Atlantech Distribution, Inc. v. Land Coast Insulation

CourtCourt of Appeals of North Carolina
DecidedJuly 16, 2024
Docket23-751
StatusPublished

This text of Atlantech Distribution, Inc. v. Land Coast Insulation (Atlantech Distribution, Inc. v. Land Coast Insulation) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantech Distribution, Inc. v. Land Coast Insulation, (N.C. Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

No. COA23-751

Filed 16 July 2024

Mecklenburg County, No. 22 CVS 540

ATLANTECH DISTRIBUTION INC., Plaintiff,

v.

LAND COAST INSULATION, INC., MATRIX SERVICE, INC.; DUKE ENERGY BUSINESS SERVICES, LLC; PIEDMONT NATURAL GAS COMPANY, INC. and FIDELITY AND DEPOSIT COMPANY OF MARYLAND, Defendants.

Appeal by Defendants from Order entered 9 March 2023 by Judge Carla Archie

in Mecklenburg County Superior Court. Heard in the Court of Appeals 10 January

2024.

Johnston, Allison & Hord, P.A., by B. David Carson, David E. Stevens and Grace E. Ketron, for Plaintiff-Appellee.

Lewis Brisbois Bisgaard & Smith LLP, by Eric G. Sauls and Jonathan M. Preziosi, admitted pro hac vice, for Defendants-Appellants.

HAMPSON, Judge.

Factual and Procedural Background

Matrix Service, Inc. (Matrix), Duke Energy Business Services, LLC (Duke

Energy), Piedmont Natural Gas Company, Inc. (PNG), and Fidelity and Deposit

Company of Maryland (Fidelity) (collectively, Defendants) appeal from an Order

granting Summary Judgment in favor of Plaintiff-Appellee Atlantech Distribution

Inc. (Atlantech). The Record before us tends to reflect the following: ATLANTECH DISTRIBUTION, INC. V. LAND COAST INSULATION, INC.

Opinion of the Court

On or about 30 April 2019, Matrix entered into a contract with PNG (the

Primary Contract), a subsidiary of Duke Energy, to perform certain engineering,

procurement, and construction services for PNG’s Robeson County LNG Peak-

Shaving Facility (the Project). The value of the Primary Contract was nearly $200

million. On or about 9 August 2019, Matrix obtained its first building permit for the

Project. On 3 July 2019, Matrix filed a Notice of Contract with the Robeson County

Clerk of Court. However, Matrix has never provided any evidence a Notice of

Contract was posted at the Project site at any time.

On or about 5 February 2021, Matrix entered into an Equipment Piping

Insulation Subcontract with LandCoast Insulation, Inc. (LandCoast) for LandCoast

to perform certain insulation work for the Project for $1,506,826. On 13 April 2021,

LandCoast entered into a Purchase Order Agreement with Atlantech. Under the

Agreement, Atlantech, serving as a second-tier subcontractor, agreed to furnish

insulation and other related materials to the Project. Pursuant to the Purchase Order

Agreement, as LandCoast purchased materials on account for the Project, Atlantech

was to deliver the purchased materials to the Project. On or about 1 February 2021,

Atlantech provided a Notice to Lien Agent for its furnishing of materials on the

Project.

Pursuant to the Purchase Order Agreement, between March and July 2021,

LandCoast ordered and purchased a total of $762,724.74 in insulation and related

materials from Atlantech for use on the Project. For each of LandCoast’s material

-2- ATLANTECH DISTRIBUTION, INC. V. LAND COAST INSULATION, INC.

orders, Atlantech issued an invoice and sales order showing delivery of the materials

to the Project. As of 28 July 2021, Atlantech had delivered the full amount of

$762,724.74 in materials to the Project and had not received any payment from

LandCoast. Due to LandCoast’s failure to make payment, Atlantech served a Notice

of Claim of Lien Upon Funds by Subcontractor to Matrix, LandCoast, and Duke

Energy on 29 July 2021. Following LandCoast’s termination from the Project,

Atlantech agreed to continue providing insulation materials for Matrix’s work on the

Project and began directly assisting Matrix.

During the course of Matrix’s work on the Project, it submitted periodic

invoices to PNG for the labor and materials it had furnished in a given period. With

each invoice, Matrix also provided a Contractor’s Partial Lien Waiver and Release.

The partial lien waivers stated: “[Matrix], in consideration of payment in the amount

of $ [invoice amount] waives and releases its lien of any right which it now has or in

the future may have to claim a lien for Equipment provided or Services performed

prior to or during the period for which the Payment Invoice to which this Lien Waiver

and Release relates[.]” Matrix submitted the relevant invoices and partial lien

waivers on 19 July 2021, 16 September 2021, and 14 October 2021.1

1 During its tenure on the Project, LandCoast likewise issued partial lien waivers with its

invoices. However, LandCoast is not a party to this action, and Matrix’s partial lien waivers are the basis for Defendants’ claim.

