ARR Roofing v. Nebraska Furniture Mart

CourtNebraska Court of Appeals
DecidedJuly 2, 2019
DocketA-18-284
StatusPublished

This text of ARR Roofing v. Nebraska Furniture Mart (ARR Roofing v. Nebraska Furniture Mart) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ARR Roofing v. Nebraska Furniture Mart, (Neb. Ct. App. 2019).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

ARR ROOFING V. NEBRASKA FURNITURE MART

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

ARR ROOFING, L.L.C., ALSO KNOWN AS BOONE BROTHERS ROOFING, APPELLANT, V.

NEBRASKA FURNITURE MART, INC., A NEBRASKA CORPORATION, AND BENCHMARK, INC., AN IOWA CORPORATION, APPELLEES.

Filed July 2, 2019. No. A-18-284.

Appeal from the District Court for Douglas County: W. RUSSELL BOWIE III, Judge. Affirmed. Heather S. Voegele-Andersen and Gretchen L. McGill, of Dvorak Law Group, L.L.C., for appellant. Brian T. McKernan and Nicole K. Griffard, of McGrath, North, Mullins & Kratz, P.C., L.L.O., for appellee Nebraska Furniture Mart, Inc. Thomas J. Guilfoyle and Nicholas F. Sullivan, of Erickson Sederstrom, P.C., for appellee Benchmark, Inc.

PIRTLE, ARTERBURN, and WELCH, Judges. PIRTLE, Judge. INTRODUCTION ARR Roofing, L.L.C. (ARR), appeals from an order entered in the district court for Douglas County which granted summary judgment in favor of Nebraska Furniture Mart, Inc. (NFM), and Benchmark, Inc., for claims of breach of contract, breach of implied covenant of good

-1- faith and fair dealing, fraudulent and negligent misrepresentations, and tortious interference. ARR argues that the district court erred in granting the summary judgment for breach of contract, in finding that NFM and Benchmark acted in good faith, in finding that there were no misrepresentations, and in finding that Benchmark was entitled to the design professional’s privilege. For the reasons that follow, we affirm. BACKGROUND NFM is a business located in Douglas County, Nebraska. In May 2013 it contracted with Benchmark, a roofing design and consulting firm, to provide NFM with roof management and consulting services for a roofing project. Pursuant to this agreement, Benchmark prepared the bid documents including the drawings and specifications of the new roof as well as the contract. These drawings and specifications showed the work that needed to be completed on the roof. Included in these drawings was a generic drawing of the decking, a part of the building that the roof is attached on to, to demonstrate where fasteners should be placed. Part of the project would also include repairing and cleaning the decking. However, as the condition of the decking could not be viewed until after the roof was removed, estimates were made in the contract with a provision that adjustments would be made after the condition of the decking was determined. On August 23, 2013, NFM, Benchmark, and ARR all attended an on-site pre-bid meeting for the project. At least some of the underside of the decking was viewable at that time as part of the building did not have a drop ceiling. ARR submitted its bid for the project and NFM accepted the bid, entering into a contract agreement on or about September 12, 2013 (Contract). Benchmark was not a party to this Contract. Initially work was to commence on September 30, 2013. NFM then requested a delay until spring 2014, to which ARR assented. Work on the project began in late May 2014. ARR encountered two major issues once work began. First, the decking had a substantially greater amount of rusting than initially planned for in the Contract. Second, it was discovered that the decking, as depicted in the generic drawings, was different than the decking currently in place. As a result, in order to attach the roof properly, ARR was required to expand the bottom deck flutes by hand. This additional work was agreed to in Change Directive No. 1 which specified the per hour cost, but not the total number of hours or cost. Ultimately, the project was completed. Benchmark and NFM issued Change Order No. 1 on or about December 12, 2014, which included all of the previous change directives and provided the total additional expense that would be included in the contract price. ARR signed off on Change Order No. 1 and subsequently submitted an application and certificate for payment which included the amount on Change Order No. 1 and showed that there were no additional funds due under the Contract. However, on April 29, 2015, ARR submitted a letter to NFM requesting adjustment to the final cost of the project for additional work. A check was ultimately issued by NFM and cashed by ARR for the amount requested by ARR on its final application and certificate for payment; however, the check was not issued until after ARR submitted its request for an adjustment. ARR subsequently filed a complaint on July 2, 2015, alleging that NFM and Benchmark had breached the Contract, breached the implied covenant of fair dealing and good faith, and made negligent and fraudulent representations. An amended complaint was filed on July 27, 2017. NFM

-2- and Benchmark each filed a motion for summary judgment on September 29, 2017. A hearing was held on December 15, 2017, at which time evidence was submitted. The district court issued an order on February 26, 2018, granting NFM and Benchmark’s motions for summary judgment on all causes of action. It is from this order that ARR appeals. ASSIGNMENTS OF ERROR On appeal, ARR assigns, consolidated, renumbered, and rephrased, that the district court erred in (1) granting summary judgment in favor of NFM and Benchmark for breach of contract, (2) finding that NFM did not breach its contract or the implied warranty, (3) finding that ARR is estopped from claiming breach of contract, (4) finding that ARR agreed to Change Order No. 1 and cannot seek additional compensation for the additional work, (5) finding that ARR’s acceptance of payment pursuant to Change Order No. 1 constitutes accord and satisfaction, (6) finding that ARR was not entitled to a 25-percent markup for any additional work required, (7) granting summary judgment in favor of NFM and Benchmark for fraudulent and negligent misrepresentation, and (8) finding Benchmark was a design professional acting within the scope of its contractual obligations and was entitled to the design professional’s privilege. STANDARD OF REVIEW In reviewing a summary judgment, an appellate court views the evidence in the light most favorable to the party against whom the judgment was granted and gives that party the benefit of all reasonable inferences deducible from the evidence. Durre v. Wilkinson Development, 285 Neb. 880, 830 N.W.2d 72 (2013). An appellate court will affirm a lower court’s grant of summary judgment if the pleadings and evidence show that there is no genuine issue as to any material fact or as to the ultimate inferences that may be drawn from the facts and that the moving party is entitle to a judgment is a matter of law. Id. ANALYSIS Breach of Contract, Implied Covenant of Fair Dealing, and Estoppel. ARR alleges that the district court erred in granting summary judgment on its claims for breach of contract and breach of implied warranty regarding NFM. The crux of ARR’s claim is that the Contract was ambiguous as to whether it included or excluded the design documents provided to them as part of the bidding process which were inaccurate as to the actual condition and design of the decking on the roof and ultimately required the changes and additional work performed. ARR further argues that the district court erred in finding that it was estopped from pursuing its breach of contract claim on the basis there was a question of fact as to whether the elements of estoppel were met regarding its claim for damages based upon the delays in the commencement of the project. Whether a contract is ambiguous is a question of law. Plambeck v. Union Pacific RR. Co., 244 Neb. 780, 509 N.W.2d 17

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Durre v. Wilkinson Development
830 N.W.2d 72 (Nebraska Supreme Court, 2013)
Wiekhorst Bros. Excavating & Equipment Co. v. Ludewig
529 N.W.2d 33 (Nebraska Supreme Court, 1995)
Plambeck v. Union Pacific Railroad
509 N.W.2d 17 (Nebraska Supreme Court, 1993)
White v. White
709 N.W.2d 325 (Nebraska Supreme Court, 2006)
Jennings v. Dunning
440 N.W.2d 671 (Nebraska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
ARR Roofing v. Nebraska Furniture Mart, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arr-roofing-v-nebraska-furniture-mart-nebctapp-2019.