Aschoff v. State

CourtNebraska Court of Appeals
DecidedMay 2, 2017
DocketA-16-249
StatusUnpublished

This text of Aschoff v. State (Aschoff v. State) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aschoff v. State, (Neb. Ct. App. 2017).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

ASCHOFF V. STATE

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

GLENDA ASCHOFF, INDIVIDUALLY AND AS PERSONAL REPRESENTATIVE OF THE ESTATE OF WILLIAM ASCHOFF, DECEASED, AND JOEL ASCHOFF, APPELLANTS, V.

STATE OF NEBRASKA ET AL., APPELLEES.

Filed May 2, 2017. No. A-16-249.

Appeal from the District Court for Buffalo County: JOHN P. ICENOGLE, Judge. Affirmed. Andrew Wilson and Lawrence Roland, of Gross & Welch, P.C., L.L.O., for appellants. Douglas J. Peterson, Attorney General, and Douglas L. Kleunder for appellee State of Nebraska. Stephen L. Ahl and Krista M. Carlson, of Wolfe, Snowden, Hurd, Luers & Ahl, L.L.P., for appellees Werner Construction, Inc., et al.

MOORE, Chief Judge, and INBODY, Judge. MOORE, Chief Judge. I. INTRODUCTION Glenda Aschoff, individually and as personal representative of the estate of William Aschoff, deceased, and Joel Aschoff (collectively the Appellants) appeal from the order of the district court for Buffalo County which granted motions for summary judgment filed by Werner Construction, Inc., Werner Construction, Co., and Werner Construction, LLC (collectively Werner) and the State of Nebraska, and denied the Appellants’ motion for partial summary judgment against Werner. Because the court properly granted summary judgment in favor of Werner and the State, we affirm.

-1- II. BACKGROUND William was killed in 2011 while operating a bulldozer in a construction project for the Nebraska Department of Roads (NDOR) in which Werner was the general contractor. William’s son, Joel, witnessed the aftermath of the accident. William and Joel were both employed by Commercial Construction, Inc. (CCI), who had been subcontracted by Werner, the general contractor on the Kearney East Bypass Project (the project), to perform grading work. This work included filling a large body of water (the lake) located on the project jobsite. As part of his job, William operated a bulldozer to push fill material into the lake. While William was doing so, the fill material collapsed and William and the bulldozer fell into the lake. William died of asphyxiation by drowning. In 2011, the State, through the NDOR, retained Werner as general contractor to perform work on the project. The State owned the project jobsite. The project included construction of an exit ramp on I-80 near Kearney, Nebraska and other road work. The contract between the State and Werner provided that it was to be performed according to the construction plans, the NDOR specifications for highway construction, the contractor’s bond, the proposal, and all special provisions of the contract. It also required work to be performed in compliance with the laws of the State of Nebraska, under the supervision of the NDOR, and in accordance with the rules and regulations of the Federal Highway Administration. The “REQUIRED CONTRACT PROVISIONS” section of the contract stated that the contract applied to all work performed on the contract by the contractor and by any subcontractor. The required contract provisions were to be included in any subcontract. In the “SUBLETTING OR ASSIGNING THE CONTRACT” section, the required contract provisions provide: The contractor shall furnish (a) a competent superintendent or supervisor who is employed by the firm, has full authority to direct performance of the work in accordance with the contract requirements, and is in charge of all construction operations (regardless of who performs the work) and (b) such other of its own organizational resources (supervision, management, and engineering services) as the [State Highway Agency] SHA contracting officer determines is necessary to assure the performance of the contract.

And, in the “SAFETY: ACCIDENT PREVENTION” section, the required contract provisions provide: 1. In the performance of this contract, the contractor shall comply with all applicable Federal, State, and local laws governing safety, health, and sanitation. . . . The contractor shall provide all safeguards, safety devices and protective equipment and take any other needed actions as it determines, or as the SHA contracting officer may determine, to be reasonably necessary to protect the life and health of employees on the job. . . . 2. It is a condition of this contract, and shall be made a condition of each subcontract, which the contractor enters into pursuant to the contract, that the contractor and any subcontractor shall not permit any employee, in performance of the contract, to work in surroundings or under conditions which are unsanitary, hazardous or dangerous to

-2- his/her health or safety, as determined under [federal] construction safety and health standards. . . .

The NDOR highway specifications provide that “[s]ubcontracts, or transfer of contract, will not release the Contractor of any liability under the contract and bonds.” They also require contractors to notify the NDOR of “the specific differing conditions,” which conditions include “subsurface or latent physical conditions which differ materially from those indicated in the contract” and “unknown physical conditions of an unusual nature and differing materially from those ordinarily encountered and generally recognized as inherent in the work provided in the contract.” The State will investigate the differing conditions and if a change is warranted will modify the contract. The NDOR highway specifications give the State’s agent authority to decide all questions regarding the quality and acceptability of materials furnished, the work performed, the manner of performance and progress of the work, interpretation of the plans and NDOR specifications, fulfillment of the contract by the contractor, disputes pertaining to mutual rights between contractors, and determination of the existence of differing site conditions, among other things. The State’s inspectors are authorized to inspect all work performed and all material furnished. The NDOR specifications also give the State’s agent the authority to suspend work if the contractor fails to correct conditions unsafe to the NDOR personnel or the traveling public, carry out provisions of the contract, carry out orders of the State’s agent, or follow the plans and specifications. The State’s agent also has the authority to authorize a temporary suspension of operations, and to remove from the worksite any contractor or subcontractor employee who does not perform the work in a proper and skillful manner. On July 18, 2011, Werner subcontracted with CCI to fill in the lake. The subcontract between Werner and CCI provided, among other things, that CCI was responsible: II. (a) To furnish . . . all labor, materials, supplies, tools, equipment, and services including field measurements necessary to complete [the work identified in the contract]. . . . .... VI. To protect his work of construction adequately and properly by lights, barriers, supports, signs and guards so as to avoid injury or damage to persons or property and to be directly responsible for damages to persons and property occasioned by failure to do so, or by any negligence of the Sub-Contractor or any of his officers, agents or employees in the performance of his work. . . . .... X. To comply with all applicable federal, state and municipal laws and/or ordinances and regulations effective where the work is to be performed under this Sub-Contract and to pay all costs and expenses connected with such compliance. . . . .... XIII. To meet all the requirements of the Occupational Safety and Health Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diversified Telecom Services, Inc. v. Clevinger
683 N.W.2d 338 (Nebraska Supreme Court, 2004)
Sturzenegger v. FATHER FLANAGAN'S BOYS'HOME
754 N.W.2d 406 (Nebraska Supreme Court, 2008)
Dow Chemical Co. v. Bright
89 S.W.3d 602 (Texas Supreme Court, 2002)
Transit Mix Concrete & Materials Co. v. Johnson
205 S.W.3d 92 (Court of Appeals of Texas, 2006)
Eastlick v. Lueder Construction Co.
741 N.W.2d 628 (Nebraska Supreme Court, 2007)
Gaytan v. Wal-Mart
289 Neb. 49 (Nebraska Supreme Court, 2014)
Pittman v. Rivera
879 N.W.2d 12 (Nebraska Supreme Court, 2016)
Strode v. City of Ashland
886 N.W.2d 293 (Nebraska Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Aschoff v. State, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aschoff-v-state-nebctapp-2017.