-3- ATLANTECH DISTRIBUTION, INC. V. LAND COAST INSULATION, INC.

On or about 14 October 2021, Matrix posted a Release of Lien Bond with

Fidelity as surety in the amount of $953,408.43 to discharge Atlantech’s 29 July Lien

Upon Funds. Under the terms of the Bond, Fidelity agreed to ensure payment by

Matrix for the amount determined to be due in satisfaction of the 29 July Lien Upon

Funds, as well as any subsequent lien filed on the Project.

On 15 November 2021, Atlantech served a Notice of Claim of Lien Upon Funds

by Second-Tier Contractor–Supplement on LandCoast, Matrix, Duke Energy, and

PNG in the amount of $762,724.74 plus interest. The same day, Atlantech served a

Subrogation Claim of Lien on Real Property by Second-Tier Subcontractor

(Subrogation Lien on Real Property) on LandCoast, Matrix, Duke Energy, and PNG,

and it filed a copy with the Robeson County Clerk of Court. The Subrogation Lien on

Real Property was recorded with the Robeson County Clerk on 18 November 2021.

At the time Atlantech filed its Subrogation Lien on Real Property, Matrix was

continuing to send invoices and partial lien waivers to PNG for work performed on

the Project. On 14 October 2021, Matrix issued invoices to PNG for $822,110.83 and

$3,714,056.58. PNG paid both invoices on or around 2 December and 13 December

2021, respectively—after Atlantech had perfected its Subrogation Lien on Real

Property. On 23 November 2021, Matrix submitted an invoice to PNG for

$1,857,028.29, which PNG paid on 22 December 2021. On 14 January 2022, Matrix

submitted another invoice to PNG in the amount of $844,239.37, which PNG paid on

16 February 2022.

-4- ATLANTECH DISTRIBUTION, INC. V. LAND COAST INSULATION, INC.

On 14 January 2022, Atlantech filed a Complaint against Defendants asserting

a lien on real property, a claim of lien upon funds, and a claim against the Fidelity

bond Matrix had posted on 14 October 2021. On 9 March 2022, Fidelity and PNG

filed their respective Answers to the Complaint. On 25 March 2022, Matrix filed its

Answer, as well as a Counterclaim and Crossclaim. On 23 November 2022, Atlantech

filed a Motion for Summary Judgment on its claim for a lien against real property.

The same day, Defendants filed a Motion for Partial Summary Judgment seeking

dismissal of Atlantech’s claim for a lien against real property. The trial court heard

arguments on 14 December 2022.

On 9 March 2023, the trial court entered an Order granting Atlantech’s Motion

for Summary Judgment on its claim for a lien against real property and denying

Defendants’ Motion for Partial Summary Judgment with respect to Atlantech’s claim

for a lien against real property. On 10 April 2023, Defendants timely filed Notice of

Appeal. On 15 June 2023, the trial court granted Defendants’ Motion to Stay

Judgment Pending Appeal and Set an Amount of Undertaking pursuant to N.C. Gen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank H. Conner Co. v. Spanish Inns Charlotte, Ltd.
242 S.E.2d 785 (Supreme Court of North Carolina, 1978)
Rawls & Associates v. Hurst
550 S.E.2d 219 (Court of Appeals of North Carolina, 2001)
Craig Ex Rel. Craig v. New Hanover County Board of Education
678 S.E.2d 351 (Supreme Court of North Carolina, 2009)
Lafayette Transportation Service, Inc. v. County of Robeson
196 S.E.2d 770 (Supreme Court of North Carolina, 1973)
Electric Supply Co. of Durham, Inc. v. Swain Electrical Co.
403 S.E.2d 291 (Supreme Court of North Carolina, 1991)
Vulcan Materials Co. v. Fowler Contracting Corp.
433 S.E.2d 462 (Court of Appeals of North Carolina, 1993)
In Re the Will of Jones
669 S.E.2d 572 (Supreme Court of North Carolina, 2008)
Wachovia Bank National Ass'n v. Superior Construction Corp.
718 S.E.2d 160 (Court of Appeals of North Carolina, 2011)
Lunsford v. Mills
766 S.E.2d 297 (Supreme Court of North Carolina, 2014)
Midrex Technologies, Inc. v. N.C. Department of Revenue
794 S.E.2d 785 (Supreme Court of North Carolina, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Atlantech Distribution, Inc. v. Land Coast Insulation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantech-distribution-inc-v-land-coast-insulation-ncctapp-2024.