Atlantic Constructors, Inc. v. KBE Building Corporation

CourtDistrict Court, W.D. Virginia
DecidedSeptember 1, 2020
Docket3:20-cv-00018
StatusUnknown

This text of Atlantic Constructors, Inc. v. KBE Building Corporation (Atlantic Constructors, Inc. v. KBE Building Corporation) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Constructors, Inc. v. KBE Building Corporation, (W.D. Va. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF VIRGINIA Charlottesville Division

MANGANARO MIDATLANTIC, LLC,

Plaintiff,

v. Case No. 3:19cv00080 KBE BUILDING CORPORATION, et al., Defendants ATLANTIC CONSTRUCTORS, INC.,

v. Case No. 3:20cv00018 KBE BUILDING CORPORATION, et al., Defendants

MEMORANDUM OPINION & ORDER

Before the Court are Defendants KBE Building Corporation’s (“KBE”) and Federal Insurance Company’s (“Federal”) (collectively the “Defendants”) Joint Motions to Consolidate the above-captioned cases.1 Joint Mot. to Consolidate Cases, Manganaro MidAtl., LLC v. KBE Bldg. Corp., No. 3:19cv80 (“Manganaro MidAtl.”), ECF No. 21; Joint Mot. to Consolidate Cases, Atl. Constructors, Inc. v. KBE Bldg. Corp., No. 3:20cv18 (“Atl. Constructors”), ECF No. 13. For the reasons stated below, the Court hereby GRANTS the Joint Motions to Consolidate, Manganaro MidAtl., ECF No. 21; Atl. Constructors, ECF No. 13, and consolidates these two cases for all further proceedings, including trial. I. Factual and Procedural Background

1 The Defendants initially moved to consolidate four separate cases, however, two of those cases have resolved and those motions are moot. See Order, Sullivan Mech. Contractors, Inc. v. KBE Bldg. Corp., No. 3:20cv13 (W.D. Va. July 29, 2020), ECF No. 39; Stipulation of Dismissal, Moore’s Elec. & Mech. Constr., Inc. v. KBE Bldg. Corp., No. 3:20cv19 (W.D. Va. Aug. 11, 2020), ECF No. 23. In November 2017, the Commonwealth of Virginia and the Rector and Visitors of the University of Virginia (collectively “Owner”) entered into a construction agreement with KBE for the construction of upper-class student housing (the “Project”). See Compl. ¶ 4, Manganaro MidAtl., ECF No. 1. Federal issued a payment bond on behalf of KBE in connection with the Project. Id. ¶ 5. In February 2018, KBE and Atlantic Constructors, Inc. (“Atlantic”) entered into

a subcontract agreement for Atlantic to provide fire protection work at the Project. Am. Compl. ¶ 5, Atl. Constructors, ECF No. 22.2 Atlantic completed its work on the Project in November 2019. Id. ¶ 7. Atlantic alleges that KBE breached the subcontract agreement, the Defendants breached the payment bond, and it is owed approximately $168,175 for its completed work. Id. ¶¶ 8, 12– 19. In May 2018, KBE and Manganaro MidAtlantic Corporation (“Manganaro”) entered into a subcontract agreement for Manganaro to install drywall, carpentry, and ceiling tiles at the Project. Compl. ¶ 7, Manganaro MidAtl. Manganaro completed its work on the Project between October 2018 and August 2019. Id. ¶¶ 9, 17. Manganaro alleges that KBE made numerous

changes to the scope of its work, and it was delayed and hindered in completing its work by KBE and other subcontractors on the Project resulting in increased costs to Manganaro. Id. ¶¶ 10–12. Manganaro further alleges that KBE breached the subcontract agreement, the Defendants breached the payment bond, and it is owed approximately $1,526,833 for its completed work. Id. ¶¶ 16, 19–30. The Defendants filed Joint Answers and Counterclaims in both cases. Joint Answer & Countercl., Manganaro MidAtl., ECF No. 10; Joint Answer & Countercl., Atl. Constructors,

2 On August 11, 2020, I entered an Order granting Atlantic’s motion to file an Amended Complaint. Order, Atl. Constructors, ECF No. 21. ECF No. 25. KBE alleges the same affirmative defenses and the same counterclaim for breach of the subcontract in both cases.3 Joint Answer & Countercl. 5–11, Manganaro MidAtl.; Joint Answer & Countercl. 4–8, Atl. Constructors. In part, KBE alleges that other subcontractors, including the Plaintiffs in these two cases, were responsible for the delays and additional costs in the Project. See Joint Answer & Countercl. 5–6, Manganaro MidAtl.; Joint Answer & Countercl.

