Arred Electrical Contracting Corp. v. Herbert Construction Corp. (In re Arred Electrical Contracting Corp.)

106 B.R. 353, 1989 Bankr. LEXIS 1706
District Court, S.D. New York·Decided September 22, 1989·No. Bankruptcy No. 86 B 11393 (BRL); Adv. No. 87-5228A·Published·Cited by 1 cases

Opinion

BURTON R. LIFLAND, Chief Judge.

BACKGROUND

The pertinent facts do not appear to be in dispute. Plaintiff, Arred Electrical Contracting Corp. (“Arred”) was the electrical subcontractor on a residential construction project at 58-60 East 88th Street in Manhattan (the “Project”). On or about April 3, 1987 Arred commenced this adversary proceeding against defendants Herbert Construction Corp. (“Herbert”) and Shnay Construction Corp. (“Shnay”), the general contractor (the “Complaint”) to recover damages in connection with work performed on the Project. Herbert answered the Complaint on or about May 22, 1987. Shnay answered the Complaint on or about April 30, 1987, with a cross-claim against the Defendant Herbert. Thereafter, on or about May 5, 1987, Defendant Shnay commenced a third party action against S & H 88th Street Associates (“S & H”), the owner, as third party Defendant. On or about July 3, 1987, Arred served an amended complaint joining S & H as a defendant. S & H then brought in an additional third party defendant, Beyer, Blinder & Belle, Architects and Planners (“Beyer, Blinder & Belle”) by a third party summons and complaint dated July 13, 1987.

On or about July 23, 1987, Arred filed a Notice of Mechanic’s Lien dated June 25, 1987 against the property of Defendant S & H 88th Street in the amount of $257,-786.11 (the “Mechanic’s Lien”). Thereafter, on or about August 28, 1987, the Mechanic’s Lien was bonded by Fidelity and Deposit Company of Maryland (“Fidelity”). Approximately five months after Arred filed its Mechanic’s Lien, Atlas Tile and Marble Works, Inc. and Atanco Inc. (collectively “Atlas Tile”), the joint venture who performed the masonry subcontracting work on the Project, joined Arred as a party defendant in a state court lien foreclosure action.

Arred now moves for an order granting it leave to amend its Complaint herein to add Fidelity as a party defendant. In addition, Arred seeks to amend its Complaint to add a cause of action for foreclosure of the Mechanic’s Lien. Arred alleges in its motion to amend that in late April 1988, its attorney, Mr. Raucher, contacted the attorneys for defendants to obtain consents to a stipulation permitting service of an amended complaint incorporating a cause of action for foreclosure. Mr. Raucher alleges that although the parties had agreed to execute the stipulation permitting the amendment, S & H’s attorneys rescinded their agreement and changed their position after the one year period set forth in § 17 of the New York .Lien Law (the “Lien Law”) had elapsed.1 Thus, no stipulation was ever formally executed except by the third party defendant Beyer, Blinder & Belle. On the other hand, S & H asserts that it never agreed to stipulate to amend the Complaint in order to allow a foreclosure claim to be asserted against itself.

Subsequently, S & H cross-moved for an order lifting the automatic stay, pursuant to § 362(a) of the Bankruptcy Code (the “Code”), for the purpose of allowing it to make an application to the state court to vacate and discharge the Mechanic’s Lien bond herein on the ground that it has expired by operation of law. S & H alleges that Arred’s proposed amended complaint which seeks a cause of action to foreclose the Mechanic’s Lien bond is time-barred pursuant to § 17 of the Lien Law.

In reply, Arred asserts that although it did not seek an order continuing its Mechanic’s Lien, its lien is fully effective because (1) Arred was joined as a party defendant in another subcontractor-lienor’s action to foreclose within the applicable period; (2) Arred sought to commence a foreclosure proceeding within the applicable one year period; (3) the instant application to amend the Complaint to include a foreclosure claim relates back pursuant to Rule 15(c) of the Federal Rules of Civil Procedure (the “Federal Rules”); and (4) [356] based on the doctrine of estoppel, the foreclosure action should be permitted to proceed.

DISCUSSION

The Viability of Arred’s Mechanic’s Lien.

Section 17 of the Lien Law is controlling with respect to the duration of a mechanic’s lien which provides that

a notice of mechanic’s lien is viable for a period no longer than one year unless, within that time, the lienor either (a) obtains an order of the court extending the lien for a period up to one year and redockets the lien; or (b) commences an action to foreclose the lien and filed a notice of pendency with the clerk of the appropriate county; or (c) is made a party defendant in an action to enforce another lien, and the plaintiff or such defendant had filed a notice of the penden-cy of the action, (emphasis in original.)

In re Millerlee Corp. 70 B.R. 780, 782 (Bankr.S.D.N.Y.1987); N.Y. Lien Law § 17 (McKinney’s 1966 and Supp.1987).

It is undisputed that on or about April 19, 1988, three months prior to the expiration of its Mechanic’s Lien, Arred was joined as a party defendant in a lien foreclosure action commenced by Atlas Tile. However, neither a notice of pendency of that action was ever filed nor was Atlas Tile’s mechanic’s lien discharged by S & H posting a bond or depositing money with the court.

Arred argues that it still falls within the purview of § 17 even though no notice of pendency was filed since Arred’s Mechanic’s Lien had been discharged some eight months earlier after S & H filed an undertaking with respect to Arred’s Mechanic’s Lien. Consequently Arred maintains that no notice of pendency was necessary. In this regard, Arred relies on the portion of the statute which states that “[w]here a lien is discharged by deposit or by order, a notice of pendency of the action shall not be filed.” N.Y. Lien Law § 17.

Arred also relies on Ward v. Kilpatrick, 85 N.Y. 418 (1881) in which funds were deposited with the court to secure the obligation of the lien. In Ward, the Court of Appeals found that the lis pendens requirement of the statute was inapplicable:

That provision under the statute has no application to a case where the lien upon the real estate is discharged by the deposit in court of the amount of the debt as was done in this case. In that event, the lien is shifted to the fund, the controversy ceases to affect the real estate or third persons, and a lis pendens becomes unnecessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Arred Electrical Contracting Corp. v. Herbert Construction Corp. (In re Arred Electrical Contracting Corp.), 106 B.R. 353, 1989 Bankr. LEXIS 1706 (S.D.N.Y. 1989).

106 B.R. 353 (Arred Electrical Contracting Corp. v. Herbert Construction Corp. (In re Arred Electrical Contracting Corp.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related