Arthur v. New House Building Corp.

217 Cal. App. 2d 526, 31 Cal. Rptr. 868, 1963 Cal. App. LEXIS 1932
CourtCalifornia Court of Appeal
DecidedJune 24, 1963
DocketCiv. 7088
StatusPublished
Cited by1 cases

This text of 217 Cal. App. 2d 526 (Arthur v. New House Building Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arthur v. New House Building Corp., 217 Cal. App. 2d 526, 31 Cal. Rptr. 868, 1963 Cal. App. LEXIS 1932 (Cal. Ct. App. 1963).

Opinion

CONLEY, J. *

The plaintiff obtained a decree for the foreclosure of a mechanic’s lien on certain real property in San Bernardino County because of the furnishing by him of concrete slabs, floors and concrete foundations for residences being erected on the premises described, of a total reasonable value of $15,600, of which the sum of $8,705 was coneededly paid, leaving a balance due of $6,895. The defendants, New House Building Corporation, Truman Enterprises, Inc., and Truman Browne, in their answer admitted that the plaintiff had performed certain work for them but denied that he had fulfilled his contract in conformity with its terms and denied that they were indebted to plaintiff. The other defendants, Continental Casualty Company and Great American Indemnity Company, were sued on the bonds which they had furnished.

*529 The defendants other than the surety companies counterclaimed on the grounds that plaintiff allegedly did not perform his contract, that the concrete work done by him was defective and would have to be torn out and replaced and that certain plumbing installations imbedded in the concrete would be ruined; the counterclaim lists numerous items of alleged damage, including $4,371 for rough plumbing allegedly rendered useless by the failure of the plaintiff to comply "with his contract, the sum of $5,500 by reason of the increase in cost of installing the concrete slabs called for by the plans and specifications and for the further sum of $300 per unit for each of 20 houses, causing an alleged additional damage of $6,000.

The pretrial order in the case shows that the following facts were admitted by the pleadings: (1) that Truman Enterprises, Inc., a corporation, is the owner of the real property described in the complaint; (2) that during the year 1957 the defendant owner began the erection of certain residences on specified real property; (3) that plaintiff began operations under his contract with defendant New House Building Corporation and finished said work in accordance with his contention that he had complied with his contract in October of 1957; (4) that New House Building Corporation originally agreed to pay plaintiff $15,600 for the labor and materials to be furnished under the contract; (5) that payments were made to plaintiff on the basis of the contract price of $650 per unit for 24 units, said payments being $5,000 on November 22, 1957, and $3,705 on November 27,1957.

It must be repeated, as it so often is in appellate decisions, that this court has a strictly limited right to review the evidence received in the court below. We can not try the case anew; we have nothing to do with weighing the evidence or with resolving conflicts therein or with judging the credibility of witnesses. In Crawford v. Southern Pac. Co., 3 Cal.2d 427, 429 [45 P.2d 183], the Supreme Court effectively summarizes the necessary duty and outlook of an appellate court as follows:

“In reviewing the evidence on such an appeal all conflicts must be resolved in favor of the respondent, and all legitimate and reasonable inferences indulged in to uphold the verdict if possible. It is an elementary, but often overlooked principle of law, that when a verdict is attacked as being unsupported, the power of the appellate court begins and ends with a determination as to whether there is any substantial *530 evidence, contradicted or uneontradicted, which will support the conclusion reached by the jury. When two or more inferences can be reasonably deduced from the facts, the reviewing court is without power to substitute its deductions for those of the trial court. ’ ’

The first question to be determined is: What was the contract actually entered into between the parties at the inception of their relationship? The defendants claim that the written form of contract with the specifications attached to their amended answer and counterclaim as Exhibit A was in fact the agreement reached between the parties; however, this contract was never signed by the plaintiff, and he contends that while he and the defendants’ representative, a Mr. Don Boyd, did talk about the proposed written contract, which was not signed, and the attached specifications at the inception of the business relationship, the oral general agreement contained a very distinct modification of the proposed writing in this, that Mr. Boyd specifically stated and agreed that the job would be done pursuant to City of Rialto inspection only; respondent testified that he calculated his bid on the job in accordance with this oral agreement and the building requirements of the City of Rialto, and therefore had a right to modify the proposed specifications accordingly.

The record shows that in March of 1957 Mr. Boyd, as general superintendent for the defendant New House Building Corporation, telephoned respondent and had him come to his office in the City of Rialto. At the time the plans and specifications were discussed, Mr. Boyd asked Mr. Arthur to give him a figure on the cement work, specifically stating that the job would be done under City of Rialto inspection only. Respondent calculated his bid on the job in accordance with the building requirements of the City of Rialto and therefore modified the specifications with respect to the footing under the garages or carports, leaving out that footing or making a modification which somewhat weakened the structure at that point and resulted in nonconformity with the requirements of Veterans Administration and F.H.A. financing. Sometime later respondent submitted a proposal to Mr. Boyd, and after further negotiations agreed to do the work on the 24 residence units in Tract 4433, located at South and Willow Streets in Rialto, County of San Bernardino, at $650 per unit. These cement slabs were in fact constructed on lots 23 through 26, 1 through 12, and 15 through 22. It is contended by the plaintiff that the unsigned “proposal and contract,’’ a copy *531 of which is attached to defendants’ amended answer and counterclaim as Exhibit A, was never agreed to by plaintiff, but that it Avas modified orally as already stated.

Respondent began work on the first four of the 24 units in June of 1957. Mr. Boyd, who had worked for Truman Browne since 1944-45 and was general superintendent for the New House Building Corporation, was in charge of the job and supervised the work that plaintiff did. During the month of October 1957 respondent completed the remaining 20 units. Mr. Boyd OArersaAV the pouring of the cement, and respondent folloAved Boyd’s directions throughout in Iioav the work Avas to be done. No complaints Avere registered by Boyd during the time that the operation was being carried forAvard. In each instance, according to his oavb. testimony, respondent dug the foundations and poured the concrete strictly in accordance Avith requirements of the City of Rialto; thereafter the 24 slabs Averc inspected and passed by the city building department.

After the completion of the Avork in October 1957, plaintiff was paid $5,000 on account on NoArember 22 and $3,705 on November 27. The record shows that subsequently the respondent talked with Boyd on several occasions, on each of which he was promised a payment of the balance due. Also, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anaheim Builders Supply, Inc. v. Lincoln National Life Insurance
233 Cal. App. 2d 400 (California Court of Appeal, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
217 Cal. App. 2d 526, 31 Cal. Rptr. 868, 1963 Cal. App. LEXIS 1932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arthur-v-new-house-building-corp-calctapp-1963.