Arundel Corp. v. United States

115 Ct. Cl. 92, 1950 U.S. Ct. Cl. LEXIS 51, 1950 WL 5042
CourtUnited States Court of Claims
DecidedJanuary 3, 1950
DocketNo. 46397
StatusPublished

This text of 115 Ct. Cl. 92 (Arundel Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arundel Corp. v. United States, 115 Ct. Cl. 92, 1950 U.S. Ct. Cl. LEXIS 51, 1950 WL 5042 (cc 1950).

Opinion

Howell, Judge,

delivered the opinion of the court:

Plaintiff, a corporation of Baltimore, Maryland, as successful bidder, entered into a written contract on September 1, 1939, with the defendant through the District Engineer of the War Department at Jacksonville, Florida, for the rental and operation of a hydraulic dredge, drill boat and other equipment for enlarging an existing levee on the eastern shore of Lake Okeechobee near Canal Point, Florida.

The lease provided that plaintiff would be paid $135 per rental hour for the first four months operating period and $110 per rental hour for any additional rental period thereafter up to six months, making a maximum period of ten months (Par. 1-07 specs., finding 5). Both rates were based upon a guaranteed output of 500 cubic yards per rental hour subject to adjustment on the basis of actual production above or below the guaranteed amount computed on a monthly basis under paragraph 1-08 (b) of the specifications (See finding 5). Under the formula, material in excess of the guaranteed output excavated by the dredge, as determined by borrow pit measurement, was to be paid for at the rate of 100 percent of the unit price and added to the sum earned by plaintiff at the rental rate for the month. On the other hand, if the material excavated was less than the guaranteed output, the deficiency yardage was to be charged against [141]*141the sum earned by plaintiff at the rate of 125 percent of the unit price.

Plaintiff was also to be paid $80 per hour for pumping water for removing unsuitable materials and $70 per hour for moving the dredge from one location to another.

While the contract was in the form of a lease contract with a stated rental rate per hour, based upon a guaranteed output, both the contracting officer and the Chief of Engineers stated that it was in fact a contract for a unit price of 27 cents per cubic yard with a penalty attached for failure to meet the contract requirements. Plaintiff also understood that the contract called for a penalty in the event of its failure to dredge the guaranteed amount of material.

Pursuant to paragraph 1-07 of the specifications, plaintiff notified the contracting officer in writing on February 2, 1940, that it proposed to terminate the contract after the expiration of the initial four months period, thus fixing March 7,1940, as the contract termination date.

The plaintiff was paid $42,172.36 for its attempt to perform the contract, in connection with which its actual costs amounted to $259,511.92 (See finding 55).

The contracting officer found that the deficiency in dredging progress was due to the failure of plaintiff to blast effectively in the borrow pit prior to dredging rather than to any restrictions imposed with respect to borrow pit width or depth by the contracting officer. This decision was affirmed on appeal except for a change in the method of computing the amount due plaintiff which resulted in an increase of from $3,106.82 previously allowed by the contracting officer to $42,172.36.

Plaintiff in this suit for the costs incurred by it in performing the work, makes the following contentions:

(1) The contract, specifications and drawings indicated no prescribed width or depth of the borrow pit to be excavated and hence plaintiff should have had the right to plan its work with no limitations on the width or depth of the borrow pits so long as it placed in the levee the necessary yardage of material meeting the gradation set out in the specifications; (2) that the contract and specifications stated that in all prior levee work in the area there had been no limita[142]*142tion as to tbe width or depth of borrow pits; (3) that the specifications stated that the contractor should plan its work and provide its equipment to operate in the borrow pit proposed to be dredged by the contractor; (4) that the specifications also indicated that the prior work done by the Government dredge Welatha would have to be used as a pattern for the work to be performed under this contract; (5) that having all of these factors in mind before bidding, plaintiff planned a borrow pit which would go deeper and place more rock in the levee than had been done by the Welatha \ (6) that its proposed borrow pit met all of the gradation requirements of the specifications, and (7) that before bidding plaintiff had talked with the contracting officer and resident engineer and had not been advised that the contractor would be restricted in the width or depth of the borrow pit.

Finally, plaintiff contends that the provision of the specifications for payment, whereby plaintiff was paid at the rate of 100 percent for extra yardage over the guaranteed output and charged at the rate of 125 percent for any deficiencies below that amount, constitutes a penalty which should not be enforced by this court.

While the findings are rather extensive and necessary to fully describe the situation from which this controversy stems, the main issue is comparatively simple. It involves a difference between plaintiff’s Superintendent Waldeck and defendant’s contracting officer with respect to the construction of certain language in the specifications.

Defendant insisted that plaintiff dredge deeply enough to obtain suitable material consisting of not less than 80 percent by volume of rock, marl, and shell conglomerate (Spec. 4-08) and claimed authority for its position under the contract and specifications, particularly that portion of paragraph 1-12 of the specification which contains this language:

* * * It is the intent that borrow pit cuts shall be dredged box cut form through the overburden into and through the stratified, harder and more desirable levee materials so as to provide the highest percentage of hard and lump materials with the minimum of waste. The contracting officer, through his agents, will stake out ranges and the contractor will be required to drive suitable dredging ranges to control his operations.

[143]*143We have found (finding 22) that as used and understood in the dredging industry, “bos cut” dredging merely required that the sides of the cut should be perpendicular and not sloped from bottom to top in order to prevent the flattening of the side of the cut in a manner that would permit sloughing in of unsuitable materials.

The words “box cut” in themselves have nothing to do with the width or depth of the borrow pit so that it is possible to perform such a form of dredging by removing materials in layers. This was the method used by plaintiff from time to time during the performance of this contract and condemned by defendant (findings 25-28) for the reason that it not only did not produce the type of material required (80 percent by volume of rock, marl, and shell conglomerate) but if placed in the levee it might leave weak spots which would cause a break during a hurricane.

Plaintiff was equally as insistent that neither the specifications nor plans required any specific width or depth to which the dredge should excavate and pointed to this language in paragraph 1-14 of the specifications:

* * * The contractor must determine for himself the size and capacity of the drill barges required to blast effectively the entire borrow pit area to be worked over.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sun Printing and Publishing Assn. v. Moore
183 U.S. 642 (Supreme Court, 1902)
Wise v. United States
249 U.S. 361 (Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
115 Ct. Cl. 92, 1950 U.S. Ct. Cl. LEXIS 51, 1950 WL 5042, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arundel-corp-v-united-states-cc-1950.