Ashley v. City of Lexington

704 S.E.2d 529, 209 N.C. App. 1, 2011 N.C. App. LEXIS 60
CourtCourt of Appeals of North Carolina
DecidedJanuary 4, 2011
DocketCOA10-314
StatusPublished

This text of 704 S.E.2d 529 (Ashley v. City of Lexington) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ashley v. City of Lexington, 704 S.E.2d 529, 209 N.C. App. 1, 2011 N.C. App. LEXIS 60 (N.C. Ct. App. 2011).

Opinion

McGEE, Judge.

This case is before our Court on appeal from a judicial review of three annexation ordinances (the ordinances) by the Superior Court of Davidson County. By agreement of the parties, all three appeals have been combined for hearing. The parties to this appeal are the City of Lexington, North Carolina (Respondent) and certain residents and owners of property located in the three areas Respondent sought to annex (Petitioners). Respondent and *4 Petitioners appeal orders partially granting and partially denying both parties’ motions for summary judgment.

Respondent passed a resolution on 14 April 2008 (the resolution) declaring its intent to annex three areas of land bordering Respondent. These areas are known as the Old Salisbury Road Annexation Area, the East Center Street Annexation Area, and the Biesecker Road Annexation Area (collectively, the annexation areas). The East Center Street Annexation Area includes a land bridge connecting the developed area to be annexed to the city boundary. By statute, the land bridge in the East Center Street Annexation Area cannot exceed twenty-five percent of the total area to be annexed, and must be adjacent on at least sixty percent of its boundary to a combination of the city boundary and the developed portion of the annexation area. All three annexation areas (excluding the land bridge) are developed but lack sewer service. The resolution described the areas to be annexed by metes and bounds descriptions that rely, in part, on thirteen-digit tax identification numbers for certain lots in the area, to locate points on the boundary of the areas to be annexed. The resolution further relied on four maps and stated that the Davidson County Clerk’s Office had additional maps and a list of people identified as owning property in the annexation areas. Respondent sent notice of the resolution to every known property owner in the annexation areas and published the resolution and maps twice in the local newspaper.

Respondent adopted a report (the report) on the annexations and made it available to the public on 28 April 2009. Twenty-three maps of the annexation areas were included in the report. The report also included a plan for extending sewer services to the annexation areas. Respondent held a public meeting to explain the report and respond to questions on 3 June 2008. Respondent then held a public hearing on the annexations on 8 July 2008.

Respondent adopted the three ordinances on 21 July 2008. The ordinances contained the same descriptions of the areas to be annexed as those included in the resolution, and also partially relied on the thirteen-digit tax record numbers to help locate the boundaries of the annexation areas. The ordinances were to be effective as of 30 June 2009, but were stayed pending the outcome on appeal.

N.C. Gen. Stat. § 160A-47(3)(c) (2009) provides that, if construction of sewer outfall lines is required, construction must be completed within two years of the effective date of annexation. *5 Secondary lines or extensions — those connecting the main outfall lines to developed property — are to be built “according to the policies in effect in such municipality for extending water and sewer lines to individual lots or subdivisions.” N.C.G.S. § 160A-47(3)(b).

According to Respondent’s existing policy, residents may petition Respondent for sewer connection. Should Respondent not have funds available to complete the request, Respondent may either deny the petition or negotiate with the petitioning residents in order to reach an agreement on payment for the connection. Historically, prior to the start of any work on a connection, Respondent has required petitioners to pay a percentage of the connection costs, ranging from fifty percent to one hundred percent of the costs.

For the three newly-annexed areas, Respondent committed to building all secondary lines at Respondent’s expense within five years of annexation. Annexation residents were allowed to petition for accelerated sewer lines but Respondent had no funds budgeted for the costs of accelerated connection. Therefore, Respondent could either deny the request or negotiate connection costs with Petitioners. Respondent provided residents with printed request forms for accelerated sewer requests. The forms required residents to pay fifty percent of the connection costs in advance of construction and within fourteen days of being notified of the costs. If these terms were not met, Respondent would deny the accelerated sewer requests and connections would be established, without cost to residents, within five years of annexation.

