Aspinwall v. City of Boston

78 N.E. 103, 191 Mass. 441, 1906 Mass. LEXIS 1298
CourtMassachusetts Supreme Judicial Court
DecidedMay 15, 1906
StatusPublished
Cited by13 cases

This text of 78 N.E. 103 (Aspinwall v. City of Boston) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aspinwall v. City of Boston, 78 N.E. 103, 191 Mass. 441, 1906 Mass. LEXIS 1298 (Mass. 1906).

Opinion

Knowlton, C. J.

The first of these suits is an action of contract, brought to recover the amount of an award of damages made by the board of street commissioners of Boston for taking land for a public street. Jersey Street was laid out and ordered to be constructed by an order of the street commissioners, on July 15,1898, and these plaintiffs were awarded damages in the sum of $14,382. On September 22,1898, the city entered upon the land for the purpose of constructing the street, and began the work of filling, which was completed on December 17, 1898. The street has never been completed in accordance with the order of the commissioners. No gutters, cross walks or sidewalks have been built, and no macadam has been put upon the roadway, but the roadway has been left open and unobstructed, and has been used by persons desiring to pass through it, since January 1,1899. These facts entitle the plaintiffs to receive the amount of the award, unless their action is barred by a contract [444]*444signed by them and others on March 25,1897, as follows: “We the undersigned owners of land within the lines of a proposed street running at right angles with Boylston Street extension at a width of fifty feet from Audubon Road to Brookline Avenue, and being at its intersection with Boylston Street extension seven hundred thirteen feet more or less distant from Boylston Road as shown on a plan marked 6 Back Bay Lands, Pierre Humbert, Jr., City Surveyor, April 10, 1894,’ on file in the office of the city engineer of said city, in consideration of the immediate laying out and construction of said proposed street at the width of fifty feet, under the provisions of chapter 323, of the Acts of the year 1891, and acts in amendment or addition thereto, and of any assessments which may be levied upon our several estates for the cost of said laying out and construction being delayed until the damages caused to us severally by the taking of said land and the cost of the construction of said street shall be determined, and of said damages being offset against the proportionate part of said cost which may be levied upon our respective estates, agree that the payment for said damages shall be delayed until the balance due from us severally after making said offset has been determined.

“ And we severally agree that we will accept as payment for so much of our said land to be taken for said street as lies within one hundred and twenty-five feet of said Audubon Road the sum of $3.00 per square foot and for so much of our said land as lies within one hundred and twenty-five feet of said Boylston Street extension the sum of $2.00 per square foot and for so much of our said land as lies within one hundred and twenty-five feet of Brookline Avenue the sum of $1.50 per square foot and for so much of our said land as lies within one hundred and twenty-five feet of Peterborough Street or within one hundred and twenty-five feet of Queensberry Street the sum of $1.50 per square foot and for the rest of our said land the sum of $1.00 per square foot. It being stipulated that the execution of this paper by any owner upon any copy of this agreement shall be tantamount to the execution of this original agreement, and that each owner signing this agreement makes no undertaking for anybody other than himself. Witness our hands and seals this twenty-fifth day of March, A. D. 1897.” (Signed and sealed.)

[445]*445The betterments have not been assessed, and the question is whether the plaintiffs are bound by this contract to delay the collection of their damages until the betterments can be offset. Water pipes were laid in the street in accordance with the order of the street commissioners, in the autumn of 1899. It is agreed that, allowing a reasonable time for surfacing and building the street, it could have been finished by the city as soon as January 1, 1900. A sewer, constructed through the street as ordered, was finished on December 17,1903.

