Assembly v. Public Utilities Commission

906 P.2d 1209, 12 Cal. 4th 87, 48 Cal. Rptr. 2d 54, 95 Daily Journal DAR 16776, 95 Cal. Daily Op. Serv. 9667, 1995 Cal. LEXIS 7015
CourtCalifornia Supreme Court
DecidedDecember 18, 1995
DocketS044844
StatusPublished
Cited by8 cases

This text of 906 P.2d 1209 (Assembly v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Assembly v. Public Utilities Commission, 906 P.2d 1209, 12 Cal. 4th 87, 48 Cal. Rptr. 2d 54, 95 Daily Journal DAR 16776, 95 Cal. Daily Op. Serv. 9667, 1995 Cal. LEXIS 7015 (Cal. 1995).

Opinion

*90 Opinion

GEORGE, J.

this case, we must determine the validity of an order, issued by the California Public Utilities Commission (Commission) in January 1995, directing the disposition of funds (then exceeding $50 million) that had been deposited by Pacific Telesis into a designated account pursuant to a November 1993 order of the Commission. In the latter decision, the Commission found that Pacific Bell, a subsidiary of Pacific Telesis, improperly failed to refund to its customers $7.9 million ordered refunded a decade earlier. As a consequence of Pacific Bell’s wrongful withholding of the refund, the Commission ordered Pacific Telesis to pay, into a designated account, $7.9 million plus interest at the rate of 18 percent per year, compounded monthly, from September 1, 1983, through the date of payment into the account. The November 1993 decision of the Commission, however, did not order that the funds that were to be deposited by Pacific Telesis be distributed directly to Pacific Bell’s customers. Instead, the Commission reserved judgment on that question, indicating that, because the current Pacific Bell ratepayers were not necessarily those who had paid the rates upon which the refund was based, the Commission, as a matter of “equity,” “may prefer to disburse this refund in a manner which will more broadly benefit Californians.”

Shortly after the November 1993 order was issued, Pacific Telesis complied with the order and deposited into a designated account (the Pacific Telesis account) the sum of approximately $50 million ($7.9 million principal, plus $42.1 million interest).

Thereafter, the Commission held hearings on the appropriate disposition of the money in the Pacific Telesis account. After initially adopting one disposition in August 1994, the Commission, in response to several rehearing petitions, modified that approach in January 1995 and entered the order that is challenged in the present proceeding. In its January 1995 decision, the Commission ordered disbursement of the sum of approximately $11.6 million to the current customers of Pacific Bell (the refund principal of $7.9 million, plus interest on that amount calculated at a rate of 3.4 percent per year, compounded monthly, from September 1, 1983 [approximately $3.7 million in interest]). With regard to the balance of the Pacific Telesis account (which at the time amounted to more than $42 million), the Commission ordered that such funds be “allocated toward school telecommunications infrastructure development and consumer education.”

*91 The petition for writ of review filed in this court in the present proceeding, 1 challenging the validity of the Commission’s January 1995 order, maintains that the Commission violated section 453.5 of the Public Utilities Code 2 in failing to order a refund of the entire amount of the Pacific Telesis refund account to Pacific Bell customers. The petition further asserts that, in diverting a portion of these funds for a different, public use of its own choosing, the Commission improperly invaded the legislative domain of taxation and appropriation.

As we shall explain, we conclude that the Commission’s January 1995 order violates section 453.5 and therefore should be set aside.

Background

In February 1993, the Commission instituted an investigation of a proposal by Pacific Telesis to “spin off’ a number of its “wireless subsidiaries” (including PacTel Cellular, PacTel Paging, and Pacific Telesis International) into a separate corporation, to be known as PacTel Corporation. In the course of its investigation of the proposed spinoff (and the conditions, if any, that should be imposed upon its approval of the proposal), the Commission determined that the Pacific Bell ratepayers were entitled to a monetary reimbursement from Pacific Telesis (Pacific Bell’s parent corporation), because the utility improperly had retained funds that should have been refunded to its ratepayers under a 1982 order of the Federal Communications Commission (FCC).

As the Commission explained in its November 1993 decision, in approving a proposal of American Telephone and Telegraph (AT&T) to capitalize a cellular subsidiary (AT&T Cellular), the FCC in 1982 had ordered AT&T to reimburse all of the Bell Operating Companies (including Pacific Bell) for certain cellular research and development expenses, explicitly directing that all expenses incurred prior to June 30, 1982, “must be reimbursed to ratepayers” who had absorbed these costs through the rates they had been charged. In September 1983, pursuant to the FCC order, AT&T paid to Pacific Bell a reimbursement of $7.9 million. Instead of refunding this amount to its ratepayers (as the FCC had directed), however, Pacific Bell unilaterally determined that the refund was not one that it was required to “pass through” to its ratepayers, and, in the words of the Commission, improperly “pocketed” the refund.

In its November 1993 decision, the Commission specifically found “that the reimbursed funds were intended by both the FCC and this Commission to *92 be refunded to PacBell ratepayers and were not so refunded.” As a consequence, the Commission concluded that its approval of the Pacific Telesis spinoff proposal should be conditioned, among other matters, upon a requirement that Pacific Telesis “pay to PacBell all principal payments with compound interest no later than 30 days after the date of this decision."

With regard to the rate of interest to be assessed on the unpaid refund, the Commission observed that conventionally the Commission had designated “the short term commercial paper rate” as the rate of interest that it charged on refunds that had been owing to ratepayers over a period of time. The Commission concluded, however, that a higher interest rate was appropriate in the present case, because Pacific Bell had disregarded the FCC order and, instead of refunding to its ratepayers the reimbursement moneys received from AT&T, had retained them, allowing the company the use of the moneys in the intervening years. The Commission concluded that, under the circumstances, an appropriate rate of interest would be the rate that Pacific Bell had charged its customers with delinquent accounts for late payments during this same period—18 percent per annum (1.5 percent per month), compounded monthly. The Commission further noted that Pacific Bell’s return on its equity investment fluctuated between 13 percent and 16 percent, and that an interest rate representing 2 to 5 percentage points above its return on such investment was reasonable. Accordingly, the Commission ordered that interest accrue at the rate of 18 percent, from September 1,1983 (the date Pacific Bell received the $7.9 million from AT&T) until payment was made by Pacific Telesis to Pacific Bell. It was further ordered that, once deposited by Pacific Telesis in an interest-bearing account, the funds accrue interest at the lower, short-term commercial paper rate.

The Commission declined to order immediate distribution of the refund to Pacific Bell’s customers, however, explaining: “[W]e hesitate to order the refund directly through to ratepayers at this time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BNSF Railway Co. v. Public Utilities Commission
218 Cal. App. 4th 778 (California Court of Appeal, 2013)
PG&E Corp. v. Public Utilities Commission
13 Cal. Rptr. 3d 630 (California Court of Appeal, 2004)
Southern California Edison Co. v. Peevey
74 P.3d 795 (California Supreme Court, 2003)
Farmland Industries, Inc. v. Kansas Corporation Comm'n
37 P.3d 640 (Court of Appeals of Kansas, 2001)
Carmel Valley Fire Protection District v. State
20 P.3d 533 (California Supreme Court, 2001)
Superior Court v. County of Mendocino
913 P.2d 1046 (California Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
906 P.2d 1209, 12 Cal. 4th 87, 48 Cal. Rptr. 2d 54, 95 Daily Journal DAR 16776, 95 Cal. Daily Op. Serv. 9667, 1995 Cal. LEXIS 7015, Counsel Stack Legal Research, https://law.counselstack.com/opinion/assembly-v-public-utilities-commission-cal-1995.