Arriwite v. SME Steel Contractors, Inc.

District Court, D. Idaho·Decided October 6, 2021·No. 4:18-cv-00543·Unknown

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO

DANIEL C. ARRIWITE, Case No. 4:18-cv-00543-DCN Plaintiff,

v. MEMORANDUM DECISION AND ORDER SME STEEL CONTRACTORS, INC., SME John Does I-V,

Defendants.

I. INTRODUCTION Pending before the Court are Defendant SME Steel Contractors, Inc.’s (“SME”) Motion in Limine (Dkt. 56) and Plaintiff Daniel Arriwite’s Motion in Limine (Dkt. 57). Both parties also filed objections to various trial submissions. Dkts. 67, 69. The Court will address some of these objections in addition to the Motions in Limine. Having reviewed the record and briefs, the Court finds that the facts and legal arguments are adequately presented. Accordingly, in the interest of avoiding further delay, and because the Court finds that the decisional process would not be significantly aided by oral argument, the Court will decide the Motions without oral argument. Dist. Idaho Loc. Civ. R. 7.1(d)(1)(B). For the reasons outlined below, the Court will GRANT in PART and DENY in PART SME’s Motion in Limine and GRANT Arriwite’s Motion in Limine. The Court also reserves ruling on most of the objections raised, but sustains Arriwite’s objection as to prospective witnesses Kent Eden and Troy Hoffman. II. BACKGROUND The facts of this case are well known to both parties and the Court will only include a brief recitation here for context. Plaintiff Daniel Arriwite was employed as a welder by SME until his termination

on July 3, 2015. On July 1, 2015, Arriwite was welding on one project when a superior asked him to move to a different project. As he began to work on the new project, Arriwite noticed that the weld was utilizing UltraCore 75C – Lincoln Electric Wire (“75C”).1 Based on his knowledge and experience in the industry, Arriwite knew 75C wire was a dangerous material that required additional safety measures and specialty equipment in order to safely

use it under Occupational Safety and Health Administration (“OSHA”) guidelines. Arriwite also knew that 75C wire could cause physical damage to the person using it if welded improperly. Not seeing any of the requisite safety measures in the immediate area, Arriwite asked other employees where the Personal Protective Equipment (“PPE”) was so that he

could safely perform the task. Arriwite was provided a paper mask and a fan. He knew these measures were inadequate and expressed concern. He was told to simply return to the project he had previously been working on and was later sent home. The following morning, on July 2, 2015, another SME employee asked to switch welders with Arriwite. Not seeing a need, Arriwite declined. Based upon this and other

disagreements during the day, Arriwite was eventually summoned to SME’s main office

1 The parties previously represented to the Court that the wire in question was 70C wire—as opposed to 75C wire—and the Court’s prior decision (Dkt. 36) utilized that reference. It is now the Court’s understanding that the wire Arriwite was asked to use (and refused) was actually 75C wire. and accused of insubordination. SME Human Resource Director, Dave Burgess, and other employees were present during this meeting. Arriwite was given a direct order to go work on the project requiring

75C wire and told that all necessary safety precautions were in place in accordance with the Material Safety Data Sheet (“MSDS”). Arriwite refused, stating the MSDS was inadequate and that the manufacturer’s warning label on the boxes of 75C wire outlined more detailed safety measures. SME told Arriwite the company followed the MSDS. Arriwite responded that OSHA required compliance with the manufacture’s warning

labels, not the MSDS, and that—if necessary—he would report SME to OSHA for safety violations. At the conclusion of the meeting, SME sent Arriwite home for the day. Arriwite immediately went to the Shoshone-Bannock Tribes’ Tribal Employment Rights Office and informed the safety compliance officer that he would likely be terminated the following

day. He also filled out and sent an OSHA report detailing SME’s unsafe use of 75C wire and the attending unsafe working conditions. The next morning, July 3, 2015, Arriwite arrived at SME and began work. Shortly thereafter, he was again escorted to the main office and informed he was being let go. A discussion regarding unemployment benefits followed and Arriwite left the premises.

On July 14, 2015, Arriwite filed a whistleblower claim with OSHA. On July 15, 2015, OSHA investigated Arriwite’s allegations. While the investigation yielded no violations, several employees informed Arriwite that SME had concealed its unsafe practices from OSHA during their visit. When Arriwite informed OSHA of this fact, OSHA initiated a second unannounced site visit. During this subsequent visit, OSHA observed numerous code violations regarding the use of 75C wire. OSHA cited SME for these violations—designated as “SERIOUS” violations under OSHA standards—and proposed

substantial fines. SME ultimately entered into a settlement agreement with OSHA for reduced penalties and stricter use of PPE. OSHA later responded to Arriwite’s whistleblower complaint and informed him there was insufficient evidence to suggest he had been terminated for refusing to work in dangerous conditions and/or for reporting those conditions to OSHA. Arriwite appealed.

OSHA denied the appeal. On December 7, 2018, Arriwite filed the instant action. In his Complaint, Arriwite brings four causes of action: 1) wrongful termination in violation of public policy; 2) negligent infliction of emotional distress; 3) breach of the covenant of good faith and fair dealing; and 4) wrongful discharge. Dkt. 1. After the close of discovery, SME filed a

Motion for Summary Judgment. Dkt. 24. The Court held oral argument and subsequently issued a decision granting in part and denying in part SME’s motion. Dkt. 36. The Court granted SME’s request as to Claims II and IV, but denied SME’s motion as to Claims I and III. In anticipation of the upcoming trial, and pursuant to the Court’s trial order (Dkt.

38), both parties filed motions in limine seeking to preclude certain evidence and testimony at trial. In its Motion, SME asks the Court to preclude all evidence and testimony as it relates to five topics. In his Motion, Arriwite asks the Court to find that testimony and evidence on two topics is admissible. Arriwite’s two topics are identical to two of SME’s five topics, therefore, for organizational purposes, the Court will address the motions simultaneously. III. LEGAL STANDARD “Motions in limine are well-established devices that streamline trials and settle

evidentiary disputes in advance, so that trials are not interrupted mid-course for the consideration of lengthy and complex evidentiary issues.” Miller v. Lemhi Cty., 2018 WL 1144970, at *1 (D. Idaho Mar. 2, 2018) (citing United States v. Tokash, 282 F.3d 962, 968 (7th Cir. 2002)). “The term ‘in limine’ means ‘at the outset.’ A motion in limine is a procedural mechanism to limit in advance testimony or evidence in a particular area.”

United States v. Heller, 551 F.3d 1108, 1111 (9th Cir. 2009) (quoting Black’s Law Dictionary 803 (8th ed. 2004)). Because “[a]n in limine order precluding the admission of evidence or testimony is an evidentiary ruling,” United States v. Komisaruk, 885 F.2d 490, 493 (9th Cir. 1989) (citation omitted) “a district court has discretion in ruling on a motion in limine.” United

States v. Ravel, 930 F.2d 721, 726 (9th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Arriwite v. SME Steel Contractors, Inc., (D. Idaho 2021).

Arriwite v. SME Steel Contractors, Inc. (Arriwite v. SME Steel Contractors, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ohler v. United States
529 U.S. 753 (Supreme Court, 2000)
United States v. Susan Alexis Komisaruk
885 F.2d 490 (Ninth Circuit, 1989)
United States v. Francis Ravel
930 F.2d 721 (Ninth Circuit, 1991)
United States v. Heller
551 F.3d 1108 (Ninth Circuit, 2009)