Arrowhead, Inc. v. Safeway Stores, Inc.

587 P.2d 411, 179 Mont. 510, 1978 Mont. LEXIS 683
CourtMontana Supreme Court
DecidedDecember 5, 1978
Docket14077
StatusPublished
Cited by11 cases

This text of 587 P.2d 411 (Arrowhead, Inc. v. Safeway Stores, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrowhead, Inc. v. Safeway Stores, Inc., 587 P.2d 411, 179 Mont. 510, 1978 Mont. LEXIS 683 (Mo. 1978).

Opinion

MR. CHIEF JUSTICE HASWELL

delivered the opinion of the Court.

Plaintiff appeals from a judgment of the District Court, Deer Lodge County, discharging and releasing plaintiff’s mechanics liens on defendants’ property and dismissing its complaint of usury against defendant.

On November 16, 1973, plaintiff contracted with defendant for the construction of a new Safeway store in Anaconda, Montana. The written contract contained a final completion date of April 10, 1974. The final contract price, after all modifications of the agreement, was $499,506.25.

The contract required plaintiff contractor to obtain bank financing for construction costs. On December 3, 1973, the parties executed Change Order No. 1. This change order provided that defendant would pay plaintiff on a monthly basis for all work completed; that defendant could deduct interest from the final payment if the work was not completed by the completion date; interest was to be Vi of 1 percent in excess of the New York Prime Rate in effect on the 51st day following the completion date and was to be com *512 puted on the total amount of money already paid to plaintiff. The contract contained a liquidated damage clause requiring plaintiff to pay defendant $ 100 for each day the job was unfinished after the contracted completion date.

By later change orders, defendants extended the construction completion date to May 31, 1974. At that time the new store was not actually completed and plaintiff was allowed to finish numerous items after this date. Plaintiff finally satisfied all obligations for this construction project on October 28, 1974.

Defendants paid plaintiff a total amount of $487,534.77. In arriving at this figure, defendant deducted $5,300 in liquidated damages and $6,671.48 in interest from its final payment to plaintiff. The liquidated damages were calculated at $ 100 per day for the 53 day period from May 31, 1974, the extended completion date, to July 24, 1974, when defendants accepted the job as complete. Interest commenced on July 21, 1974 and ran to September 4, 1974, a period of 47 days, with interest at 12‘/2 percent per annum.

Plaintiff brought suit against defendant to foreclose its mechanics lien on August 11, 1976. Plaintiff sought recovery of the $11,971.48 held back by defendants as liquidated damages and interest. In April, 1977, plaintiff sought leave to amend its complaint to add its allegations of usury. Leave to amend was denied. However, the court subsequently allowed plaintiff to plead its claim of usury in its reply to defendant’s affirmative defenses. Plaintiff sought $29,482 damages for usury.

The case was tried by the court, sitting without a jury, in May 1977. The District Court entered its findings, conclusions and judgment on September 8, 1977, providing in substance that plaintiff had been granted proper extensions for completion of construction; that defendant had properly withheld $5,300 in liquidated damages for failure to complete construction by the contract completion date; and that plaintiff’s claim of usury was barred by the statute of limitations. Plaintiff appeals.

The underlying issue on appeal is the sufficiency of the evidence to support the District Court’s findings of fact and conclusions of *513 law. Specifically, plaintiff questions the findings and conclusions in two areas:

1. The finding and conclusion that defendant granted plaintiff sufficient extension of time to complete the contract and therefore defendant could properly withhold liquidated damages for the days the job was unfinished after the completion date.

2. The finding and conclusion that plaintiff’s usury claim was barred by the two year statute of limitations.

We have announced our standard of review in cases involving the sufficiency of the evidence to support the findings, conclusions and judgment in this language:

“When reviewing .findings of fact and conclusions of law of a district court, sitting without a jury, this Court has. repeatedly held such findings and conclusions will not be disturbed if supported by substantial evidence and by the law. Compton v. Alcorn, 171 Mont. 230, 557 P.2d 292; (1976); Brady v. State Highway Comm’n, 163 Mont. 416, 517 P.2d 738; Timmerman v. Gabriel, 155 Mont. 294, 470 P.2d 528; Wash. Water Power Co. v. Morgan Electric Co., 152 Mont. 126, 448 P.2d 683. When reviewing evidence it will be viewed in the light most favorable to the prevailing party in the district court, and the credibility of witnesses and the weight assigned to their testimony is for the determination of the district court in a nonjury trial. (Citations omitted.)” Luppold v. Lewis (1977), 172 Mont. 280, 563 P.2d 538, 540, 541.

Plaintiff first contends that it encountered a number of delays in constructing defendants’ store which were not of its own making. It maintains that the evidence shows that these delays amounted to a total of 144 days. Defendants only granted plaintiff 51 days, so plaintiff is entitled to additional 93 days.

Applying the foregoing standard of reviews, we hold that the District Court’s findings and conclusions that plaintiff was given sufficient extensions of time are supported by the evidence.

At trial, plaintiff broke down the 144 days in delays as follows: 21 days lost due to cold weather; 37 days lost due to the wind and *514 the chill factor; 20 days lost due to a flood of the site; 19 days lost due to a strike; 10 days lost because of a shortgage of fuel; 22 days lost because of owner caused delays; and, 15 days due to a shortage of materials.

Plaintiff’s comptroller testified that the 51 days in extensions granted by defendants can be broken down as: 18 days for the strike; 18 days for the flood and weather related problems, and 15 days for material shortages. Plaintiff’s construction manager testified that the 18 days for the strike was a sufficient extension for that delay. The 15 days for material shortage requested by plaintiff is what they were given by defendant for this delay. Thus, the question before this Court is whether plaintiff is entitled to additional extensions of time for the flood and weather problems; and extensions due to the shortage of fuel and alleged owner caused delays.

With regard to the delays from the flood, cold weather, and wind, the evidence shows that plaintiff was given an 18 day extension for these delays. Defendants’ architect testified that plaintiff’s job reports indicated only a 7 day delay in construction due to the flood. Plaintiff’s construction manager testified that they were delayed 20 days. The trial court resolved this conflict in the testimony in favor of the architect and refused to grant plaintiff an additional 20 days.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mowrer v. Eddie
1999 MT 73 (Montana Supreme Court, 1999)
In Re Guardianship of Mowrer
1999 MT 73 (Montana Supreme Court, 1999)
Beyer v. First Nat. Bank of Dillon
612 P.2d 1285 (Montana Supreme Court, 1980)
Knight & Co. v. Manaras
603 P.2d 675 (Montana Supreme Court, 1979)
Rogers v. Relyea
601 P.2d 37 (Montana Supreme Court, 1979)
Hopper v. Hopper
601 P.2d 29 (Montana Supreme Court, 1979)
Carbon County v. Schwend
594 P.2d 1121 (Montana Supreme Court, 1979)
First SEC. Bank of Bozeman v. Goddard
593 P.2d 1040 (Montana Supreme Court, 1979)
Farmers State Bank v. Mobile Homes Unlimited
593 P.2d 734 (Montana Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
587 P.2d 411, 179 Mont. 510, 1978 Mont. LEXIS 683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrowhead-inc-v-safeway-stores-inc-mont-1978.