Arnold v. Luedtke Engineering Co.

196 F. App'x 331
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 4, 2006
Docket05-1416
StatusUnpublished
Cited by1 cases

This text of 196 F. App'x 331 (Arnold v. Luedtke Engineering Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arnold v. Luedtke Engineering Co., 196 F. App'x 331 (6th Cir. 2006).

Opinions

DAMON J. KEITH, Circuit Judge.

Appellant, Richard T. Arnold (“Arnold”), appeals the district court’s order granting summary judgment to Luedtke Engineering Co. (“Luedtke”), on Arnold’s claim of negligence under the Jones Act, 46 U.S.C. § 688, and vessel unseaworthiness pursuant to general admiralty and maritime law, against his employer. The district court found that Arnold was not a “seaman” as defined by the Jones Act during his employment of reconstructing a seawall along the shore of the Erie Canal. We conclude, however, that the district court erred in employing a snapshot test for seaman status and improperly took the mixed question of law and fact away from the jury. Accordingly, we reverse the decision of the district court and remand this case for trial.

I. Background

Luedtke is a maritime construction and dredging company involved in maintenance dredging, marina construction, and break-wall construction. Over the past twenty-three years, Arnold was employed with Luedtke in various capacities including runner, deckhand, tugboat pñot, and project foreman. Arnold, as part of his employment with Luedtke, was a member of the Seafarers International Union for over 20 years and licensed as a tugboat Captain.

[332]*332A. The Black Rock Lock Project

The events giving rise to this dispute occurred in September 2002 while Arnold was assigned as project foreman to a seawall reconstruction project at Black Rock Lock in Buffalo, New York. The seawall is 750 feet in length along the shore of the Erie Canal. From the waterside, the seawall is seven feet tall, however, from the beachside the wall is waist-level. Luedtke’s task on the project, which took approximately nine months to complete, was to straighten the seawall and ensure that the material from the beach did not enter the canal. At the beginning of the project, five Luedtke employees were assigned to the job in addition to the Corp. of Engineers representative who was there daily. The project was constructed in four phases: (1) sheet piling, (2) stone placement behind the refurbished wall, (8) wedge plate attachment, and (4) concrete pouring. Arnold fully participated in the first two phases of the project and was injured during the end of the third phase. The project began in February 2002 and continued until November of that year. Arnold was injured at the end of September, at least seven months into the project and at most two months from the completion of the project.

There were three vessels that were used to complete the Black Rock Lock project: a tugboat, derrick boat, and floating work raft. The Luedtke tugboat was used to push the derrick boat to the work site. Arnold was the Captain of the tugboat as it departed from Michigan to Buffalo, New York. The derrick boat is a one-hundred thirty foot by forty foot barge. It contains navigation lights, anchoring spuds, a galley, and sleeping quarters. While the derrick boat can be moved short distances by using an attached crane, the tugboat is generally utilized to transport it. During the first two phases of the project, the derrick boat was used to transport equipment and materials from one side of the lock to the other side. Additionally, the Luedtke employees placed a crane on the derrick boat in order to assist in the placement of the steel plates along the seawall. Finally, the floating work raft is a forty by six foot pontoon raft. The raft was moved around the seawall both manually by Arnold and, at other times, mechanically by a crane. The work raft was used as a platform from which Arnold could weld steel plates onto the seawall from the waterside.

Arnold’s job duties at the Black Rock Project were varied. As project foreman he reported to the superintendent. He was also the tugboat captain. In addition to his foreman and captain responsibilities, he was responsible for overseeing the sheeting phase, pouring concrete behind the wall, tying rebar, setting tubes,1 and finally welding wedge plates to each tube.2 Arnold also was responsible for making repairs to the derrick boat and inspecting it every morning.

B. The Accident

When the wedge plate phase began, between seven or eight months into the project, Luedtke had laid off or otherwise released/reassigned all other employees associated with the project aside from Arnold and Rich Payment (“Payment”), another Luedtke employee. The third phase required Arnold to engage in welding one-hundred pound steel plates to the new seawall. In order to maneuver the plate into place along the seawall, first, Arnold would carry a plate by hand a short dis[333]*333tance from the beach to the seawall. Then he would place the plate on top of the seawall, step on to the seawall and attach the plate to a cable jack, which lowered the plate into position on the waterside of the seawall. Finally, Arnold would lower himself onto the work raft where he would weld the plate into place.

While Arnold worked abroad the raft, Payment’s job was to assist a separate construction company, which used the derrick boat to complete its part of the seawall. Arnold was in charge of piloting the tugboat when the construction company indicated that the derrick boat needed to be moved. According to Arnold, at a maximum he piloted the tugboat three to four times per day for an estimated fifteen to twenty minutes per tug during the four to five week welding phase. Arnold estimated that the longest tow he was required to make on this phase of the Black Rock Lock Project was three to four hundred feet. Testimony indicated that the Breyman construction company worked ten hours per day after which Payment would return to the raft and assist Arnold. It was during the course of the time Arnold was working alone that his injury allegedly occurred.

In early September 2002, Arnold began experiencing back pain while lifting the wedge plates. Arnold continued to work for approximately three more weeks until he could no longer get out of bed due to the pain. Arnold officially left the job on September 20, 2002 and Payment finished the wedge phase with another Luedtke employee within seven days. The entire project was completed in November 2002.

On October 14, 2002, Arnold underwent back surgery. Subsequently, his treating physician declared him unfit for his prior occupation. Pursuant to the employment contract with the Seafarer’s Union, Luedtke paid Arnold $300 per week following his injury as maintenance and cure. Maintenance and cure is paid to injured members of the union by their employers. Thereafter, Arnold brought the present suit alleging negligence and vessel unseaworthiness under the Jones Act stemming from his injury while working on the seawall. The district court found that Luedtke was entitled to judgment as a matter of law because Arnold did not satisfy the two-prong Chandris test that the Supreme Court developed to determine the status of seaman under the Jones Act. Chandris, Inc. v. Latsis, 515 U.S. 347, 115 S.Ct. 2172, 132 L.Ed.2d 314 (1995). Arnold filed a timely notice of appeal with this Court.

II. Discussion

A. Standard of Review

We review a district court’s grant of summary judgment de novo. Golden v. City of Columbus,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
196 F. App'x 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arnold-v-luedtke-engineering-co-ca6-2006.