This text of ASFA Construction Industry and Trade, Inc. (ASFA Construction Industry and Trade, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ASFA Construction Industry and Trade, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) ASF A Construction Industry and Trade, Inc. ) ASBCA No. 57269 ) Under Contract No. 000000-00-0-0000 )

APPEARANCE FOR THE APPELLANT: D. Lee Toedter, Esq. Orange Beach, AL

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ John R. Longley, JA CPT Tyler L. Davidson, JA CPT Edward Ahn, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PAGE

ASFA Construction Industry and Trade, Inc. (ASF A), appeals from a deemed denial of its claim seeking a $478,476.02 equitable adjustment or, alternatively, a termination for convenience settlement based upon an alleged implied-in-fact contract with the Joint Contracting Command-Iraq/Afghanistan (JCC-1/A) Regional Contracting Center-Balad (RCC-Balad) to repair an asphalt plant and rock crusher at Logistics Support Area (LSA) Anaconda in Balad, Iraq. Our jurisdiction arises from the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. In a previous decision, ASFA Construction Industry & Trade, Inc., ASBCA No. 57269, 11-2 BCA ~ 34,791, we denied the government's motion to dismiss this appeal for lack of jurisdiction on the basis that the alleged contract did not exist, holding that triable issues remained regarding the parties' respective conduct which precluded dismissal. 11-2 BCA ~ 34,791 at 171,249. The parties have elected to submit the appeal on the written record pursuant to Board Rule 11. We decide entitlement only. We sustain the appeal.

FINDINGS OF FACT

1. On 23 August 2007, the JCC-1/A RCC-Balad issued a request for information (RFI) to companies "interested in constructing a concrete batch plant on LSA Anaconda." Potential contractors were asked to respond by 25 August 2007 regarding their planned approach for the construction and operation of the concrete batch plant. Among other questions, the RFI asked potential contractors if they could "bring a batch plant onto LSA Anaconda at your own cost and the possibility of no work to start with." (R4, tab 1) At the time, only one concrete contractor was on Balad Air Base and the government did not want to bring in concrete from outside the base due to security concerns regarding the potential for explosives to be hidden within the concrete. Through the RFI, the government was attempting to increase contracting capability operating inside the base to meet its concrete requirements and also to secure more competitive prices. (R4, tab 50 (Berg dep.) at 16-18)

2. ASF A responded to the RFI by letter dated 25 August 2007 (R4, tab 2).

3. By memorandum dated 5 September 2007, contracting officer (CO) Chad D. Miller notified potential contractors that they would "be given the opportunity to present their plan of constructing a [concrete] batch plant" during a one-hour oral presentation on 19 September 2007. Topics to be addressed included equipment, set-up, barrier material, raw materials, labor, delivery and security, quality of concrete work, and financial resources. Potential contractors were directed to submit a "read ahead packet" to the government by 14 September 2007. (R4, tab 3)

4. ASF A provided the required read ahead packet to the government prior to its oral presentation (R4, tab 22). ASF A outlined by brand name, model designation, and (where appropriate) capacity of the concrete batch plant, stone crusher plant, mixer truck, and other pieces of equipment and vehicles that ASF A intended to provide (id. at 5). ASFA stated that "[a]ll equipment is ready to be shipped to Anaconda at the ASFA warehouse in Turkey," and that "delivery to Anaconda can be completed within 45 days." ASF A further stated that installation "can be compl[ e]ted within 30 days upon arrival of all the equipment in Anaconda." (Id. at 7)

5. By memorandum dated 31 October 2007, Lt Col Todd M. Burkhardt, USAF, Chief, RCC-Balad, notified ASF A that it had been selected to build a concrete batch plant on Balad Air Base, stating:

1. Congratulations! ASFA Group has been selected as the contractor to build a batch plant on Balad Air Base, Iraq. This award is based on your verbal presentation for the construction of a concrete batch plant on Balad Air Base, Iraq.