The fundamental question is whether the contract was of a kind that, upon acceptance by the city, might become binding upon the parties. It was not signed by any one representing the city of Boston, and no one had authority to make a contract for the city to do the things referred to in the writing. A street can be laid out and constructed only upon an adjudication of a tribunal acting officially, and determining that the public convenience and necessity require it to be laid out as a street. See Somerville v. Dickerman, 127 Mass. 272; Parks v. Boston, 8 Pick. 218. But a unilateral contract, offering to the city favorable terms as to land damages as an inducement to the laying out of a street, may be considered by the board charged with the duty of dealing with such matters, and may be accepted and made binding, by performance of that which is referred to in it as its consideration. Crocket v. Boston, 5 Cush. 182. White v. County Commissioners, 2 Cush. 361. Boston v. Simmons, 9 Cush. 373. Bell v. Boston, 101 Mass. 506. Atkinson v. Newton, 169 Mass. 240, 242, and cases cited. Bartlett v. Boston, 182 Mass. 460.

There is no doubt, in the present case, that the board of street commissioners acted upon this contract in making the order, and to that extent accepted it. They assessed the land damages according to the provisions of the contract. If the construction had been finished seasonably in pursuance of the provisions of the writing, there would have been a complete acceptance by performance, which would have bound the city, as well as the plaintiffs, provided the contract is such as the representatives of the city had a right to make. First National Bank v. Watkins, 154 Mass. 385. Wellington v. Apthorp, 145 Mass. 69, 73. Cottage Street Church v. Kendall, 121 Mass. 528. In regard [446]*446to the nature of the contract in this particular, the only ground for doubt is as to those provisions which require postponement of the collection of betterments until the damages caused to the several signers of the writing shall be determined, and prescribe a set-off of the damages against the betterments. This arrangement is not within the language of the R. L. c. 50, § 11, which authorizes an agreement for the assumption of the betterments by the city or town upon a release of the damages on terms agreed upon, but it resembles such an agreement, although it does not require the city to give up anything important. Where a city or town would have the advantage of delay in paying the damages, and of an agreement to accept a stated sum as damages, an arrangement that betterments and damages shall be set off against each other is not objectionable, provided the lien for betterments is preserved. Inasmuch as the street commissioners assessed the damages according to the terms of the agreement and the city authorities have carried the construction of the street almost to completion, we see no such risk of loss from the postponement of the collection of the betterments -until the amount of the damages to these subscribers and the cost of the construction shall be determined, as should make the contract illegal. Upon such an assessment of damages under such an agreement as to the mode of assessing them, it is not possible that litigation to determine the amount could arise and be protracted in the courts. The statute postpones an assessment of betterments until after the construction has been completed, (R. L. c. 50, § 1,) and there need be no considerable delay in ascertaining the cost of construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sturdy v. Planning Board
586 N.E.2d 11 (Massachusetts Appeals Court, 1992)
Radnor Township School District v. Valley Forge Military Academy Foundation
59 Pa. D. & C.2d 768 (Delaware County Court of Common Pleas, 1970)
Department of Public Welfare v. Town of Billerica
213 N.E.2d 392 (Massachusetts Supreme Judicial Court, 1966)
Henry v. Lipman
8 Mass. App. Div. 107 (Mass. Dist. Ct., App. Div., 1943)
Kirchner v. City of Pittsfield
44 N.E.2d 634 (Massachusetts Supreme Judicial Court, 1942)
Inhabitants of Southborough v. Boston & Worcester Street Railway Co.
145 N.E. 422 (Massachusetts Supreme Judicial Court, 1924)
Capen v. Capen
234 Mass. 355 (Massachusetts Supreme Judicial Court, 1920)
King v. City of Springfield
124 N.E. 426 (Massachusetts Supreme Judicial Court, 1919)
Notkins v. Pashalinski
76 A. 1104 (Supreme Court of Connecticut, 1910)
Burrage v. City of Boston
84 N.E. 1017 (Massachusetts Supreme Judicial Court, 1908)
Boston Water Power Co. v. City of Boston
80 N.E. 598 (Massachusetts Supreme Judicial Court, 1907)
Averill v. City of Boston
80 N.E. 583 (Massachusetts Supreme Judicial Court, 1907)
Whitcomb v. City of Boston
78 N.E. 407 (Massachusetts Supreme Judicial Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
78 N.E. 103, 191 Mass. 441, 1906 Mass. LEXIS 1298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aspinwall-v-city-of-boston-mass-1906.