Arrowhead Contractors, Inc. v. Graybar Electric Co., Inc.

CourtLouisiana Court of Appeal
DecidedNovember 5, 2008
DocketCA-0008-0038
StatusUnknown

This text of Arrowhead Contractors, Inc. v. Graybar Electric Co., Inc. (Arrowhead Contractors, Inc. v. Graybar Electric Co., Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrowhead Contractors, Inc. v. Graybar Electric Co., Inc., (La. Ct. App. 2008).

Opinion

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

08-38

ARROWHEAD CONTRACTORS, INC.

VERSUS

GRAYBAR ELECTRICAL COMPANY, INC., ET AL.

**********

APPEAL FROM THE THIRTIETH JUDICIAL DISTRICT COURT PARISH OF VERNON, NO. 72,631 B HONORABLE JOHN C. FORD, DISTRICT JUDGE

MARC T. AMY JUDGE

Court composed of Ulysses Gene Thibodeaux, Chief Judge, John D. Saunders and Marc T. Amy, Judges.

AFFIRMED. Thibodeaux, Chief Judge, dissents in part and assigns written reasons.

Elvin C. Fontenot, Jr. 110 East Texas Street Leesville, LA 71446 (337) 239-2684 COUNSEL FOR INTERVENOR/APPELLEE: Patrick Carr

Lamar M. Richardson, Jr. 110 Moore's Road Mandeville, LA 70471 (985) 626-4414 COUNSEL FOR INTERVENOR/APPELLEE: Manilo V. Mendoza Robin D. Pittman Baldwin, Haspel, Burke & Mayer, LLC 1100 Poydras Street, Suite 2200 New Orleans, LA 70163 (504) 585-7711 COUNSEL FOR DEFENDANT/APPELLEE: Graybar Electrical Company, Inc.

Eugene J. Radcliff Jonathan C. Augustine Montgomery, Barnett, Brown, Read, Hammond & Mintz, LLP 5353 Essen Lane, Suite 140 Baton Rouge, LA 70809 (225) 329-2800 COUNSEL FOR PLAINTIFF/APPELLANT: Arrowhead Contractors, Inc. AMY, Judge.

The plaintiff, a roofing subcontractor working at Fort Polk, alleged that the

general contractor failed to pay as agreed and that it breached its contract by not

supplying supervision at the site. The contractor placed the disputed funds into the

registry of the court and contested the breach of contract claim. Two roofing

businesses hired by the plaintiff intervened and asserted that they were not paid sums

due. The subcontractor responded by filing a reconventional demand against the

roofers. The trial court granted the contractor’s motion for involuntary dismissal on

the breach of contract claim. It also awarded the roofers’ demands from the funds

deposited with the court. The plaintiff appeals. For the following reasons, we affirm.

Factual and Procedural Background

Graybar Electrical Company, Inc., a contractor working on housing units at

Fort Polk, hired the plaintiff, Arrowhead Contractors, Inc., for roofing and painting

portions of the work. Arrowhead, in turn, hired subcontractors to complete the work.

Arrowhead filed this matter, alleging that Graybar breached its contract and that it

refused to pay the full sums owed. Although Graybar contested the breach of contract

claim, it deposited $41,251.72 into the court’s registry. Graybar indicated that the

figure “correspond[ed] to the amount Plaintiff’s subcontractors and suppliers have

asserted remains unpaid by Plaintiff to them.”

Two of Arrowhead’s roofing subcontractors, Patrick D. Carr d/b/a Carr

Construction and Manlio V. Mendoza and/or Custom Quality Construction, LLC,

filed petitions of intervention, seeking distributions from the sum in the court’s

registry. Arrowhead filed reconventional demands against Carr and Custom, alleging

its entitlement to the deposit. Arrowhead claimed that Carr failed to satisfy its

contract with Arrowhead, causing it to sustain repair costs, attorney fees, and court costs. It further claimed damages for the loss of its contract with Graybar, which, it

contends, was caused by Carr’s breach. As for Custom, Arrowhead alleged that it

failed to perform under its contract, again causing repair costs, attorney fees, and

court costs. Arrowhead additionally sought damages associated with a mechanic’s

lien filed against it by Custom.

