Atmos Energy Corp. v. Georgia Public Service Commission

674 S.E.2d 312, 285 Ga. 133, 2009 Fulton County D. Rep. 749, 2009 Ga. LEXIS 75
CourtSupreme Court of Georgia
DecidedMarch 9, 2009
DocketS08G1206
StatusPublished
Cited by8 cases

This text of 674 S.E.2d 312 (Atmos Energy Corp. v. Georgia Public Service Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atmos Energy Corp. v. Georgia Public Service Commission, 674 S.E.2d 312, 285 Ga. 133, 2009 Fulton County D. Rep. 749, 2009 Ga. LEXIS 75 (Ga. 2009).

Opinion

HUNSTEIN, Presiding Justice.

In this challenge to a rate change ruling by the Georgia Public Service Commission (“PSC”), the Court of Appeals vacated the superior court’s order on the petition for judicial review filed by Atmos Energy Corporation (“AEC”) on the basis that the superior court lacked jurisdiction to hear the petition and then remanded the case to that court with direction that it dismiss the petition. Atmos Energy Corp. v. Ga. Public Svc. Comm., 290 Ga. App. 243 (1) (659 SE2d 385) (2008). We granted AEC’s writ of certiorari to address questions regarding the finality of the orders issued by the PSC. For the reasons that follow, we affirm the Court of Appeals.

OCGA § 46-2-25 governs the procedure for changing any rate, charge, classification or service by any utility subject to the jurisdiction of the PSC. Subsection (a) of that statute requires the utility to give 30 days notice to the PSC and the public regarding such a change. Pursuant to subsection (b) of OCGA § 46-2-25, the PSC, in order to enter upon a hearing concerning the lawfulness of the change, is authorized to suspend the operation of the proposed change and defer the use of the change “but not for a period longer than five months beyond the time when it would otherwise go into effect.” Should a longer period of time be necessary, OCGA § 46-2-25 (b) explicitly authorizes the PSC to “apply to the Superior Court of Fulton County for an extension of such period, as provided for in Code Section 46-2-57.”

The facts pertinent to this case are as follows. AEC, a natural gas distribution company subject to the PSC’s jurisdiction, commenced a *134 utility rate-change proceeding before the PSC on May 20, 2005. The PSC suspended operation of that change pursuant to OCGA § 46-2-25 (b) and conducted a series of hearings on the matter. On the last day of the six-month “file and suspend” period provided in OCGA § 46-2-25, 1 the PSC entered a 12-page order (the “November Order”) that contained findings of facts and conclusions of law authorizing AEC to increase its rates in part. Although the November Order stated, at the bottom of each page, that it was a “final order,” it also specifically provided that “[a] more detailed Order explaining each item herein will follow.” AEC chose to file a petition for rehearing and reconsideration of that order. See PSC Rule 515-2-1-.08. At its administrative session in December 2005, the PSC addressed AEC’s motion and, by voice vote, decided to amend and modify a portion of the November Order to correct a computation error.

Within 30 days of the December voice vote, AEC filed a petition in the Fulton County Superior Court in which it sought judicial review of the November Order and December voice vote. While this petition was pending, the PSC issued a 59-page “Order on Reconsideration and Final Order” for “the purpose of ruling on [AEC’s] Petition for Rehearing, Reconsideration and Oral Argument and providing the more detailed Order referenced in the November . . . Order.” This order, which also corrected the computation error as voted on at the December administrative session, was issued on February 2, 2006. The PSC later moved to dismiss AEC’s petition on various grounds. In its response, AEC specifically asserted that the February Order was not valid and a “nullity” because it was filed approximately two and one-half months after expiration of the “file and suspend” period in OCGA § 46-2-25 and a month and one-half after the December voice vote to deny AEC’s motion for reconsideration. The superior court denied the PSC’s motion to dismiss on the basis, inter alia, that AEC “constructively petitioned for judicial review of the February” Order, and affirmed the PSC’s rate change ruling on the merits. As noted above, the Court of Appeals then vacated the superior court’s ruling and remanded the case with direction that it dismiss the petition. Atmos Energy Corp., supra, 290 Ga. App. at 249 (1).

1. AEC contends the Court of Appeals erred by holding that the November Order was not a final order subject to judicial review. Although AEC points to a number of factual issues that it asserts *135 serve to indicate that the November Order could have been a final order, e.g., it was a written order containing findings of fact and conclusions of law and a vote approving the order was entered into the official minutes of the PSC, the Court of Appeals carefully examined the language in the November Order itself and found that the order was “nothing more than an interim decision by the PSC. [Cits.]” Atmos Energy Corp., supra, 290 Ga. App. at 246 (1) (a). Our review of the record reveals no error in this factual finding.

AEC also proposes a legal argument in support of its position, which is based on the language in OCGA § 46-2-25 that the PSC “may suspend the operation” of a proposed change “but not for a period longer than five months beyond the time when it would otherwise go into effect.” Id. at (b). 2 Relying on this statutory language, AEC asserts that the November Order had to be a final order because the PSC was required by OCGA § 46-2-25 to decide the proposed change by the end of the “file and suspend” period. This argument, however, overlooks this Court’s contrary interpretation of OCGA § 46-2-25 in Atlanta Gas Light Co. v. Ga. Textile Assn., 266 Ga. 738 (470 SE2d 230) (1996). The trial court in that case found that, although Atlanta Gas Light had dismissed an underlying rate case in which the intervenors had sought to appeal an adverse PSC ruling, the intervenors’ appeal was not thereby rendered moot because it “would evade review since a rate case must be decided within six months from notice of a proposed change and it was unlikely that a judicial appeal . . . could be completed prior to the conclusion of the administrative proceeding.” Id. at 738. This Court rejected “the trial court’s determination that rate cases must be decided within six months” and instead construed OCGA § 46-2-25 (b) as “stat[ing] only that the effective rate suspension period is six months from the date rates are filed,” in determining that “no reason appears as to why this issue would evade review in future cases.” Atlanta Gas Light Co., supra, at 739 (1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C.P.R. v. Henry County Board of Education
Court of Appeals of Georgia, 2014
C. P. R. v. Henry County Board of Education
763 S.E.2d 725 (Court of Appeals of Georgia, 2014)
Georgia Society of Ambulatory Surgery v. Ga Dch
Court of Appeals of Georgia, 2012
Bailey v. Kunz
706 S.E.2d 98 (Court of Appeals of Georgia, 2011)
Boca Petroco, Inc. v. Petroleum Realty II
678 S.E.2d 330 (Supreme Court of Georgia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
674 S.E.2d 312, 285 Ga. 133, 2009 Fulton County D. Rep. 749, 2009 Ga. LEXIS 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atmos-energy-corp-v-georgia-public-service-commission-ga-2009.