Atlanta Board of Education v. Oxford Building Services

220 S.E.2d 485, 136 Ga. App. 168, 1975 Ga. App. LEXIS 1285
CourtCourt of Appeals of Georgia
DecidedOctober 17, 1975
Docket50475
StatusPublished

This text of 220 S.E.2d 485 (Atlanta Board of Education v. Oxford Building Services) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlanta Board of Education v. Oxford Building Services, 220 S.E.2d 485, 136 Ga. App. 168, 1975 Ga. App. LEXIS 1285 (Ga. Ct. App. 1975).

Opinion

Pannell, Presiding Judge.

Oxford Building Services, Inc., brought an action against the Atlanta Board of Education seeking recovery of an alleged balance due for janitorial services and [169]*169supplies from "on or about July 24, 1968, through on or about August 27,1971.” By stipulation of the parties, the amount, the buildings and the contracts involved were agreed upon as hereinafter shown in the trial judge’s order to whom the case was submitted for trial without a jury. The controversy arises out of three types of contracts between the parties referred to as the five percent contract, the two percent contract, and the "formula” contract. We are not concerned with the formula contracts on the present appeal.

The question is whether these contracts, in providing a method of arriving at damages for a breach by the appellee was a provision for liquidated damages, which are recoverable by the appellant, or was a penalty, which is not recoverable by the appellant as against the appellee’s claim for janitorial services and supplies. See generally Sanders & Ables v. Carter, 91 Ga. 450 (17 SE 345); Tuten v. Morgan, 160 Ga. 90 (127 SE 143); Muller Bank Fixture Co. v. Georgia R. &c. Co., 145 Ga. 484 (89 SE 615); Sanders v. Carney, 118 Ga. App. 576 (164 SE2d 856); Mayor &c. of Washington v. Potomac Engineering &c. Co., 132 Ga. 849 (65 SE 80); Heard v. Dooley County, 101 Ga. 619 (28 SE 986); Mayor &c. of Brunswick v. Aetna Indemnity Co., 4 Ga. App. 722 (62 SE 475); Miazza v. Western Union Telegraph Co., 50 Ga. App. 521 (178 SE 764); Ocmulgee Building &c. v. Thomson, 52 Ga. 427.

The five percent contracts under "Reports and Payments” read: "The Contractor shall maintain a Performance Chart in duplicate, listing by room all of the periodic work required under this contract, and this chart shall be posted daily showing the work performed and the date of performance. The Performance Chart shall be subject to an inspection by the Supervisor at any time. At the end of each calendar month a duplicate of the completed Performance Chart shall be certified to by the foreman and Chief Officer of the contractor with a statement that, T certify the above to be true and correct.’ The certified Performance Chart shall be submitted to the Supervisor, together with an invoice for payment for work performed during the month.

"Upon receipt of the certified chart and invoice, a representative of the Supervisor, in company with the [170]*170contractor or an authorized representative, shall make thorough inspection of the buildings involved, and if it is found that the contractor has failed to carry out any provisions of the contract, the contractor will be notified of such failure and be given 24 hours from the time of notice to make the necessary corrections. If work found to be in default under this contract is not corrected to the satisfaction of the supervisor within 24 hours, the Atlanta Board of Education shall charge against the contractor damages in an amount equal to 5 per cent of the amount invoiced for monthly services for each additional 24 hours that the contractor fails to perform the work required.

"No payment shall be made to the contractor on the invoice submitted for service for the previous month until all terms of this contract have been complied with, and then such payment shall be limited to the amount remaining as due on the invoice after the deduction of damages provided herein.

"Payment on the invoice shall also be subject to cancellation provisions set forth elsewhere in these specifications.”