At the close of Arrowhead’s case, the trial court granted Graybar’s motion for

involuntary dismissal. On the remainder of the claims, and after the close of evidence,

the trial court found in favor of the intervenors.1 It awarded $5,190.00 to Carr and

1 The trial court rendered the following written reasons for ruling:

The court considers the testimony of the parties, evidentiary offerings and post-trial memoranda and finds it more probable than not that the written contract entered into by Mendoza (Custom Quality Construction) and Arrowhead was modified to correct certain deficiencies which were ostensibly caused by Arrowhead’s supplier in delivering the wrong kind of roof flashing. The Court, therefore, concludes that the work billed for by Mendoza’s company, Custom Quality Construction, reflecting the costs necessary to make the repairs. Therefore, the court awards Custom Quality Construction $14,205.47 plus court costs and legal interest from date of judicial demand. Per diem and travel expenses are not payable under the contract.

Patrick Carr seeks payment for work alleged to have been performed under an oral contract.

Carr entered into a verbal contract with Arrowhead’s superintendent and according to Carr was told to invoice Arrowhead at the rate of $55.00 per square plus ten percent.

Counsel for plaintiff argues that the Court should consider Carr’s testimony unworthy because of impeachment and assume that Carr’s contract was for the same amount as Custom Quality Construction’s. Custom Quality Construction’s contract was for $55.00 per square foot with no mention of ten percent.

The Court considers all of these circumstances and particularly that each invoice submitted by Carr was clearly marked $55.00 per square plus ten percent. Invoices were consistently underpaid by Arrowhead for one reason or another but no mention of an overcharge of ten percent per square. There was no mention of a ten percent overcharge on checks written for payment, correspondence or pleadings. The Court therefore finds that it is more probably than not that Carr’s contract was for $55.00 per square plus ten percent.

Accordingly, the court awards Carr $5,190.00 plus costs of court and legal interest from date of judicial demand.

2 $14,205.47 to Custom from the court’s registry. It ordered the remaining funds

distributed to Arrowhead.

Arrowhead appeals, assigning the following as error:

(A) The Trial Court legally erred by awarding monetary relief/damages to the intervenors, CQC and Carr, considering neither party put on a case-in-chief as a prerequisite to carrying their respective burdens of proof to show entitlement to the relief asserted in their petitions for intervention.

(B) The Trial Court was manifestly erroneous and/or clearly wrong in disregarding the express and unambiguous language contained within the four corners of ACI’s written subcontractor agreements, along with the undisputed corroborating testimony of several witnesses, to award CQC and Carr monetary relief and/or damages for expenses not authorized under said agreements.

(C) The Trial Court was manifestly erroneous in granting Graybar’s Motion for Involuntary Dismissal and refusing to adjudicate ACI’s damages claim against Graybar, considering the undisputed witness testimony that Graybar and ACI agreed Graybar would have someone on-site to act as a liaison between ACI and Ft. Polk’s Garrison Department to ensure ACI’s work would pass government inspection.

Discussion

Burden of Proof

The trial encompassed Arrowhead’s main demand against Graybar, Carr and

Custom’s intervention for entitlement to funds in the registry of the court, and

Arrowhead’s reconventional demand for the funds. The trial court explained that the

claims would be heard together.2 Carr and Custom questioned Arrowhead’s

witnesses presented in support of its main demand. At the close of Arrowhead’s case,

counsel for both intervenors explained that they did not present additional witnesses

2 The trial court explained: “No, we’re going to take the whole thing together.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. Huber & Heard, Inc.
657 So. 2d 409 (Louisiana Court of Appeal, 1995)
Citgo Petroleum Corp. v. Yeargin, Inc.
690 So. 2d 154 (Louisiana Court of Appeal, 1997)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Arrowhead Contractors, Inc. v. Graybar Electric Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrowhead-contractors-inc-v-graybar-electric-co-inc-lactapp-2008.