Atlantic Coast Line Railroad v. United States

129 Ct. Cl. 137, 1954 U.S. Ct. Cl. LEXIS 78, 1954 WL 6107
United States Court of Claims·Decided July 13, 1954·No. No. 368-52·Published·Cited by 6 cases

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Defendant leased from plaintiff a tract of 107.1 acres on the south bank of the Savannah River near Savannah, Georgia. It was to be used by defendant for an extension of an adjoining shipyard being operated for the defendant by the Southeastern Shipbuilding Corporation. On it the defendant intended to erect various buildings and a dock.

Article III of the lease provided:

The Lessor further agrees that it will not make or assert any claim on account of damage or injury of whatsoever nature caused to the leased premises by an act or omission of the Lessee or any of its agents, employees, or independent contractor employed by it in connection with the removal from the leased premises of any facilities, structures, buildings, or other property of whatsoever nature. The leased premises, however, from which any facilities are removed, shall be restored to as good a condition as they were prior to the acquisition, construction, or installation of such facilities.

On May 21, 1948, the War Assets Administration, which had taken over the property from the United States Maritime Commission after the war, notified plaintiff that it would surrender the lease effective July 31,1948, and would remove the improvements placed on the property. The lease was surrendered and the improvements were removed, except that there was left on the premises concrete building foundations and concrete slabs, called platens, a part of the superstructure of the dock, and the pilings which had been driven into' the. bed of the river to hold up the dock. Plaintiff demanded the removal of all of these things, or, in the alternative, the payment of the cost of their removal. Upon the rejection of this demand, plaintiff brought this suit.

The Commissioner has found that the cost of the removal of the concrete building foundations would be $11,760; that the cost of removing the platen foundations would be $11,550; and the cost of removing the dock superstructure would be $11,250. The parties agree on these figures. The [139]*139Commissioner has also found that it would cost $52,400 to remove the piling. The defendant accepts this figure, but the plaintiff says that it would cost at least $102,000 to remove it.

Defendant admits that plaintiff is entitled to the cost of removing the above-mentioned things from the premises, but it says that there should be offset against this cost the increased value of the premises resulting from filling it in by the defendant, which, it is agreed, is $70,000.

The two issues in the case are, therefore, the cost of removing the pilings, and defendant’s right to offset the value of the improvement on the property against the cost of removing the remainder of the structures.

The pilings were driven down through about 10 or 12 feet of mud in the bottom of the river, and into the marl which was underneath the mud. Defendant’s engineer testified that the cost of removing them would be $5.00 a pile, if they were driven only down to the marl, but that it would probably cost as much as $15.00 a pile to completely remove them if they had been driven into the marl. Defendant’s engineer also testified that the property would not be injured for future use if the piles were merely broken off at the marl line; and that this could be done for $5.00 a pile.

But plaintiff’s engineers say that breaking them off at the marl line would not permit another dock to be erected at this site unless it was of the same character as the dock erected by the defendant. They admit that if a dock of the same character was to be erected in the future, that the stumps of the old piles could be used as a foundation for any new piles that might be driven for a later structure. About the only trouble they could foresee was the possibility that a future occupant might want to reinforce the underpinning of a dock he might want to erect at some place other than where it had been reinforced by defendant. In this event they say they could not drive reinforcing piles because they would encounter the remainder of the piles left by defendant.

Defendant’s engineer said this would present no difficulty because if they did, the new pile would just glance off and go on down by the side of the old pile. This seems reasonable to us. Even where the dock had been reinforced by [140]*140defendant the piles were at least two feet apart and considerably further apart at other points. There was, therefore, plenty of room for the new piles. We are unable to see how leaving the stumps of the old piles would materially injure the property for future use.

The Commissioner has allowed $52,400 for the cost of removing these piles. Since there were from 6,500 to 7,100 piles, this is an allowance of between $7 and $8 a pile for removing them. It seems to us that this is a reasonable figure. The defendant does not contend that it is too much.

We are also of the opinion that defendant is not entitled to offset the enhancement in value of the property from filling it in against the admitted obligation of the defendant to remove the concrete foundations and piles, because there is no provision in the lease which authorizes it. The parties knew the defendant would fill in the property, because it was not usable without it, but no provision was made for compensating the defendant therefor upon termination of the lease. Defendant filled it in not at the demand or request of the plaintiff, but of its own volition. It was done not for the benefit of the landlord, but for the lessee’s benefit. The resulting benefit to the landlord was incidental to the defendant’s use of the property. In such case there is no obligation on plaintiff to reimburse defendant for the cost of doing so, in the absence of a provision in the lease requiring it.

In 32 Am. Jur. p. 524, it is said:

In the absence of any agreement between the parties, there is no obligation on the part of the lessor to pay the lessee for improvements erected by the latter upon the demised premises, even though the improvements are such that by reason of their annexation to the freehold they become a part of the realty and cannot be removed by the lessee.

Ample authority is cited to support the text, including Kutter v. Smith, 2 Wall. 491.

It may seem inequitable to put defendant to the expense of removing these things that might impair a future use of the property without giving it credit for what it did to improve the property; but that is the way the lease was written, and it was the defendant who wrote the lease. We can only [141]*141give effect to what was written, and not to what the defendant now thinks should have been written.

Defendant says the lease provides that the property shall be restored to as good a condition as it was when the lease was executed, and not to the same condition. Hence, it says if the value of the improvements equals the impairment in value, the condition of the lease is satisfied.

But this is not what the lease says. It says the lessor will make no claim for damage to that part of the property from which structures or facilities erected by defendant are removed, with the proviso that that part of the leased premises from which structures are removed shall be restored to a condition as good as they were before erection of the structure. What the parties had in mind was the effect on the property of the erection of the structures and their removal.

Free access — add to your briefcase to read the full text and ask questions with AI

Atlantic Coast Line Railroad v. United States, 129 Ct. Cl. 137, 1954 U.S. Ct. Cl. LEXIS 78, 1954 WL 6107 (cc 1954).

129 Ct. Cl. 137 (Atlantic Coast Line Railroad v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cruzan v. Franklin Stores Corporation
380 P.2d 190 (New Mexico Supreme Court, 1963)
Realty Associates, Inc. v. United States
138 F. Supp. 875 (Court of Claims, 1956)
County of Riverside v. United States
137 F. Supp. 409 (Court of Claims, 1956)
Riverside County v. United States
137 F. Supp. 409 (Court of Claims, 1956)