2. We are currently working with Terrain Management to get the land for the batch plant and rock crushing area. The land space we had was determined to be unsuitable and we are diligently working to get a new area. We will let you know as soon as the land is available.

2 3. Please acknowledge receipt of this letter in the space provided below and promptly return a signed copy of this letter to the addressed [sic] noted above.

4. We look forward to your company joining our contract support team and anticipate a prosperous working relationship.

5. Refer any questions to [Kimberly Burt].

(R4, tab 4) ASFA acknowledged receipt of the memorandum on 2 November 2007 (id.).

6. An asphalt plant and a rock crusher had been abandoned on the land to be given to ASFA to erect its concrete batch plant. It was the government's practice to use this leftover or "stay-behind" equipment for its own purposes. (Berg dep. at 31-36). Following the concrete batch plant award notice, CO MAJ Robert J. Berg conducted a terrain walk with Mr. Orcan Fikirdanis, an ASF A site representative. During the terrain walk, CO Berg instructed ASFA to push the abandoned, government-owned asphalt and rock crushing equipment aside. (Id. at 27-28, 30-32)

7. An 18 November 2007 email entitled "Batchplant Update" from Capt Karsten E. Lipiec of the Terrain Management Office, The Mayor's Cell, LSA Anaconda, to L TC Joseph Tyron, CO Berg and others provided:

Gentlemen, I went out and did a survey of your asphalt plant/crusher. See attached slide. [IJ [CO] Berg from contracting has offered the [ASF A] company to clean this up as part of their contract to start a new concrete batch plant here ....

My plan would be for your equipment to be stored near the perimeter, in a fenced-in, locked location not too far from here.... As you mentioned, your equipment does not run but you plan to fund an expert to troubleshoot it for you NET Jan 08.

[CO] Berg,

Sir, given this new information, how feasible is it to have [ASF A] perform this work? Once clear, the land could

1 The email included an attached document entitled "20 BDE Asphalt Plant.ppt" (R4, tab 6). That document, however, is not included in the record.

3 support set-up of [ASF A's] equipment. [ASF A's] plant requires 11,300 square meters. It could easily fit into the 28,467 SM measured here.

(R4, tab 6)

8. A 10 December 2007 email from CO Kristopher J. Pondo, Capt, USAF, advised ASF A:

You are allowed to open an asphalt plant on Anaconda. The lot of land will no longer be divided but will be ASF A's for both an asphalt and concrete plant. A letter will soon follow signed by [CO] Berg and [LTC] Tyron. For now I am authorizing you to proceed.

(R4, tab 7)

9. By a 10 December 2007 memorandum from LTC Tyron and CO Berg, the government notified ASF A that it had been selected to build an asphalt plant in addition to the concrete batch plant, stating:

1. Congratulations! ASF A Group has been selected for as [sic] the contractor to build another batch plant on Balad Air Base, Iraq. This award is based on your verbal presentation for the construction of an asphalt batch plant on Balad Air Base, Iraq.

2. We are currently working with Terrain Management to get the land for the batch plant and rock crushing area. The land space we had was determined to be unsuitable and we are diligently working to get a new area. We will let you know as soon as the land is available.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
City of El Centro v. The United States
922 F.2d 816 (Federal Circuit, 1990)
Total Medical Management, Inc. v. United States
104 F.3d 1314 (Federal Circuit, 1997)
Trauma Service Group v. United States
104 F.3d 1321 (Federal Circuit, 1997)
William M. Hanlin v. United States
316 F.3d 1325 (Federal Circuit, 2003)
Kam-Almez v. United States
682 F.3d 1364 (Federal Circuit, 2012)
Advanced Team Concepts, Inc. v. United States
68 Fed. Cl. 147 (Federal Claims, 2005)
Ace-Federal Reporters, Inc. v. Barram
226 F.3d 1329 (Federal Circuit, 2000)
Anderson v. United States
344 F.3d 1343 (Federal Circuit, 2003)
Russell Corp. v. United States
537 F.2d 474 (Court of Claims, 1976)