A group opposing the annexation, Citizens United Against Forced Annexation, had residents place a sticker on the printed forms that stated: “I agree to the same water/sewer extension policy that is in effect for City residents pursuant to N.C. Gen. Stat. 160A-47(3)(B).” Respondent refused to accept forms bearing the stickers and so notified residents. After being informed of the denial of forms bearing the stickers, a group of residents went to City Hall and removed the stickers. Respondent still refused to accept any form that at one time had a sticker placed on it. Residents who submitted forms with the stickers were provided with new forms and were told they would need to fill out the new forms in order to request accelerated sewer services.

According to the report, by 15 July 2008, Respondent had received “148 valid forms signed by property owners within the annexation areas requesting that residential .sewer line extensions be accelerated to be made available within two years of the effective *6 date of annexation].]” Once Respondent received the forms, its Public Works Division calculated the costs of the connection and sent contracts to the property owners. The executed contracts, along with fifty percent of the costs, were to be returned within fourteen days. None of the residents who were notified of the costs sent Respondent an executed contract or payment. Therefore, Respondent did not schedule expedited sewer service connections for any property within the annexation areas.

Petitioners filed three petitions in Davidson County Superior Court seeking judicial review of the ordinances on 15 September 2008. Petitioners challenged the boundary descriptions of the areas to be annexed, alleging that the boundary descriptions were not proper metes and bounds descriptions. Petitioners further argued that Respondent’s requiring fifty percent of payment of the costs of sewer service connections within fourteen days was not part of Respondent’s existing policy regarding extension of sewer lines because this method constituted neither a rejection nor a negotiation.

Both parties moved for summary judgment on 9 November 2009.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matheson v. City of Asheville
402 S.E.2d 140 (Court of Appeals of North Carolina, 1991)
In Re Annexation Ordinance D-21927 Adopted by City of Winston-Salem
278 S.E.2d 224 (Supreme Court of North Carolina, 1981)
Forsyth Citizens Opposing Annexation v. City of Winston-Salem
312 S.E.2d 517 (Court of Appeals of North Carolina, 1984)
City of Kannapolis v. City of Concord
391 S.E.2d 493 (Supreme Court of North Carolina, 1990)
Burnette v. City of Goldsboro
654 S.E.2d 834 (Court of Appeals of North Carolina, 2008)
Hall v. City of Asheville
664 S.E.2d 77 (Court of Appeals of North Carolina, 2008)
Pinewild Project Ltd. Partnership v. Village of Pinehurst
679 S.E.2d 424 (Court of Appeals of North Carolina, 2009)
Sonopress, Inc. v. Town of Weaverville
562 S.E.2d 32 (Court of Appeals of North Carolina, 2002)
In Re Annex. Ord. No. 1219 Adopt. by Asheville
303 S.E.2d 380 (Court of Appeals of North Carolina, 1983)
Huyck Corp. v. Town of Wake Forest
356 S.E.2d 599 (Court of Appeals of North Carolina, 1987)
In Re City of Durham Annexation Ordinance Numbered 5991 for Area A
316 S.E.2d 649 (Court of Appeals of North Carolina, 1984)
Brown v. City of Winston-Salem
614 S.E.2d 599 (Court of Appeals of North Carolina, 2005)
Norwood v. VILLAGE OF SUGAR MOUNTAIN
667 S.E.2d 524 (Court of Appeals of North Carolina, 2008)
Nolan v. Village of Marvin
624 S.E.2d 305 (Supreme Court of North Carolina, 2006)
Nolan v. Town of Weddington
642 S.E.2d 261 (Court of Appeals of North Carolina, 2007)
In re Annexation Ordinance Adopted by the City of New Bern
180 S.E.2d 851 (Supreme Court of North Carolina, 1971)
Blackwell v. City of Reidsville
502 S.E.2d 371 (Court of Appeals of North Carolina, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
704 S.E.2d 529, 209 N.C. App. 1, 2011 N.C. App. LEXIS 60, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ashley-v-city-of-lexington-ncctapp-2011.