Atchison, Topeka & Santa Fe Railroad v. Lenz

35 Ill. App. 330, 1889 Ill. App. LEXIS 565
CourtAppellate Court of Illinois
DecidedFebruary 12, 1890
StatusPublished

This text of 35 Ill. App. 330 (Atchison, Topeka & Santa Fe Railroad v. Lenz) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atchison, Topeka & Santa Fe Railroad v. Lenz, 35 Ill. App. 330, 1889 Ill. App. LEXIS 565 (Ill. Ct. App. 1890).

Opinion

Moran, J.

This action was brought to recover damages alleged to have been sustained by appellees, by depreciating the market value of certain lots owned by them, by means of the erection of the viaduct on 18th street over the tracks of appellant, and those of the Alton and the Western Indiana railroads, and by reason of laying certain railroad tracks by appellant across 18th street and in Blackwell street. The trial before a jury resulted in a verdict against appellant for $10,000, and to reverse the judgment entered thereon this appeal is prosecuted.

The main question presented by the record, and the one which we deem controlling, for the purpose of this review, is whether, under the facts, the appellant is chargeable with any liability for damage to appellee’s property, caused by the building of the 18th street viaduct.

It is not contended by appellees that the viaduct or any part thereof was actually built by appellant, but it is claimed that a certain portion of the cost of the erection was paid by it, and that said fact, considered in connection with certain contracts made and ordinances passed by the city and accepted by appellant, were sufficient to charge appellant with liability for damage to property, resulting from the erection of the viaduct in the manner in which it was erected. The ordinances and contracts showing appellant’s relation to the erection of said viaduct are in substance as follows :

On September 15, 1879, the city passed an ordinance permitting the Chicago & Western Indiana Railroad Company to enter the city, cross intervening streets, etc., “ upon express condition that said company erect and maintain viaducts over such tracks or streets as the city council may require, and construct approaches to the viaducts, under the supervision of the department of public works, or other proper authority.”

The company was required to indemnify the city against all damages, judgments, etc., which may be recovered against it by reason of the privileges or authority granted.

In March, 1881, an ordinance was passed authorizing said Western Indiana Company to erect a viaduct at the east end of 18th street bridge; “work to be according to plans and specifications of the Department of Public Works, and to be under the superintendence and direction, and to the satisfaction of the Commissioners of Public Works of said city,” and viaduct to be maintained at the expense of the said company and city to be indemnified against damages resulting from exercise by the company of the privileges granted. On June 30, 1887, an order of the city council directed the commissioners of public works to notify the said railroad to erect and complete for public use a viaduct over the tracks and grounds of said company on 18th street, with necessary approaches, etc., said work to be completed by said company at such time during that year as the commissioners should indicate.

On August 10,1887, a contract was made between the Western Indiana Company and the city of Chicago, which recites the obligation of the said company as to the erection and maintenance of viaduct approaches, etc., at 18th street, under plans of the department of public works; that city is to build another bridge at 18th street; that the viaduct shall be constructed as indicated, upon plans attached and work done under control of department of public works; that contracts for said work shall be let by said department of public works, the company having first approved the same by indorsement; that company shall pay as its proportion of the costs one-sixth of the cost of the center pier of swing bridge, the entire cost of the work east of the east pier of bridge, viaduct piers, etc., and all other expenses connected with said construction to the end of said approach at the west curb line of Wentworth avenue, except so much as is to be paid by the Alton R. R. Co. The Western Indiana Company agrees to save the city harmless from any and all damages which may be recovered against it for damages to lots, lands or buildings resulting from the construction of said viaduct, piers, and the approaches thereto which lie east of the bridge.

On said August 10th, after the making of said last mentioned contract, the appellant entered into a contract with the Western Indiana Company which recites the said contract with the city, by which, among other things, the said C. & W. I. R. R. Co. has agreed to pay for the construction and maintenance of that portion of said viaduct extending east from the center of the first pier for said viaduct on the east side of Grove street about 138 feet east therefrom, “ and that said last named portion of said viaduct is so constructed especially for the benefit and advantage of” appellant as collateral to and in extension of the contract of lease between the Western Indiana Company and appellant; therefore appellant agrees to pay from time to time to said Western Indiana Company the entire expense of construction and maintenance of “ one-half of the pier made to support said viaduct on the easterly side of Grove street, and one-half of the abutment supporting the approach to said viaduct, which is about 138 feet east thereof, and the entire cost of the superstructure of said viaduct between said pier and abutment,” and the contract goes on to specify the time and manner of payment. It appears from the evidence introduced by appellee that the plans for the building of the viaduct were completed and on file in the office of the city engineer in the fall of 1886; that some changes were made therein before the construction, but no alteration in the steepness of grade and no change from Wentworth avenue asa starting point, and’it is also shown by appellee, and is without contradiction, that the work was in fact done by the city under the direction of the city engineer and in pursuance of the contract between the city and the Western Indiana Company, the material portion of which we have heretofore stated. There is no evidence in the case tending to show that the construction of the viaduct from the east side of Grove street to the east side of Blackwell street in the manner desired by appellant, extended the starting point of the viaduct to Wentworth avenue, or in any degree increased the injurious effect of the viaduct upon appellees’ property beyond what it would have been if it had not been constructed between such points in such manner as to allow the land between these points to be used for appellant’s tracks. The claim is purely and simply that because such portion of the viaduct was constructed in the manner in which appellant desired, and because, in consideration thereof, it agreed to pay a part of the cost of the construction between those two points, it has become liable for the damage done to appellees’ property, situated a block east, though the viaduct would have had the same relation to, and effect upon, appellees’ property if it had been built in some other manner between the east side of Grove street and the east side of Blackwell street, than the manner in which, at appellant’s request, it -was constructed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Culbertson & Blair Packing & Provision Co. v. City of Chicago
111 Ill. 651 (Illinois Supreme Court, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
35 Ill. App. 330, 1889 Ill. App. LEXIS 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atchison-topeka-santa-fe-railroad-v-lenz-illappct-1890.