4, Atl. Constructors.; Defs.’ Mem. in Supp. of Joint Mot. to Consolidate4, Manganaro MidAtl., ECF No. 22; Defs.’ Mem. in Supp. of Joint Mot. to Consolidate 4, Atl. Constructors, ECF No. 14. The Defendants filed their Joint Motions to Consolidate and Memoranda in Support in May 2020. Manganaro and Atlantic filed their Responses in Opposition, Manganaro MidAtl., ECF No. 25; Atl. Constructors, ECF No. 17, and the Defendants filed a Joint Reply, Manganaro MidAtl., ECF No. 26; Atl. Constructors, ECF No. 18. On August 18, this Court held a hearing on the motions. The matters are now ripe for decision. II. Legal Framework Rule 42 of the Federal Rules of Civil Procedure provides, “[i]f actions before the court

involve a common question of law or fact, the court may . . . consolidate the actions.” Fed. R. Civ. P. 42(a)(2). “District courts have broad discretion under [Rule 42] to consolidate causes pending in the same district.” A/S J. Ludwig Mowinckles Rederi v. Tidewater Constr. Corp., 559 F.2d 928, 933 (4th Cir. 1977) (citing Fed. R. Civ. P. 42(a)). The Court must weigh the risk of prejudice and possible confusion from consolidation against the burden on the parties, witnesses, and judicial resources to conduct multiple suits involving common questions of law or fact, the length of time to conclude multiple lawsuits as opposed to a single lawsuit, and the “relative

3 The Defendants allege that the Plaintiffs breached the subcontract in many of the same ways, but include additional breaches on the part of Manganaro. expense” to all of the parties presented by a single consolidated trial or multiple trials. Campbell v. Bos. Sci. Corp., 882 F.3d 70, 74 (4th Cir. 2018). Generally, “judicial economy favors consolidation because it saves time and expenses and avoids the risk of inconsistent judgments.” Diment v. Sup. Ct. of Va., No. 3:07cv33, 2007 WL 4302867, at *1 n.1 (W.D. Va. Dec. 6, 2007) (citing Switzenbaum v. Orbital Scis. Corp., 187 F.R.D. 246, 248 (E.D. Va. 1999)).

III. Analysis These cases involve substantial common questions of law and fact, including the same prime construction contract, the same Project, the same defendants, the same causes of action, and the same defenses and counterclaims. See Harris v. L & L Wings, Inc., 132 F.3d 978, 981 n.2 (4th Cir. 1997) (noting that plaintiffs’ cases “brought against the same defendant, relying on the same witnesses, alleging the same misconduct, and answered with the same defenses clearly meet th[e] standard” for consolidation under Rule 42(a)); Rishell v. Comput. Scis. Corp., Nos. 1:13cv931, 1:14cv213, 2014 WL 11515835, at *1 (E.D. Va. Apr. 4, 2014) (consolidating cases that involved the same defendant and likely involved deposing the same witnesses and exploring

the same defenses). The Plaintiffs allege that the Defendants breached the subcontract agreements4 and failed to pay for work satisfactorily completed. The Defendants counter with the same affirmative defenses to those claims and substantially similar counterclaims, including that the Plaintiffs in these two cases are at least partially responsible for each other’s damages. Questions of law will center on contract interpretation of the prime contract and the two subcontracts at issue which, although different, are similar enough to warrant consolidation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Atlantic Constructors, Inc. v. KBE Building Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-constructors-inc-v-kbe-building-corporation-vawd-2020.