Arrow Electronics, Inc. v. Quantum Corporation

District Court, N.D. California·Decided January 21, 2025·No. 5:23-cv-03746·Unknown

Opinion

Case No. 23-cv-03746-NC Plaintiff, ORDER GRANTING IN PART AND v. DENYING IN PART DEFENDANT’S MOTION FOR PARTIAL QUANTUM CORPORATION, SUMMARY JUDGMENT; ORDER DENYING PLAINTIFF’S MOTION Defendant. FOR SUMMARY JUDGMENT Re: ECF 57, 81

This case arises from a contract dispute between Plaintiff Arrow Electronics, Inc. and Defendant Quantum Corporation. Arrow alleges Quantum breached their supply agreement, consisting of a Master Agreement and Addendum, when Quantum failed to issue purchase orders to pay for aged inventory. It also alleges that in doing so, Quantum additionally breached its implied covenant of good faith and dealing. Before the Court are Quantum’s motion for partial summary judgment and Arrow’s motion for summary judgment. Quantum requests partial summary judgment that (1) the Court cannot consider extrinsic evidence for purposes of interpreting Arrow’s form agreements unless Arrow identifies specific provisions in the agreements it drafted that it contends are ambiguous; (2) forecasts submitted by Quantum do not constitute or create binding purchasing obligation on the part of Quantum; (3) forecasts submitted before June 4, 2021, were not governed by the Addendum; (4) Arrow was required to satisfy its obligation to provide inventory reports as a condition precedent and take receipt and have physical custody in its warehouse of the parts at issue for at least 60 days before it had the right to request purchase orders from Quantum under the Addendum; and (5) Arrow’s Second Claim for Breach of Implied Covenant of Good Faith and Fair Dealing is redundant of, and subsumed by, Arrow’s First Claim for Relief for Breach of Contract. Arrow requests summary judgment that Quantum breached the parties’ contract and Arrow is damaged in the amount of $4,029,413.20, or alternatively, $3,719,807.21, as well as reasonable attorneys’ fees, costs, and interest. The Court, for the reasons below, GRANTS in part Quantum’s motion for partial summary judgment as to finding that (3) the forecasts submitted before June 4, 2021, were not governed by the Addendum; (4)(b) Arrow was required to take receipt and have physical custody in its warehouse of the parts at issue for at least 60 days before it had the right to request purchase orders from Quantum under the Addendum; and (5) Arrow’s Second Claim for Breach of Implied Covenant of Good Faith and Fair Dealing is redundant of, and subsumed by, Arrow’s First Claim for Relief for Breach of Contract, and DENIES in part Quantum’s motion for partial summary judgment as to finding that (1) the Court cannot consider extrinsic evidence for purposes of interpreting Arrow’s form agreements unless Arrow identifies specific provisions in the agreements it drafted that it contends are ambiguous; (2) forecasts submitted by Quantum do not constitute or create binding purchasing obligation on the part of Quantum; and (4)(a) Arrow was required to satisfy its obligation to provide inventory reports as a condition precedent before it had the right to request purchase orders from Quantum under the Addendum. Additionally, the Court DENIES Arrow’s motion for summary judgment that Quantum breached the parties’ contract and Arrow is damaged in the amount of $4,029,413.20, or alternatively, $3,719,807.21, as well as reasonable attorneys’ fees, costs, and interest. A. Factual Findings 1. Master Agreement and Addendum On September 30, 2020, Arrow and Quantum entered into a Master Agreement through which Quantum would provide written forecasts of its demand for products, and Arrow would procure and supply the inventory. ECF 1-1 (Master Agreement). On May 12, 2021, Quantum signed an Addendum to the Master Agreement. ECF 1-2 (Addendum). Arrow signed the Addendum on June 4, 2021. Id. There is dispute as to when the Addendum became effective. The Master Agreement and Addendum (the Agreements) govern the relationship between the parties. ECF 1 ¶ 21. If there is conflict between the terms of the Agreements, the Addendum governs. Master Agreement at 6; Addendum at 1. The Parties agree that both contracts are controlled by New York law and are unambiguous. ECF 1 ¶ 42; ECF 61 at 6. The Parties disagree as to what the Agreements require Arrow and Quantum to do. 2. Party Actions On May 26, 2021, Arrow representative Kristin Goff told Quantum representative Patricia Timmons that the products Quantum wished to purchase had a lead time between 12 to 16 weeks. ECF 54-5 (Goff Decl.), Ex. 9 at 1. Goff also stated that Arrow “should be booking hard orders now for all demand through 9/30/21,” which was 18 weeks from May 26, 2021. Id. Quantum alleges that the 12- to 16- week lead time was based on an April 29, 2021, email from John Lauritano, a manufacturer representative, suggesting that Arrow “[t]ell Quantum lead time has stretched to 16 weeks if needed to get their attention.” ECF 62 at 6; ECF 83 (Hammon Decl.), Ex. G at 2. Arrow alleges that these lead times were a result of Arrow learning in April and May 2021 that lead times had climbed from 12 weeks in early 2021 to 16 weeks by the middle of the year. Willis Decl., Ex. 41 at 1; Goff Decl., Ex. 9 at 1. Around the same time, a sales manager for a third manufacturer, AMD, warned Quantum that lead times were as high as 30 weeks. Willis Decl., Ex. 42 at 2. Decl., ¶ 5, Ex. 10. Along with the forecast, Quantum instructed Arrow to “get parts on order so that [Quantum] can have buffer stock at Arrow.” Id. There is dispute as to whether this forecast was subject to the Addendum. Quantum allegedly sent a forecast to Arrow on July 21, 2021 (July Forecast) that was identical to its May Forecast, but there is dispute as to whether it was sent, who it was created by, and thus, whether this was considered a Material Requirement Plan (MRP) under the Addendum. ECF 64 at 7 n.24; ECF 62 at 9; ECF 66 at 7. Arrow began ordering components starting June 3, 2021, and continued to place orders throughout the summer. Goff Decl. ¶¶ 6–7, Ex. 11 at 1; ECF 54-4 (Korn Decl.) ¶¶ 7–9, Exs. 5 and 5-A. Arrow ordered more than 75% of its units, 15,206 of them, over a three-day period from July 6, 2021, through July 8, 2021. ECF 67-1 (Wexler Reply Decl.) ¶ 5. In July 2021, Arrow placed orders for 6,912 units with less than 30 days lead time for 12 of the 15 models at issue in the motion. ECF 83 (Wexler Decl.) ¶ 9. By September 1, 2021, Arrow had ordered about 90% of its 19,333 units. Korn Decl. ¶ 8. When placing orders during Summer 2021, Arrow used lead times shown in Table 1 that took into account the expanding manufacturer lead times, the manufacturers’ historical performance against lead times, the tight market amid the pandemic, the direction from Quantum to build up buffer inventory, and the Addendum requirement that Arrow maintain reserved inventory for Quantum. Korn Decl. ¶¶ 23, 26, Ex. 8. 99-week entries meant that Kioxia could not quote a lead time and would supply components only as they became available, and zero-week entries denoted inadequate information to verify a precise lead time, so Arrow’s system planned for a year out by default. Korn Decl. ¶¶ 28– 29. 1 Table 1 2 ene | SY |S DE DE | Ae |S | 3 Week 1|2{[3 |4]s5]1]2 {3 {4{ 1 2 3 4 |KxGeozNv2seG | 99] 99| 99| 99| 99| 99| 99| 99| 99| 99| 99] 99| 99 4 || [xxcooznvsizc| of of of of 99| 99] 99] o9| 99] 99] 99] 99) |sprussiceB | 99{ 99| 99| 99| 99| 99/ □□□ 99] 99| 99] 99] 99] 99 | 5 || |spruss3ceB_ | 99| 99| 99| 99| 99] 99| 99| 99| 99| 99] □□□ 99| 99 |sprusssceB | 99| 99| 99| 99| 99| 99| 99| 99| 99] 99| 99| 99| 99) 6 || |sprussices | 99| 99| 99| 99| 99| 99| 99| 99| 99| 99| 99| 99] 99] [sprusssceB_ | 0] Of oT oto of of of of of of 9 7 || [sprusssces | 99| 99| 99| 99| 99| 99| 99| 99| 99] 99| 99| 99| 99 8 || [upepi20ceps1 | of of of of of of of of of of of | HDEBL2iGEAS1| o| o| o[ o| o| of of of of of o| of oF 9 [upEBL22GEBS1|_o| o| of o| of of of of of of of of oa 10 || [wpemz2ceasi | of oe] sf 8] 8] s| s{ s{ s{ s{ s{ sl s| |HDEPN20GEAS1| 14] 14] 14] 14] 14] 14] 14] 4]

