Armenti v. Brooklyn Union Gas Co.

157 A.D. 276, 142 N.Y.S. 420, 1913 N.Y. App. Div. LEXIS 6575
Appellate Division of the Supreme Court of the State of New York·Decided May 23, 1913·Published·Cited by 11 cases

Opinion

Burr, J.

This action is brought to recover for the pecuniary injury resulting from the death of Francesco Armenti on the 20th of November, 1908, through the caving in of an excavation made through Gold street, in the borough of Brooklyn, for the purpose of constructing a sewer. Plaintiff’s intestate was in the employ of defendants Rodgers and Hagerty, who had a contract with the city of New York for such construction. The Brooklyn Union Gas Company and the Edison Electric Illuminating Company were originally joined with Rodgers & Hagerty as parties defendant. When the action was brought to trial the complaint was dismissed as to the gas company and the illuminating company on the pleadings and opening of counsel. The propriety of this ruling is acquiesced in. At the close of plaintiff’s case the complaint was dismissed as to the defendants Rodgers & Hagerty, and the exceptions were ordered to be heard in the first instance at the Appellate Division of this court. Under such cbcumstances plaintiff is entitled to the most favorable construction of the evidence.

The complaint alleged the service of a notice under the Employers’ Liability Act. When offered in evidence it was excluded as defective and insufficient. The notice is not made a part of this record, and the correctness of this ruling seems to be conceded. Defendant’s liability, if any, must, therefore, rest upon a breach of a master’s obligation to his servant, unaffected by that statute.

The causes for the accident, and the grounds of negligence set forth in the complaint as amplified by the bill of particulars, were various. The one finally relied upon was failure to properly shore, support and secure the sides of the excavation made for the construction of such sewer, and to maintain such shoring so that it should be safe and suitable. The questions presented, therefore, are two-fold: first, does the evidence permit a finding that the subsidence occurred because the shoring [278] and bracing gave way, and if so, are the defendants liable therefor? The sewer was built of concrete, was nearly circular in form, about seventeen feet in diameter, and was laid at the bottom of an open trench about eighteen feet wide and about forty-five feet deep. On the day of the accident about one hundred and thirty-five feet of this trench was open. The sewer had been constructed in two sections, and the lower half or invert of the sewer at the bottom of the trench had been completed. This invert was at least seven feet in height from the bottom of the excavation, and extended the entire width thereof between the sheathing on either side. Defendants were about to place upon the top of the completed invert iron forms over which concrete was to he put to the thickness of two feet or more, making in connection with the previously constructed invert a completed tube, and while thus engaged the sides of a portion of this open cut caved in, and plaintiff’s intestate was caught in the mass of falling material and killed. After the occurrence earth, timber, gas mains, pipes, masonry, and even the paving and flagging which had been upon the surface of the street adjoining the excavation were mingled together at the bottom thereof, in such confusion that it would be at least difficult to draw any very satisfactory conclusion from what then appeared as to the manner of construction. There is evidence, however, most of which was given by four of the workmen employed in the construction of said sewer, from which a jury could have found the following facts: In preparing the excavation for the reception of this concrete structure, the sides thereof had been sheathed with planking about two inches in thickness. This sheathing was supported by “rangers” running longitudinally along the sides of the sheathing on the inner side thereof. These rangers consisted of planks from nine to twelve inches in width. Across the excavation and supporting these rangers were cross-braces horizontally placed. There is a slight variance in the testimony as to the distance which separated these cross-braces, but the greater weight of the more reliable testimony is that they were five feet apart, measured in a vertical line, and six or eight feet apart horizontally. It appeared that in order to make room for the iron forms which were to be [279] placed upon the top of the completed invert it was necessary to remove a part of this cross-bracing, and there is no suggestion that the method adopted of building the lower half of the sewer and then placing upon that the iron forms to sustain the concrete for the construction of the upper half, and the removal of a portion of the cross-bracing in order to permit this to be done, was not a proper method of construction if carefully employed. Di Orescenti, • a fellow-workman of decedent, who, upon the morning when the casualty occurred, was engaged in filling in that portion of the excavation where the sewer had been completed, testified that on previous occasions it had been the custom to place forms about twenty-five or thirty feet long, removing the cross-bracing for that purpose. On this day, when the work was approaching completion, the space cleared for the forms was sixty feet in length. It appears that it was the duty of a gang, known as the carpenter’s gang, to construct the supports for the excavation, and to prepare for the placing of the iron forms when that became necessary. Decedent was a member of a gang known as the concrete gang, whose duty it was to prepare and lay the concrete when the forms had been put in place. Di Orescenti testified that on the morning in question the carpenter’s gang had taken away three lines of cross-braces, one over the other, for a distance of sixty feet, leaving only five or six of these cross-braces between the top of the excavation and the point where the lower cross-brace remained, instead of ten or eleven as had previously been employed. He also testified that he noticed that the timber which was the lowest of those not taken away started to break, and then the sheathing boards commenced to give in below, and that after the earth had fallen from down below, then the top came down, too. He testified that he heard a cracking sound about four or five minutes after the braces had been removed, and that none of the shoring planks fell until after the brace broke. Guerra, another fellow-workman of decedent, testified that three rows of these cross-braces, measured in a vertical line, had been taken away, leaving a space of fifteen feet measured from the bottom of the trench toward the top. Another witness, Heitmann, testified that he heard a rumble and cracking [280] of timber, and then saw everything on both sides falling in the trench toward the center of the street. He adds, “a little after everything was falling towards the center, the open gas main started in to light up.” Ernest 0. Moore, called as an expert witness by plaintiff, who on the day after the accident examined that portion of the excavation immediately adjoining the place of the subsidence which had escaped destruction, also testified as to the construction there employed, and his testimony does not vary substantially from that given by the coemployees of decedent in the particulars above specified. He gave some additional testimony from which a jury might have found that the sheathing planks were of unequal length, varying from ten to fifteen feet, and that owing to the depth of the excavation it was necessary to employ three or more of these planks placed one on top of the other. The ends of these planks were referred to in the evidence as “butts,” and these ends were not spliced together. While it seems to have been the

Free access — add to your briefcase to read the full text and ask questions with AI

Armenti v. Brooklyn Union Gas Co., 157 A.D. 276, 142 N.Y.S. 420, 1913 N.Y. App. Div. LEXIS 6575 (N.Y. Ct. App. 1913).

157 A.D. 276 (Armenti v. Brooklyn Union Gas Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Staples v. Town of Amherst
146 A.D.2d 292 (Appellate Division of the Supreme Court of New York, 1989)
Kahn v. Gates Construction Corp.
103 A.D.2d 438 (Appellate Division of the Supreme Court of New York, 1984)
Navlyt v. Kalinich
260 N.E.2d 855 (Appellate Court of Illinois, 1970)
Bradley v. Metropolitan Sanitary District of Greater Chicago
206 N.E.2d 276 (Appellate Court of Illinois, 1965)
Cook v. Pieper
34 Misc. 2d 532 (New York Supreme Court, 1962)
El Paso Electric Co. v. Safeway Stores, Inc.
257 S.W.2d 502 (Court of Appeals of Texas, 1953)
C. K. Eddy & Sons v. Tierney
267 N.W. 852 (Michigan Supreme Court, 1936)
Rookstool v. Cudahy Packing Co.
158 N.W. 440 (Nebraska Supreme Court, 1916)
Mautsewich v. United States Gypsum Co.
112 N.E. 471 (New York Court of Appeals, 1916)
Coleman v. Ruggles-Robinson Co.
159 A.D. 268 (Appellate Division of the Supreme Court of New York, 1913)