 p.m.; and 3) compel compliance with certain standards of the federal Occupational Safety and Health Administration that require construction sites to prevent falling debris outside its exterior walls.
On December 10, 2007, prior to the injunction hearing, the parties signed a Rule 11 agreement that, among other things, called for Lyda to: 1) restrict its work “that generates any significant level of noise” to the hours between 8 a.m. and 10:00 p.m. each day; 2) direct lighting from a tower crane onto the construction site and erect screens to prevent light from shining onto the Auburn’s property; and 3) erect eight-foot-tall screens around concrete pours to prevent concrete debris from migrating to Auburn’s property.
The agreement called for Drury’s owner, Rick Drury, and Lyda’s construction manager, Dan Wetting, to jointly observe a concrete pour on December 11, 2007, in order to identify and resolve
problems. Also, the parties agreed the terms of the Rule 11 agreement would have no precedential value and would not be used as evidence in court or as the basis for seeking similar relief in court.
On January 14, 2008, the trial court proceeded with the remaining issues in Auburn’s application for a temporary injunction concerning dust and debris. In its opening statement, Auburn asked for “injunctive language that prohibits [Lyda] from having debris land on our property.” Testimony and exhibits, which included photographs and construction materials, focused on the issue of dust and debris. According to evidence produced at the hearing to consider the temporary injunction, Auburn has refunded money to perhaps ten customers who were annoyed by the construction next door, in addition to offering credits or discounts to others. At the hearing, Rick Drury testified he has personally picked up nails, lumber, and bits of concrete that have fallen from the neighboring construction project onto the hotel property. He testified two cars had been splattered with concrete, while a security guard testified she had been struck, but not injured, by a small piece of falling debris. Drury also testified that he worried the hotel would lose customers and long-term goodwill among guests as the construction continues.
The trial court denied the temporary injunction, and this accelerated appeal followed.
STANDARD OF REVIEW
A trial court has broad discretion in deciding whether to grant or deny a temporary injunction.
Butnaru v. Ford Motor Co., 84 S.W.3d 198, 204 (Tex. 2002); Wu v. City of San Antonio, 216 S.W.3d 1, 4 (Tex. App.—San Antonio 2006, no pet.). We review the grant or denial of a temporary injunction for a clear abuse of discretion without addressing the merits of the underlying case. Walling v. Metcalfe, 863 S.W.2d 56, 58 (Tex. 1993); Ireland v. Franklin, 950 S.W.2d 155, 157 (Tex. App.—San Antonio 1997, no writ). An appellate court will uphold the trial court’s order unless the
trial court’s action was so arbitrary that it exceeded the bounds of reasonable discretion. Butnaru, 84 S.W.3d at 204. In an appeal from an order granting or denying a request for a temporary injunction, appellate review is confined to the validity of the order that grants or denies the injunctive relief. Universal Health Servs., Inc. v. Thompson, 24 S.W.3d 570, 576 (Tex. App.—Austin 2000, no pet.). We may neither substitute our judgment for that of the trial court nor consider the merits of the lawsuit. Id. Instead, we view the evidence in the light most favorable to the trial court’s order, indulging every reasonable inference in its favor, and determine whether the order was so arbitrary as to exceed the bounds of reasonable discretion. Id. When, as here, no findings of fact or conclusions of law are requested or filed, we must uphold the trial court’s judgment on any legal theory supported by the record. See, e.g., Davis v. Huey, 571 S.W.2d 859, 862 (Tex. 1978); Seaman v. Seaman, 425 S.W.2d 339, 341 (Tex. 1968).
DISCUSSION
To obtain a temporary injunction, the applicant must plead and prove three specific elements:
(1) a cause of action against the defendant; (2) a probable right to the relief sought; and (3) a probable, imminent, and irreparable injury in the interim. Butnaru, 84 S.W.3d at 204; City of San Antonio v. Vakey, 123 S.W.3d 497, 499 (Tex. App.—San Antonio 2003, no pet.). An injury is irreparable if the injured party cannot be adequately compensated in damages or if the damages cannot be measured by any certain pecuniary standard. Butnaru, 84 S.W.3d at 204. In its Amended Application for Temporary Injunction, Auburn complained it had suffered — and would continue to suffer — probable, imminent, and irreparable injury due to the loss of goodwill and the risk of injury to its guests or employees by falling debris.
1. Loss of goodwill Goodwill is property and, as such, its owner may recover for damages to it. Texas & P. Ry.
Co. v. Mercer, 90 S.W.2d 557, 560 (1936). Goodwill is generally understood to mean the advantages that accrue to a business on account of its name, location, reputation, and success. Swinnea v. ERI Consulting Eng’g, Inc., 236 S.W.3d 825, 837 (Tex. App.—Tyler 2007, pet. filed); Taormina v. Culicchia, 355 S.W.2d 569, 574 (Tex. Civ. App.—El Paso 1962, writ ref’d n.r.e.). The value of the goodwill “depends upon the fixed and favorable consideration of customers arising from an established and well-known and well-conducted business.” Taormina , 355 S.W.2d at 574.
Here, Oscar Cepeda, general manager of the Drury hotel, testified that some customers had complained about noise or debris. Cepeda claimed the hotel’s occupancy rate had declined due to the construction, to which Lyda objected on the ground that Auburn had not established a foundation for its assertion. The court sustained Lyda’s objection and rejected Cepeda’s testimony as speculation, stating:
Free access — add to your briefcase to read the full text and ask questions with AI
Auburn Investments, Inc. v. LYDA Swinerton Builders, Inc. and NSHE TX Gainsville, LLC (Auburn Investments, Inc. v. LYDA Swinerton Builders, Inc. and NSHE TX Gainsville, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.