Atlanta, K. & N. Ry. Co. v. Southern Ry. Co.

153 F. 122, 82 C.C.A. 256, 1907 U.S. App. LEXIS 4385
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 2, 1907
DocketNo. 1,588
StatusPublished
Cited by5 cases

This text of 153 F. 122 (Atlanta, K. & N. Ry. Co. v. Southern Ry. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlanta, K. & N. Ry. Co. v. Southern Ry. Co., 153 F. 122, 82 C.C.A. 256, 1907 U.S. App. LEXIS 4385 (6th Cir. 1907).

Opinion

LURTON, Circuit Judge,

after making the foregoing statement, delivered the opinion of the court.

This is a litigation between two competing railway companies over the question of priority to a right of way desired by each for the purpose of constructing a spur, whereby certain manufacturing plants on the bank of the Tennessee river, at Knoxville, Tenn., might be served. The steps taken by each to obtain that part of the only direct route are fully stated in the opinion of this court, reported 131 Fed. 666, 66 C. C. A. 601. The former hearing was upon the pleadings and exhibits and a volume of affidavits and counter affidavits. We then held that the Southern Railway Company had obtained the prior right over the land of S. B. Luttrell through priority of contract with the owner, and this conclusion was again reached by the court below upon full evidence. The essential facts of the controversy, as presented by this transcript, are so materially identical with those found in the former as not to demand any further restatement of the case or reconsideration of the conclusions we tiren reached. The first, second, third, and fourth assignments of error, which alone challenge the conclusion of fact as to the priority of right of the Southern Railway Company, are therefore overruled.

The remaining assignments involve questions not necessarily precluded by the fact of the priority of right found in favor of the appellee company. The first of the questions covered by the assignments of error referred to is that the court erred in requiring the Atlanta, Knoxville & Northern Railway Company to deliver possession of the disputed right of way and desist from interfering with the use and occupation of same by that company. The ground upon which error is predicated is that pending this suit, and while the Southern was excluded from the occupation of the right of way in dispute, it had abandoned this route and constructed its spur upon another and different route, and by this alternate route had reached and was serving the manufacturing plants which it originally purposed to reach by the disputed line. Intervening between the main line of the railway of each of the antagonistic companies, and the lands occupied by the industries negotiating with both for the construction of a spur for their private use, lay a body of land abutting on the Tennessee river owned by Mr. S. B. Luttrell. The industries desiring the spur proposed to furnish the company with which it should first agree a right of way across this Luttrell land. The only direct or feasible way was at the foot of a bluff on this land and along the bank of the river. The industries came first to an agreement with the Southern, and procured from Luttrell a deed to this coveted right of way, a way apparently too narrow to be used by both companies. After the Southern had come to an agreement, and after Luttrell had executed a deed to the Southern of the right of way, and while it was in the hands of a representative of the industries, but unregistered, the Atlanta, Knoxville & Northern- Railway Company commenced a condemnation proceeding against Luttrell. Upon the strength of this fact and of a preliminary survey, it put a force of men at work upon this Luttrell right' of way. Upon the same day, and perhaps, or almost, simultaneously with the action of the Atlanta, Knoxville & Northern Railway Company, [124]*124the Southern likewise took possession of part of the same route. At this juncture the present bill was filed in a state chancery court, and an ex parte injunction was allowed excluding the Southern from the disputed route and from interfering with the occupation of the Luttrell right of way by the Atlanta, Knoxville & Northern Railway Company. At a later hour of the same day, a like bill was filed in same court by the Southern Railway Company, and an ex parte injunction obtained stopping the activities of the Atlanta, Knoxville &■ Northern Railway Company. Some days later the chancellor denied a motion to dissolve the injunction restraining the Southern, but did dissolve the injunction restraining the Atlanta, Knoxville & Northern Railway Company. This action left the Atlanta, Knoxville & Northern Railway Company in possession, and it has since remained in possession, and has constructed a s.pur track over part of the disputed route under the protection of the interlocutory injunction. The case in which this injunction was allowed was later removed to the Circuit Court of the United States, and at a still later day the injunction dissolved, and an interlocutory injunction awarded the Southern. The decree awarding this was the subject of the first appeal already referred to.

The agreement between the Southern Railway Company and the industries, under which at an expense of several thousand dollars the latter had procured Luttrell to convey to the Southern Railway Company the right of way across his premises, obligated the former to at once construct and operate the proposed switch. When it found itself excluded from this route, it entered into a supplemental agreement, whereby "the industries agreed that the railway company might substitute an 'alternate line. This supplemental agreement recites that it is necessitated' by the pending litigation with the Atlanta, Knoxville & Northern Railway Company. The original agreement bore date of June 30, 1903, and this supplemental agreement was made September 1, 1903, and pending this suit. Pursuant to this later arrangement, the Southern Railway Company constructed a spur to certain marble quarries; the spur being about four miles in length. This spur paralleled the route originally projected as far as the location of the contracting industries, but was about 1,000 feet south of that line. From this quarry spur a lateral spur was constructed to reach the industries lying north and on the river. This spur is shown to have been quite inexpedient, as it crossed several traveled streets and roads, and was built in a public street for several hundred feet. The grade was bad, and the spur very expensive to operate, and not so convenient to some of the industries. To obtain the assent of one of the largest of the contracting industries, the appellee agreed to bear certain hauling expenses incident to the substitution of this alternate way “until such time as the Southern may secure control of its original line or arrange to make delivery of logs at the point contemplated in the original contract.”

That this “alternate” line, so far as the spur from the quarry line is concerned, was only a temporary expedient resorted to as a consequence of its wrongful exclusion by appellant from the right of way to which it had a deed, is most evident from all the circumstances in the case, including the very significant clause from the supplemental agreement [125]*125above quoted. It would be a most remarkable result if an expedient to which the conduct of the appellant has driven the appellee should upon mere evidence of the fact, and without any supplemental bill, be held sufficient evidence of an abandonment of the very right of way in litigation and a sufficient reason for denying the relief which the cross-bill plaintiff is otherwise plainly entitled to. The appellant itself is responsible for the nonuser of this right of way up to this time, and has protected its own wrongful possession by the processes of the court erroneously granted. The mere fact that the appellee has constructed a spur into these industries over a longer and more expensive route does not, under the circumstances, amount to serious evidence of an intent to abandon the more direct way from which it has been excluded. Abandonment of a irroperty right is always a question of intention.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anson v. Tietze
190 S.W.2d 193 (Supreme Court of Missouri, 1945)
Highway Const. Co. v. McClelland
14 F.2d 406 (Eighth Circuit, 1926)
Nelson v. Black Diamond Mining Co.
237 F. 264 (W.D. Kentucky, 1916)
Camp v. Field
189 F. 285 (U.S. Circuit Court for the Northern District of Georgia, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
153 F. 122, 82 C.C.A. 256, 1907 U.S. App. LEXIS 4385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlanta-k-n-ry-co-v-southern-ry-co-ca6-1907.