Ash Grove Lime & Portland Cement Co. v. Moran Construction Co.

296 N.W. 761, 139 Neb. 176, 1941 Neb. LEXIS 45
CourtNebraska Supreme Court
DecidedMarch 7, 1941
DocketNo. 30928
StatusPublished
Cited by1 cases

This text of 296 N.W. 761 (Ash Grove Lime & Portland Cement Co. v. Moran Construction Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ash Grove Lime & Portland Cement Co. v. Moran Construction Co., 296 N.W. 761, 139 Neb. 176, 1941 Neb. LEXIS 45 (Neb. 1941).

Opinion

Landis, District Judge.

The Ash Grove Lime & Portland Cement Company, a corporation, appellee, obtained below a judgment for $26,181 on a contract bond against the Moran Construction Company, a corporation, as principal, and the Continental Casualty Company, a corporation, as surety. The Continental Casualty Company, appellant, alone appeals therefrom.

The facts are: The Moran Construction Company entered into a written contract with the department of public works of the state of Nebraska for the construction of a highway, and agreed therein, among other things, “to pay all just claims for material, supplies, tools, machinery and labor, and all other just claims filed against it or any of its subcontractors in carrying out the provisions.” To secure the faithful performance of this contract, the Moran Construction Company, as principal, and the Continental Casualty Company, as surety, executed and delivered to the state their contract bond providing therein, among other things: “It is expressly understood and agreed that this bond is given to secure and does secure not only the faithful performance by the principal herein named of said contract for the construction work as specified in said contract and in strict accordance with the terms of said contract and the plans and specifications thereto attached and made a part thereof, but that it is given to secure and does secure also the payment by the said bounden Moran Construction Company of all just claims for materials, lubricants, oil and gasoline used or consumed in the construction of the work.”

The Moran Construction Company entered into a written contract with the Ash Grove Lime & Portland Cement Company to purchase the cement necessary to carry out the highway construction project. In accordance therewith, cement was delivered and used in the project. Out of the [178]*178proceeds of the project, various sums were paid to the appellee cement company by the Moran Construction Company, some of which were credited on the cement purchased. Two such payments in amounts of $5,029.15 and $15,970.85, totaling $21,000, were not credited on the cement purchased, but by specific direction written in the checks the Moran Construction Company ordered the cement company, appellee, to apply them in payments of notes due appellee on other construction contracts than that covered by the contract bond as is shown by the checks themselves reproduced in appellee’s brief. Appellee knew the source of the funds received by it in payment of the indebtedness for the cement purchased on the paving project, and of the $21,000 on notes not connected with said project, to be from payments by the state of Nebraska on the paving project covered by the bond upon which appellant is surety.

When the paving project was completed, appellee claimed that there was $18,746.10 due it for cement used in the paving project and the further sum of interest computed on items not paid within 30 days of invoice, amounting to $3,226.27, and also interest on the $18,746.10 from March 1, 1936, at 6 per cent., totaling the judgment obtained herein of $26,181 by the appellee against the Moran Construction Company as principal and Continental Casualty Company as surety. Neither appellant nor appellee have any procedural problems.

Appellee, though there is no bill of exceptions in this case, reproduces the two checks in its brief sustaining the first affirmative defense of the surety which was erroneously stricken below. It is apparent from the record that there is upon the part of all counsel a commendable attempt to submit all the facts, leaving for the court only a question of law to determine.

The controlling proposition for decision is: Where a contractor owes to the same creditor several debts growing out of various construction contracts, one of which is secured by a bond, has the surety on such bond a legal right to have any payment made by the contractor, principal on [179]*179such bond, from funds derived from such contract applied in satisfaction of the debt created under such contract, in preference to any other indebtedness of the contractor to such creditor, where the creditor knows the source of such funds ?

Ordinarily, where the debtor directs the application of payments, the creditor must comply with the direction. Should the additional situation that the surety has some interest or equity in the funds with which the debtor makes payment to the creditor who has knowledge of the source thereof furnish an exception to this rule and allow the surety to insist that at least such payments shall be made to discharge the assured debt?

With us it is a matter of first impression and in considering the cases of other jurisdictions we find them in hopeless conflict. On analysis they may be said to fall into two main classes, one where they allow the surety to apply and control such payments, and the other where such right is refused the surety. The cases which allow control are divided into two classes, one allows control by the surety in every case, and the other allows application only where the creditor knows the source of the funds.

The courts which allow control despite knowledge by the creditor of the source of the funds place their decision on the ground of the equitable interest of the surety. Emphasis is made of the fact that money received from the contract upon which the surety is liable should be applied on the contract obligations upon which such surety can be held. Columbia Digger Co. v. Rector, 215 Fed. 618; Columbia Digger Co. v. Sparks, 227 Fed. 780; Sioux City Foundry & Mfg. Co. v. Merten, 174 Ia. 332, 156 N. W. 367.

The courts which refuse to allow the surety to direct application of the payments unless the creditor knew the source of the funds seem to reason by analogy that the surety’s interest resembles somewhat of the cestui in a constructive trust, where the contractor assumes the position of trustee and the contract funds the trust res. Thacker v. Bullock Lumber Co., 140 Ky. 463, 131 S. W. 271; [180]*180Sturtevant Co. v. Fidelity & Deposit Co., 92 Wash. 52, 158 Pac. 740.

There are the opposing views, where it is held that the surety has no right to apply and control the payments of the contractor to the creditor, even where such creditor has full knowledge of the source of the payment and of the surety relation. Grover v. Board of Education, 102 N. J. Eq. 415, 141 Atl. 81; Standard Oil Co. v. Day, 161 Minn. 281, 201 N. W. 410, 41 A. L. R. 1291. In commenting on this last case in the note in 41 A. L. R. 1298, it is suggested in relation thereto: “When, as in the reported case, the secondary creditor knew the source of the funds with which the secondary payment was made, the weight of authority seems to support the right of the person making the original payment (or one in the same position) to insist upon an. application of the secondary payment which will protect him, or his property; or, at least, upon that hypothesis it cannot be said affirmatively to support the contrary view which is taken in the reported case.” There are certain situations where equitable principles may be applied that relax the strict rules. This is true in our state in the materialman’s lien cases for materials furnished a contractor for erection of buildings and the liability of the owner is considered. Crane Bros. Mfg. Co. v. Keck, 35 Neb. 683, 53 N. W. 606; Boyer-Van Kuran Lumber & Coal Co. v. Colonial Apartment House Co., 94 Neb. 180, 142 N. W. 519; Lee v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
296 N.W. 761, 139 Neb. 176, 1941 Neb. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ash-grove-lime-portland-cement-co-v-moran-construction-co-neb-1941.