Art Goebel, Inc. v. Array Construction Co.

437 N.W.2d 117, 1989 Minn. App. LEXIS 302, 1989 WL 23409
CourtCourt of Appeals of Minnesota
DecidedMarch 21, 1989
DocketCX-88-2162
StatusPublished
Cited by3 cases

This text of 437 N.W.2d 117 (Art Goebel, Inc. v. Array Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Art Goebel, Inc. v. Array Construction Co., 437 N.W.2d 117, 1989 Minn. App. LEXIS 302, 1989 WL 23409 (Mich. Ct. App. 1989).

Opinion

OPINION

SHORT, Judge.

Following an arbitration award, the trial court granted summary judgment against appellant’s district court claims.

FACTS

In 1979, appellant Art Goebel, Inc. contracted with general contractor Arkay Construction Co. (Arkay) for construction of a new building. Arkay subcontracted with respondent Video, Inc. for the masonry work; Video purchased concrete blocks from respondent Anchor Block Co. (Anchor).

Two years after completion, Anchor was required to perform cosmetic repair on the building due to faulty blocks. Two years later it was discovered that this repair was not permanent; appellant therefore brought suit against all three respondents.

The trial court stayed its proceedings pending the outcome of compulsory arbitration between appellant and Arkay; Video voluntarily joined the arbitration. In the memorandum accompanying the stay, the trial court noted:

[T]he arbitration will settle the total amount of loss, if any, to the [appellant], leaving to this court if indemnity is sought, only to determine the proportionate liability, if any, of the unbound party.

Anchor was not contractually required to submit to arbitration and refused to participate.

In settlement of all claims submitted, the arbitrator ordered Video to pay appellant $2,593, an amount allegedly representing the present value of the cost of future repairs. In a one-line memorandum, the arbitrator found Anchor (not Video) to be the negligent party.

Appellant accepted payment from Video and did not appeal the arbitration award. Upon appellant’s motion to lift the stay and Anchor’s motion for summary judgment, the court granted an appealable partial summary judgment, finding appellant collaterally estopped from litigating damage issues against Anchor.

ISSUE

Did the trial court err in granting partial summary judgment?

*119 ANALYSIS

In reviewing summary judgment, this court must determine whether there exist any genuine issues of material fact, and whether the trial court erred in its application of the law. Betlach v. Wayzata Condominium, 281 N.W.2d 328, 330 (Minn.1979). This court views the evidence in a manner most favorable to the nonmoving party and gives that party the benefit of all reasonable inferences to be drawn from the underlying facts. Vacura v. Haar’s Equipment, Inc., 364 N.W.2d 387, 391 (Minn.1985).

I.

Appellant argues that whether the arbitrator considered the possible diminution in value of the building, due to permanent injury, is a genuine issue of material fact precluding summary judgment. We disagree. Because the arbitration award was not appealed, the issue of whether certain evidence was presented and considered by the arbitrator is not properly before this court. See Mattsen v. Packman, 358 N.W.2d 48, 50 (Minn.1984). The arbitrator, in the absence of any agreement limiting his authority, is the final judge of both law and fact. State, by Sundquist v. Minnesota Teamsters Public & Law Enforcement Employees Union Local No. 320, 316 N.W.2d 542, 544 (Minn.1982) (quoting Cournoyer v. American Television & Radio Co., 249 Minn. 577, 580, 83 N.W.2d 409, 411 (1957)).

This case is similar to a case in which a successful party in conciliation court attempted to sue for greater damages in district court:

A judgment on the merits constitutes an absolute bar to a second suit * * * not only as to every * * * matter which was actually litigated, but also as to every matter which might have been litigated.

Mattsen, 358 N.W.2d at 49 (emphasis added) (quoting Hauser v. Mealey, 263 N.W.2d 803, 807 (Minn.1978). Appellant’s claim for damages resulting from construction was litigated in the arbitration proceeding. Whether the arbitrator considered the diminution evidence is irrelevant and not a material fact issue.

II.

Appellant also argues that the trial court erred in applying the doctrine of collateral estoppel to appellant’s district court claims against Anchor.

Whether collateral estoppel is available is a mixed question of law and fact subject to de novo review; once it is determined that collateral estoppel is available, the decision to apply the doctrine is left to the trial court’s discretion.

Regents of the University of Minnesota v. Medical Inc., 382 N.W.2d 201, 207 (Minn.Ct.App.1986), pet. for rev. denied (Minn. Apr. 18, 1986), cert. denied 479 U.S. 910, 107 S.Ct. 307, 93 L.Ed.2d 282 (1986) (citing United States v. Geophysical Corp. of Alaska, 732 F.2d 693, 697 (9th Cir.1984)).

(A) Availability of Collateral Estoppel.

The availability of the doctrine in the arbitration context has never been decided by a Minnesota appellate court. In Johnson v. Consolidated Freightways, Inc., 420 N.W.2d 608 (Minn.1988), the supreme court indicated its willingness to apply the doctrine in the appropriate fact situation, but noted it would not reach the issue there because it found that the facts of the case did not “support estoppel in any event.” Id. at 613. The court noted that estoppel has been applied to other informal proceedings, such as conciliation court. See Mattsen, 358 N.W.2d at 50. Furthermore, although estoppel depends on a judgment, exceptions to that rule are recognized where the parties have acquiesced in the outcome. See Ellis v. Minneapolis Commission on Civil Rights, 319 N.W.2d 702, 704 (Minn.1982). In our opinion, appellant acquiesced in the arbitration award by accepting the damages from Video and refraining from appeal. This is an appropriate factual context to apply the doctrine.

(B) Application of Collateral Estoppel. [Collateral estoppel] applies where (1) the issue was identical to one in a prior adjudication; (2) there was a final judgment on the merits; (3) the estopped party was *120

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Houlihan v. Fimon
454 N.W.2d 633 (Court of Appeals of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
437 N.W.2d 117, 1989 Minn. App. LEXIS 302, 1989 WL 23409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/art-goebel-inc-v-array-construction-co-minnctapp-1989.