Attorney General v. State Corp. Comm'n

CourtSupreme Court of Virginia
DecidedSeptember 12, 2014
Docket131873
StatusPublished

This text of Attorney General v. State Corp. Comm'n (Attorney General v. State Corp. Comm'n) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Attorney General v. State Corp. Comm'n, (Va. 2014).

Opinion

PRESENT: Kinser, C.J., Lemons, Millette, Mims and McClanahan, JJ., and Lacy and Koontz, S.JJ.

OFFICE OF THE ATTORNEY GENERAL, DIVISION OF CONSUMER COUNSEL OPINION BY v. Record Nos. 131872, 131873 JUSTICE ELIZABETH A. McCLANAHAN September 12, 2014 STATE CORPORATION COMMISSION, ET AL.

FROM THE STATE CORPORATION COMMISSION

In these consolidated appeals, we consider whether the State

Corporation Commission (“the Commission”) properly interpreted

Code § 56-585.1(A)(6) (“Subsection (A)(6)”) to allow Virginia

Electric and Power Company, d/b/a Dominion Virginia Power

(“Dominion”), to recover an enhanced rate of return on common

equity for transmission infrastructure associated with the

Brunswick County Power Station and included in the Subsection

(A)(6) rate adjustment clause for that facility.

I. Facts and Proceedings

In 2012, Dominion filed an application with the Commission

for certificates of public convenience and necessity approving

construction of (1) the Brunswick County Power Station, an

approximately 1,358 megawatt natural gas-fired combined cycle

electric generating facility to be located in Brunswick County,

and (2) transmission interconnection facilities associated with

the Brunswick generation plant, including new transmission lines,

two new switching stations, and facilities necessary to “tap”

existing transmission lines in Brunswick and Greensville Counties. The estimated costs of the Brunswick project total

$1.27 billion, including approximately $89.1 million in

associated transmission infrastructure costs.

Pursuant to Code § 56-585.1(A)(6), Dominion’s application

also sought approval of a rate adjustment clause (“RAC”),

designated as Rider BW, to recover the costs of the Brunswick

project and infrastructure associated therewith, “including the

transmission facilities necessary to interconnect the facility

with [Dominion’s] transmission system.” 1 At the time of its

1 At the time of Dominion’s application, Subsection (A)(6) read, in relevant part, as follows:

To ensure a reliable and adequate supply of electricity, to meet the utility’s projected native load obligations and to promote economic development, a utility may at any time, after the expiration or termination of capped rates, petition the Commission for approval of a rate adjustment clause for recovery on a timely and current basis from customers of the costs of . . . one or more other generation facilities. . . .

A utility that constructs any such facility shall have the right to recover the costs of the facility, as accrued against income, through its rates, including projected construction work in progress, and any associated allowance for funds used during construction, planning, development and construction costs, life-cycle costs, and costs of infrastructure associated therewith, plus, as an incentive to undertake such projects, an enhanced rate of return on common equity calculated as specified below.

2 application, Dominion’s general rate of return on common equity

(“ROE”) authorized by the Commission during Dominion’s 2011

biennial rate review was 10.4%. As part of Rider BW, Dominion

sought a 100 basis point (1%) enhancement on its general ROE for

the projected construction work in progress period, the

associated allowance for funds used during the construction

period, and the first fifteen (15) years of the service life of

The costs of the facility, other than return on projected construction work in progress and allowance for funds used during construction, shall not be recovered prior to the date the facility begins commercial operation.

Such enhanced rate of return on common equity shall be applied to allowance for funds used during construction and to construction work in progress during the construction phase of the facility and shall thereafter be applied to the entire facility during the first portion of the service life of the facility . . . .

Such enhanced rate of return on common equity shall be calculated by adding the basis points specified in the table below to the utility’s general rate of return, and such enhanced rate of return shall apply only to the facility that is subject of such rate adjustment clause . . . .

The basis points to be added to the utility’s general rate of return to calculate the enhanced rate of return on common equity . . . shall vary by type of facility, as specified in the following table.

Code § 56-585.1(A)(6) (as amended by 2012 Acts ch. 435)(emphasis added).

3 the Brunswick facility. 2 Dominion proposed applying the resulting

11.4% enhanced ROE to the costs of the generation facility as

well as the costs of associated transmission and non-transmission

infrastructure.

After receiving Dominion’s application, the Commission’s

staff filed a motion for ruling asking the Commission to rule

that the enhanced ROE authorized by Subsection (A)(6) “applies

only to the ‘facility,’ i.e., the generating plant, and not to

‘infrastructure associated therewith[.]’” The Office of the

Attorney General’s Division of Consumer Counsel (“Consumer

Counsel”) and the Virginia Committee for Fair Utility Rates each

filed responses supporting the Staff’s interpretation of

Subsection (A)(6).

Dominion filed a response opposing the Staff’s motion,

arguing that the Staff’s position is inconsistent with the plain

language of Subsection (A)(6), which establishes that costs of

associated infrastructure are “costs of the facility.” Moreover,

Dominion argued that the Staff’s interpretation of Subsection

2 Subsection (A)(6) includes a table designating the number of basis points to be added in calculating the enhanced ROE recoverable by a utility based on the type of generation facility constructed. At the time of Dominion’s application, a 100 basis point enhancement was available for natural gas combined-cycle generation facilities. See 2012 Acts ch. 435. However, in 2013, the General Assembly amended Subsection (A)(6). As a result, electric utilities may no longer receive an enhanced ROE for new generation construction projects filed for approval after January 1, 2013, except for nuclear and offshore wind facilities. See 2013 Acts ch. 2. 4 (A)(6) is inconsistent with the General Assembly’s stated goal of

providing “an incentive to undertake such projects,” which

necessarily require transmission and other infrastructure to

function. 3

The Commission held a public evidentiary hearing at which

Dominion presented evidence in support of its application.

Significantly, Dominion presented testimony that “but for”

construction of the Brunswick generating facility, the related

transmission lines and facilities would not be built.

As relevant to this appeal, the Hearing Examiner found that

Subsection (A)(6) authorizes an enhanced ROE on all costs of a

qualifying generating facility, “including the costs of

infrastructure necessitated by the facility.” Consequently, the

Hearing Examiner recommended that the Commission should accept

Dominion’s proposed rate design contained in Rider BW, including

the application of the enhanced ROE to the project’s transmission

infrastructure, if the project were approved. 4

3 Dominion also asserted that the Staff’s position contradicted the Commission’s established precedent from 12 previous cases in which it had approved recovery of an enhanced rate of return for transmission infrastructure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piedmont Environmental v. Virginia Elec.
684 S.E.2d 805 (Supreme Court of Virginia, 2009)
Northern Virginia Electric Cooperative v. Virginia Electric & Power Co.
576 S.E.2d 741 (Supreme Court of Virginia, 2003)
Buonocore v. Chesapeake & Potomac Telephone Co.
492 S.E.2d 439 (Supreme Court of Virginia, 1997)
Commonwealth v. Appalachian Electric Power Co.
68 S.E.2d 122 (Supreme Court of Virginia, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
Attorney General v. State Corp. Comm'n, Counsel Stack Legal Research, https://law.counselstack.com/opinion/attorney-general-v-state-corp-commn-va-2014.