Attorney General Ex Rel. Department of Environmental Quality v. Bulk Petroleum Corp.

741 N.W.2d 857, 276 Mich. App. 654
CourtMichigan Court of Appeals
DecidedNovember 27, 2007
DocketDocket 264207
StatusPublished
Cited by24 cases

This text of 741 N.W.2d 857 (Attorney General Ex Rel. Department of Environmental Quality v. Bulk Petroleum Corp.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Attorney General Ex Rel. Department of Environmental Quality v. Bulk Petroleum Corp., 741 N.W.2d 857, 276 Mich. App. 654 (Mich. Ct. App. 2007).

Opinion

PER CURIAM.

Defendants appeal as of right the trial court’s order denying their motion for the reduction of a $1,090,000 penalty and granting plaintiff’s motion for additional penalties of $1,418,900. We affirm.

I. FACTS

In 1986, defendants acquired the former Bulk Station 3612, a retail gas station, located at 2020 North *656 US-23 in Hartland, Michigan, from Chevron, Inc. The property had five underground storage tanks that leaked petroleum from approximately 1986 to 1999. The problem was not corrected, and in 1993 the Department of Natural Resources (DNR), the predecessor of the Department of Environment Quality (DEQ), 1 issued a unilateral administrative order (UAO). The UAO required defendants to implement free product removal, install a groundwater treatment system, provide monthly reports to the DEQ, and provide the DEQ with copies of their contracts with qualified consultants. Defendants failed to comply with the requirements of the UAO, and they also failed to submit a final assessment report (FAR) detailing their progress in remediating the site as required by § 21311a, MCL 324.21311a, of part 213 of the Natural Resources and Environmental Protection Act (NREPA), MCL 324.21301a et seq.

On August 10, 2000, the DEQ imposed a $29,400 penalty on defendants for failing to submit a statutorily complete FAR, but defendants did not pay the penalty. In October 2000, defendants began excavating the contaminated soil from the site. On December 17, 2001, the Attorney General, on the relation of the DEQ, filed a complaint against defendants in the circuit court requesting that the court order defendants to comply with the UAO and the NREPA. Plaintiff moved for summary disposition, and on July 8, 2003, defendants stipulated that they were liable for violations of the UAO and the NREPA. Plaintiff then sought penalties in the amount of $3,364,400.

Defendants’ consultant had submitted a FAR in October 2002; however, the DEQ determined that the *657 FAR was statutorily incomplete and instructed defendants to correct the deficiencies in a timely manner. Defendants hired a new consultant, Northern Environmental Technologies, Inc., to prepare a new FAR.

At a hearing on August 5, 2003, the trial court imposed a $1,090,000 penalty on defendants for their failure to submit a statutorily complete FAR. The trial court also stated that it would monitor defendants’ actions and make “any adjustments to penalties for the violations as alleged in the Motion for Summary Disposition.” On October 30, 2003, defendants submitted a statutorily complete FAR to the DEQ. The DEQ then submitted a letter to defendants commenting on the FAR and requesting modifications. Defendants paid the $1,090,000 penalty on December 9, 2003.

On January 21, 2005, the DEQ moved for additional penalties, seeking the remainder of the $3,364,400 originally asked for, and defendants brought a motion to reduce the original $1,090,000 penalty. At a March 8, 2005, hearing, the trial court denied defendants’ motion and granted plaintiffs motion for additional penalties in the amount of $1,418,900, taking into account the seriousness of defendants’ violations and defendants’ noncompliance. The trial court also ruled that defendants waived a statute of limitations defense to the penalties by stipulating the entry of an order of summary disposition on the issue of liability on July 8,2003. Defendants now appeal.

II. IMPOSITION OF THE PENALTIES

Defendants argue that the trial court erred in imposing $1,090,000 in penalties at the August 5, 2003, hearing and $1,418,900 in penalties at the March 8, 2005, hearing. We disagree.

*658 A. STANDARD OF REVIEW

The interpretation and application of a statute constitutes a question of law that this Court reviews de novo. Eggleston v Bio-Medical Applications of Detroit, Inc, 468 Mich 29, 32; 658 NW2d 139 (2003).