Free access — add to your briefcase to read the full text and ask questions with AI

Arrow Electronics, Inc. v. Quantum Corporation, (N.D. Cal. 2025).

Arrow Electronics, Inc. v. Quantum Corporation (Arrow Electronics, Inc. v. Quantum Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
JA Apparel Corp. v. Abboud
568 F.3d 390 (Second Circuit, 2009)
Washington Central Railroad v. National Mediation Board
830 F. Supp. 1343 (E.D. Washington, 1993)
EXPRESS, LLC v. Fetish Group, Inc.
464 F. Supp. 2d 965 (C.D. California, 2006)
Medinol Ltd. v. Boston Scientific Corp.
346 F. Supp. 2d 575 (S.D. New York, 2004)
Tolan v. Cotton
134 S. Ct. 1861 (Supreme Court, 2014)
Cowen & Co., LLC v. Fiserv, Inc.
141 A.D.3d 18 (Appellate Division of the Supreme Court of New York, 2016)
Bucho Holding Co. v. Temporary Housing Rent Commision
184 N.E.2d 569 (New York Court of Appeals, 1962)
Ashkenazi v. Kent South Associates, LLC
51 A.D.3d 611 (Appellate Division of the Supreme Court of New York, 2008)
Kass v. Kass
235 A.D.2d 150 (Appellate Division of the Supreme Court of New York, 1997)
Barthelemy v. Air Lines Pilots Ass'n
897 F.2d 999 (Ninth Circuit, 1990)