Attorney General v. Baldwin

279 N.E.2d 710, 361 Mass. 199, 3 ERC (BNA) 1875, 1972 Mass. LEXIS 872
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 17, 1972
StatusPublished
Cited by6 cases

This text of 279 N.E.2d 710 (Attorney General v. Baldwin) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Attorney General v. Baldwin, 279 N.E.2d 710, 361 Mass. 199, 3 ERC (BNA) 1875, 1972 Mass. LEXIS 872 (Mass. 1972).

Opinion

Hennessey, J.

This is a bill in equity brought pursuant to G. L. c. 91, § 23, in which the plaintiff sought to enjoin the defendants from performing certain work in an area of Boston known as Tenean Creek. The bill alleged that the work was being done in violation of the terms of a license issued to the defendants by the Department of Public Works (Department). The matter is before us on the defendants’ appeals from an interlocutory decree overruling their demurrer and from a final decree enjoining them from continuing filling operations within the area and, further, ordering them to remove all fill previously placed there. On these appeals the defendants argue that (1) the Superior Court lacked jurisdiction to hear the matter; (2) the demurrer should have been sustained because the bill failed to state concisely and with substantial certainty a claim for relief; and (3) the judge’s findings do not support his final decree. There is before u's a transcript of the evidence and a report of material facts.

On September 13, 1967, the Department granted the trust a license “to maintain existing seawall and solid fill, *201 to place fill, to build and maintain steel and stone bulkheads, a concrete diversion wall, a solid fill pier and reinforced concrete culvert, to place and maintain timber piles and fixed floats and to dredge in Tenean Creek, so-called, off the Neponset River, in the city of Boston.” The license provided, in part, that “[s]olid fill may be placed within an enclosure consisting in part of said culvert, in part of a dike of coarse material with a facing of stone riprap . . . and in part of a steel sheet piling bulkhead . . . which shall be built prior to commencement of the filling” (emphasis supplied). The license also stated that “[a]Il of the work authorized hereby shall be performed in the locations shown on said plans and in accordance with the details there indicated” (emphasis supplied), and that “[t]he dike authorized hereby shall be constructed of coarse materials such as rock and gravel free of wood or organic materials and shall be faced with riprap to the satisfaction of the Department.” Immediately after the issuance of the license the defendants began filling operations at the site, which consisted of twenty-three acres of land. At the time of the trial in April, 1970, approximately one-half of the area had been filled by the defendants. However, beginning in October, 1968, the Department informed the defendants on several occasions that the work being done at the site did not conform to the requirements of the license. On September 9, 1969, the defendants were ordered “to stop forthwith, all filling and related work” because of, among other reasons, 2 the defendants’ “[f]ailure to construct culvert, bulkhead and dike prior to placement of fill in accordance with the provisions of the license.”

After a trial during which a view of the locus was taken, the judge made detailed and lengthy findings of *202 fact. The judge found that “the dike authorized under the license was to be constructed of coarse materials such as rock and gravel, free of wood or organic materials, and was to be faced with riprap to the satisfaction of the Department.” On the view the judge did not observe any steel bulkhead or extension of the culvert or any diking faced with riprap. He did observe “large timbers and other debris on the surface of the fill and in some instances imbedded in the fill at various depths.” The judge also found that on June 22, 1967, the Commonwealth appropriated the sum of $178,000 “for the purpose of plans, repairs, and extensions of the Tenean Creek culvert,” that the appropriation was extended until June, 1969, and that no money was ever spent from this appropriation. The judge further found that although this appropriation “was originally intended to be used for the construction of the concrete extension of the existing culvert” neither the appropriation nor the reference in the license or permission in the license that this culvert could be constructed by others, “established any legal obligation on the part of the Commonwealth to do same.” The judge did rule that the construction of the culvert was a requirement of the license. The judge' further found that the fill permitted should have been placed within an enclosure consisting of a steel bulkhead, culvert extension and dike, that the defendants “from the very outset, did not intend to construct a dike with rip-rap, the steel bulkhead, or cause to be constructed the concrete culvert,” but rather intended “to fill the center of the area . . . and thereafter the dike, bulkhead, and culvert, if they were to be built, would have enclosed the area that had already been filled.” This filling procedure, the judge found, was not in accordance with the requirements of the license and, therefore, constituted “a public nuisance within the meaning of” G. L. c. 91, § 23. Finally, we observe that subsequent to the court’s decision, the Legislature, pursuant to G. L. c. 91, § 15, revoked the license granted to the defendants. See St. 1970, c. 846.

*203 1. The defendants first contend that the subject matter of the present controversy was not a matter properly within the jurisdiction of the Superior Court. While it is true that lack of jurisdiction in the court below can be raised in this court for the first time (Warner v. Mayor of Taunton, 253 Mass. 116, 118; Golden v. Crawshaw, 302 Mass. 343, 344), we think that the present case was properly brought in the Superior Court. By instituting the proceedings, the plaintiff sought to have the defendants’ operations at Tenean Creek declared a public nuisance under G. L. c. 91, § 23. In the words of the statute, the relief sought, namely, “to enjoin or abate such nuisance” is equitable in nature. As such, the Superior Court had jurisdiction under G. L. c. 214, § 1, as appearing in St. 1935, c. 407, § 2, which provides, in part, that “[t]he supreme judicial and superior courts shall have original and concurrent jurisdiction in equity of all cases and matters of equity cognizable under the general principles of equity jurisprudence.” The defendants argue that the Superior Court lacked jurisdiction because G. L. c. 91, § 57, grants exclusive jurisdiction to this court in matters involving violations of c. 91. We disagree. The injunctive relief sought here, being a mat-, ter within “the general principles of equity jurisprudence,” is governed by the jurisdictional provisions of G. L. c. 214, § 1. Such relief is, in our opinion, alternative to that contained in G. L. c. 91, § 57. Even assuming, however, that § 57 provides the only available remedy, the same result would follow since G. L. c. 213, § 1A, as appearing in St. 1962, c. 722, § 3, grants concurrent jurisdiction to the Superior Court “of all proceedings, cases and matters of which the supreme judicial court has jurisdiction.”

2. The defendants also argue that it was error to overrule their demurrer. They contend that the bill fails to state concisely and with substantial certainty a claim for relief and, further, that the bill fails to allege that the defendants are operating without a license or otherwise *204 proceeding in violation of G. L. c. 91, § 23. There was no error.

General Laws c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cox v. City of Dallas
256 F.3d 281 (Fifth Circuit, 2001)
City of Boston v. Smith & Wesson Corp.
12 Mass. L. Rptr. 225 (Massachusetts Superior Court, 2000)
Abramian v. President & Fellows of Harvard College
9 Mass. L. Rptr. 556 (Massachusetts Superior Court, 1998)
Nature Church v. Board of Assessors
429 N.E.2d 329 (Massachusetts Supreme Judicial Court, 1981)
In the Matter of Troy
306 N.E.2d 203 (Massachusetts Supreme Judicial Court, 1973)
Lynch v. Board of Appeal
297 N.E.2d 63 (Massachusetts Appeals Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
279 N.E.2d 710, 361 Mass. 199, 3 ERC (BNA) 1875, 1972 Mass. LEXIS 872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/attorney-general-v-baldwin-mass-1972.