Atlantic Richfield Co. v. U.S. Department of Energy

977 F.2d 611, 1992 U.S. App. LEXIS 20480, 1992 WL 207619
CourtTemporary Emergency Court of Appeals
DecidedAugust 27, 1992
DocketNo. DC-117
StatusPublished
Cited by3 cases

This text of 977 F.2d 611 (Atlantic Richfield Co. v. U.S. Department of Energy) is published on Counsel Stack Legal Research, covering Temporary Emergency Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Richfield Co. v. U.S. Department of Energy, 977 F.2d 611, 1992 U.S. App. LEXIS 20480, 1992 WL 207619 (tecoa 1992).

Opinion

JOHN W. PECK, Judge:

This appeal arose from the denial by the Office of Hearings and Appeals (OHA) of ARCO’s application to refile Refiner’s Monthly Cost Allocation Reports (RMCARs). The district court affirmed OHA’s denial. For the reasons stated below, we affirm the district court.

FACTS

During the period of petroleum price controls, the applicable regulations permitted oil refiners to incorporate increased crude oil costs into the prices of their refined products covered by the regulations. The formula for allocating costs to price increases for the covered goods was referred to as the V factor. The V factor entailed taking the total volume of a given covered product sold and dividing by the total volume of all covered products sold. The resulting fraction was then used to determine the portion of increased crude oil costs that could be attributed to the covered product. Oil refiners could either increase the price of the covered product or bank the increased costs to offset overcharges.

When the Economic Stabilization Act (ESA) expired on April 30, 1974, the Emergency Petroleum Allocation Act (EPAA) succeeded it as the vehicle for administering the price controls. Under the EPAA and the accompanying Department of Energy (DOE) regulations, certain products which had been regulated under the ESA were no longer subject to price controls. Under the new regulations, the increased cost of crude oil used to produce the newly exempt products was included in the total increased cost of producing covered goods, but the volume of the exempt goods sold was not included in the denominator of the V factor. Therefore, the oil companies could pass on the increased crude oil costs to produce newly exempt products in the price of both the newly exempt goods and the covered goods. In an eleventh hour attempt to prevent this result, DOE passed an emergency amendment to the regulations on April 30, 1974 which included the volume of newly exempt goods in the denominator of the V factor and thus prevented refiners from allocating increased crude oil costs from exempt goods to the price of the covered products. DOE promulgated the amendment without an opportunity for notice or comment.

As a refiner, ARCO was required to file Refiner’s Monthly Cost Allocation Reports (RMCARs). After the promulgation of the emergency amendment, ARCO consistently filed its RMCARs using the amended V factor. However, Mobil Oil challenged the amendment in court. In Mobil Oil Corp. v. Dep’t of Energy, 610 F.2d 796 (Temp.Emer.Ct.App.1979), cert. denied, 446 U.S. 937, 100 S.Ct. 2156, 64 L.Ed.2d 790 (1980) (Mobil I), this court affirmed the district court’s determination that the amendment was substantively and proee-durally invalid because DOE had failed to consider the relevant factors set forth in § 4(b) of the EPAA, 15 U.S.C. § 753(b)(1) and failed to provide notice to interested parties and an opportunity for comment. After remand and a second appeal, this court ruled that Mobil was permitted to reallocate its costs in accordance with the unamended V factor for the period between the 1974 amendment and February 1976. Mobil Oil Corp. v. Dep’t of Energy, 647 F.2d 142 (Temp.Emer.Ct.App.1981) (Mobil II). In 1981, DOE attempted to repromul-gate and retroactively apply the 1974 amendment. However, in Mobil v. Dep’t of Energy, 678 F.2d 1083, 1090 (Temp.Emer.Ct.App.1982) (Mobil III), this court invalidated the regulation.

In March 1979, DOE promulgated a refiling regulation which provided that after May 31, 1979, any refiner wishing to refile a revised RMCAR for a period more than one year prior to the refiling would have to obtain written permission from DOE “for good cause shown.” 10 C.F.R. § 212.-126(d). The regulation also stated:

DOE will not make a finding of good cause routinely. Where it appears that [613]*613such a finding may adversely affect the interest of the consuming public, a firm must demonstrate in its application, at a minimum, that the claimed errors or omissions in the report or reports which the firm seeks to replace or modify did not result from a failure to exercise due care or diligence.

In March and April 1980 and August 1981, ARCO requested permission from DOE to refile its RMCARs using the unamended Y factor. In each case, DOE rejected these refilings as premature pending final resolution of the Mobil litigation. In March 1982, ARCO again requested permission to refile. DOE did not respond to this request and ARCO did not pursue the matter. Shortly thereafter, ARCO and DOE entered into settlement negotiations regarding ARCO’s compliance with the price control regulations. The negotiations resulted in a settlement and consent order in which the unamended V factor was used.

Meanwhile, in 1979, Don Van Vranken and other ARCO wholesale customers, who are intervenors in this case, brought suit in federal court alleging that ARCO had overcharged resellers for covered goods. Van Vranken v. Atlantic Richfield Corp., 699 F.Supp. 1420 (N.D.Cal.1988), aff'd, 890 F.2d 421 (Temp.Emer.Ct.App.1989). In considering whether ARCO had overcharged its customers, the district court had to review ARCO’s calculation of its banks of unrecov-ered costs which would be used to offset overcharges. Thus, the effect of the invalidation of the 1974 amendment became important with regard to calculating ARCO’s banked costs. In a summary judgment motion, ARCO argued that the Mobil cases allowed it to retroactively reallocate its costs. The practical effect of such a reallocation would have been that ARCO could increase its banked costs and reduce its overcharge liability. The district court rejected ARCO’s argument holding that the Mobil decisions did not automatically allow ARCO to reallocate its costs. Id. at 1424.

On appeal, this court held that the Mobil cases neither required nor permitted ARCO to retroactively reallocate its costs. Van Vranken v. Atlantic Richfield Corp., 890 F.2d 421 (Temp.Emer.Ct.App.1989). The court reasoned that ARCO was not required to reallocate costs because it was not unlawful for ARCO to have priced its goods below the fixed maximum price by using the amended V factor. The court also stated that ARCO was not permitted to reallocate its costs because it had failed to obtain permission from DOE as required by the regulations. Furthermore, the court ruled that ARCO had waived it right to relief by failing to challenge the amendment in a timely manner.

In December 1989, ARCO applied for permission to refile its RMCARs claiming that this court’s decision in Van Vranken necessitated the action. DOE did not respond to the application. ARCO treated DOE’s silence as a denial and appealed to the OHA.

In February 1991, OHA upheld DOE’s sub silentio denial. OHA concluded that the Mobil

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
977 F.2d 611, 1992 U.S. App. LEXIS 20480, 1992 WL 207619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-richfield-co-v-us-department-of-energy-tecoa-1992.