Arnold Altex Aluminum Co. v. Sire Plan, Inc.
This text of 149 So. 2d 79 (Arnold Altex Aluminum Co. v. Sire Plan, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The defendant appeals a judgment entered on a trial without a jury, in an action for damages for alleged breach of a contract for manufacture and installation of windows and doors in an apartment building. The trial court held there was a breach of contract, assessed the damages and entered judgment.
The complaint alleged, and the trial judge so found, that Comas Corporation was an undisclosed principal, on whose behalf Es-cot Construction Corp. made the contract [80]*80with the defendant Arnold Altex Aluminum Co.1
As its first point appellant argues that because the contract provided that a subcontractor was not entitled to look to the owner, “the owner in turn may not look to the subcontractor.” We must reject that contention as not being applicable to this case. That argument assumes that Escot Construction Corp. was the contractor and that defendant was a subcontractor. As pointed out above, it was alleged that the Comas Corporation was an undisclosed principal for whom Escot made the contract with the defendant. Appellant’s theory of the facts would require not only that we disregard that allegation but that we reject the finding of the trial judge, quoted above, where he held that the relationship as alleged in the complaint was established by the evidence, resulting in a direct contract between Comas and the defendant. Appellant makes no showing to warrant such action by us. The trial judge was the trier of the facts, and his finding on this pivotal point of the case was not shown to be wholly wrong or against the manifest weight of the evidence.
In a second point appellant challenges the assignment under which the plaintiff maintained the action as assignee of the claim of Comas against the defendant. The assignment was in writing. The trial judge held the assignment effective for the purpose and we agree.
Affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
149 So. 2d 79, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arnold-altex-aluminum-co-v-sire-plan-inc-fladistctapp-1963.