The two percent contracts under "Reports and Payments” read: "The Contractor shall maintain a negative Performance Chart in duplicate, supplied by the Operations Department, listing by general areas all of the periodic work required under this contract, and this chart shall be posted daily showing the work performed and the date of performance. The Performance Chart shall be subject to an inspection by the supervisor at any time. At the end of each calendar month a duplicate of the completed Performance Chart shall be certified to by the Foreman and Chief Officer of the contractor with a statement that 'I certify the above to be true and correct.’ The certified Performance Chart shall be submitted to the Supervisor, together with an invoice for payment for work performed during the month.

"Whenever a representative of the Department of Operations of the Atlanta Board of Education shall make a thorough monthly inspection of the buildings involved, and if it is found that the contractor has failed to carry out any provisions of the contract, the contractor will be notified of such failure and be given 24 hours from the [171]*171time of notice to make the necessary corrections. If work found to be in default under this contract is not corrected to the satisfaction of the Director of Operations within 24 hours, the Atlanta Board of Education shall charge against the contractor damages in an amount equal to two (2) percent of the amount invoiced for monthly services for each additional 24 hours that the contractor fails to perform the work required.

"When it is determined that the contractor has omitted or failed to perform any daily scheduled work in accordance with these specifications the Director of Operations will immediately notify the contractor of the condition and location of the deficiency. Contractor will then be allowed three (3) hours to make the correction. Should the contractor fail to complete all work or respond to the notification within the time allowed then the Director of Operations may have said work performed by Atlanta Board of Education personnel and charge back to the contractor all costs incurred.

"No payment shall be made to the Contractor on the invoice submitted for service for the previous month until all terms of this contract have been complied with, and then such payment shall be limited to the amount remaining, as due on the invoice after the deduction of damages provided herein.

"Payment on the invoice shall also be subject to cancellation provisions set forth elsewhere in these specifications.”

After hearing evidence on the circumstances surrounding the provisions of the contracts, which development received input from the bidders when the original contracts (five percent) were bid, as well as when the two percent contracts were substituted for the five percent contracts, and after considering numerous letters of default written to the appellee, and that where a notice of default was given and not corrected in twenty-four hours another notice was sent, and was sent each day thereafter until full compliance with the defects pointed out in the default letter had been met, the trial judge entered the following order:

"The above and foregoing case having come on for a trial before the Court, without a jury, evidence was [172]*172introduced and argument made by attorneys for both parties and the Court makes the following findings of fact and conclusions of law.
Findings of Fact
"1. That the parties and the subject matter of this law suit are subject to the jurisdiction of this Court.
"2. That beginning in July, 1968, the Plaintiff entered in several contracts with Defendant agreeing to provide specified janitorial services in certain public schools operated by Defendant for a fixed price payable monthly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanders v. Carney
164 S.E.2d 856 (Court of Appeals of Georgia, 1968)
American Photocopy Equipment Co. v. Lew Deadmore & Associates, Inc.
193 S.E.2d 275 (Court of Appeals of Georgia, 1972)
Ocmulgee Building & Loan Ass'n v. Thomson
52 Ga. 427 (Supreme Court of Georgia, 1874)
Sanders & Ables v. Carter
91 Ga. 450 (Supreme Court of Georgia, 1893)
Dart v. Southwestern Building & Loan Ass'n
27 S.E. 171 (Supreme Court of Georgia, 1896)
Heard v. Dooly County
28 S.E. 986 (Supreme Court of Georgia, 1897)
Mayor of Washington v. Potomac Engineering & Construction Co.
65 S.E. 80 (Supreme Court of Georgia, 1909)
Tuten v. Morgan
127 S.E. 143 (Supreme Court of Georgia, 1925)
Mayor of the City of Brunswick v. Ætna Indemnity Co.
62 S.E. 475 (Court of Appeals of Georgia, 1908)
Miazza v. Western Union Telegraph Co.
178 S.E. 764 (Court of Appeals of Georgia, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
220 S.E.2d 485, 136 Ga. App. 168, 1975 Ga. App. LEXIS 1285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlanta-board-of-education-v-oxford-building-services-gactapp-1975.