B. ANALYSIS

1. THE AUGUST 5, 2003, PENALTIES

On August 5, 2003, the trial court assessed $1,090,000 in penalties against defendants for their failure to submit a statutorily complete FAR. Defendants challenge the trial court’s imposition of those penalties on three grounds. First, defendants assert that they should have been required to pay only the $29,400 in penalties imposed by the DEQ for their failure to submit a FAR because the trial court had no authority under MCL 324.21313a(l) to impose a higher penalty. Second, defendants contend that plaintiff failed to meet his evidentiary burden to support the imposition of the penalties. Finally, defendants argue that the trial court erred in failing to consider the seriousness of defendants’ violations and any good-faith effort by defendants to comply with the NREPA when imposing the penalties. We disagree.

a. THE TRIAL COURT’S AUTHORITY TO IMPOSE THE PENALTIES

Section 21311a of part 213 of the NREPA provides that “[w]ithin 365 days after a release has been discovered, a consultant retained by an owner or operator shall complete a final assessment report [FAR] that includes a corrective action plan developed under section 21309a and submit the report to the [DEQ].” MCL 324.21311a(l).

*659 Further, if a FAR is not completed within the statutory time frame, then the DEQ may impose graduated penalties according to the following schedule:

(a) Not more than $100.00 per day for the first 7 days that the report is late.
(b) Not more than $500.00 per day for days 8 through 14 that the report is late.
(c) Not more than $1,000.00 per day for each day beyond day 14 that the report is late. [MCL 324.21313a(l).]

Additionally, § 21323(l)(d) of part 213 authorizes the Attorney General to commence a civil action on behalf of the DEQ and to seek several remedies for noncompliance, including

[a] civil fine of not more than $10,000.00 for each underground storage tank system for each day of noncompliance with a requirement of [part 213] or a rule promulgated under [part 213]. A fine imposed under this subdivision shall be based upon the seriousness of the violation and any good faith efforts by the violator to comply with the part or rule. [MCL 324.21323(l)(d).]

Defendants contend that because the plain language of MCL 324.21313a(l) only authorizes the DEQ to impose penalties for an untimely FAR, the trial court was without authority to assess the $1,090,000 penalties against defendants. We disagree.

As an initial matter, we note that defendants failed to raise this argument below. Therefore, it is not properly preserved for appellate review. Brown v Loveman, 260 Mich App 576, 599; 680 NW2d 432 (2004) (noting that, as a general rule, this Court does not review issues that are not raised and decided by the trial court).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mark L Wilkie Revocable Trust v. Peter B Stano
Michigan Court of Appeals, 2026
City of River Rouge v. Dte Electric Company
Michigan Court of Appeals, 2019
Law Offices of Jeffrey Sherbow, PC v. Fieger & Fieger, PC
930 N.W.2d 416 (Michigan Court of Appeals, 2019)
Township of Williamstown v. Sandalwood Ranch LLC
927 N.W.2d 262 (Michigan Court of Appeals, 2018)
Peter Galinis v. County of Branch
660 F. App'x 350 (Sixth Circuit, 2016)
in Re Koehler Estate
Michigan Court of Appeals, 2016
Gary Wilson v. City of Grosse Pointe Park
Michigan Court of Appeals, 2016
Detroit Edison Company v. Stenman
875 N.W.2d 767 (Michigan Court of Appeals, 2015)
Carson Fischer Plc v. Mettler Walloon LLC
Michigan Court of Appeals, 2015
St Clair Inn LLC v. Transcapital Bank
Michigan Court of Appeals, 2015
Ees Coke Battery LLC v. City of River Rouge
Michigan Court of Appeals, 2014
Dunn v. Bennett
846 N.W.2d 75 (Michigan Court of Appeals, 2013)
In re Forfeiture of a Quantity of Marijuana
805 N.W.2d 217 (Michigan Court of Appeals, 2011)
Marilyn Froling Revocable Living Trust v. Bloomfield Hills Country Club
769 N.W.2d 234 (Michigan Court of Appeals, 2009)
In Re Nm Holdings Company, LLC
405 B.R. 830 (E.D. Michigan, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
741 N.W.2d 857, 276 Mich. App. 654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/attorney-general-ex-rel-department-of-environmental-quality-v-bulk-michctapp-2007.