Armco Drainage & Metal Products, Inc. v. State

3 Misc. 2d 803, 156 N.Y.S.2d 90, 1956 N.Y. Misc. LEXIS 1504
CourtNew York Court of Claims
DecidedOctober 15, 1956
DocketClaim No. 32880
StatusPublished

This text of 3 Misc. 2d 803 (Armco Drainage & Metal Products, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armco Drainage & Metal Products, Inc. v. State, 3 Misc. 2d 803, 156 N.Y.S.2d 90, 1956 N.Y. Misc. LEXIS 1504 (N.Y. Super. Ct. 1956).

Opinion

Richard S. Heller, J.

This claim has been submitted to the court on an agreed statement of facts. The claim arises out of a contract for the construction of an arterial highway in the city of Binghamton.

[805]*805The Department of Public Works prepared a bid proposal and specifications for the work. The construction involved the diversion of a stream through a 102-inch diameter steel pipe, part of which, known as multi-plate ”, was to be installed in an open cut and part of which, known as “ tunnel liner plate ”, was to be installed in a tunnel. Detailed specifications of the mechanical and physical characteristics and methods of installation of the tunnel liner plate were set forth.

The tunnel liner plate as specified was unique and had been developed by the plaintiff so that tunnels could be constructed by unskilled workmen classified as common laborers. For many years installations of tunnel liner plate by the claimant and others using the plate had been made by common laborers paid at the prevailing wage for common laborers in the areas where the work was done. This information was given to the Department of Public Works by the claimant and it was contemplated both by the claimant and the Department of Public Works that the work would be performed by common laborers to be paid at the rate of $1.87% per hour with two men having previous experience in the work, being paid at the rate of $2.15 per hour.

As required by section 220 o'f the Labor Law, the bid proposal contained a schedule of job classifications and the minimum wage to be paid to each of these classifications. The only job classification contained in that schedule applicable to the installation of tunnel liner plate was “ Laborer ” at a minimum wage of $1.71 per hour.

Prior to the award of the contract, claimant had entered into a contract with N. R. Corbisello, Inc., and Triple Cities Construction Co. whereby claimant was to perform the installation of the multi-plate and tunnel liner plate in the event that Corbisello and Triple Cities were awarded the contract and claimant was approved as a subcontractor by the State as required by the contract provisions set forth in the bid proposal. In entering into this contract claimant was aware of the schedule of minimnffl hourly rates and contemplated payments of not more than the rate to be paid by the prime contractors for laborers of $1.87% per hour with two men experienced in the installation of tunnel liner plate being paid $2.15 per hour.

On June 20,1952 the contract was awarded to K R. Corbisello, Inc., and Triple Cities Construction Co. and on July 11, 1952 claimant was approved by the State as subcontractor to perform the work of installing the multi-plate and tunnel liner plate. On September 1, 1952 claimant commenced the installation of the multi-plate in the open cut leading to the site of the proposed tunnel and this work was performed by ironworkers at [806]*806the rate of $2.82 per hour. The wage schedule attached to the bid proposal provided for “ Iron & Steel Worker (Structural) ” at a rate of $2.62% per hour. The wage schedule also contained a provision that labor classifications not listed could be used only with the consent of the Superintendent of Public Works and the rate to be paid was to be given by the Superintendent of Public Works after advising with the State Department of Labor.

On September 10,1952 the multi-plate installation was stopped by a jurisdictional dispute between the Ironworkers Union and the Laborers Union which was settled between the unions and the installation continued as before. On October 14, 1952 claimant commenced installation of the tunnel liner plates utilizing two men having previous experience in the work at a rate of $2.15 per hour and common laborers at $1.87% per hour. A demand was made by the union that claimant pay the so-called New York sand hog rate of $3 per hour or at least the $2.82 per hour being paid ironworkers on the multi-plate installation. Claimant refused and on October 17, 1952 a strike was called shutting down the entire project.

On the same date the Department of Public Works requested the Industrial Commissioner to furnish wage rates for positions on the project identified as “liner plate laborer (free air) ” and “ tunnel laborer (free air) ” indicating that union officials claimed the rate should be $2.14% and $1.87% per hour respectively. On the same date the Industrial Commissioner advised the Department of Public Works of prevailing hourly wage rates as

“Liner Plate Laborer (free air) $2.14%
Tunnel Laborer (free air) 2.14%
Laborer (common) 1.87

and the Department of Public Works so informed the claimant. The Laborers Union continued to object to the wage rates but permitted resumption of work on the project with the exception of the tunnel, and discussions continued among claimant, the general contractor, the Department of Public Works, union officials and the State Labor Mediation Board.

On October 23, 1952 the Binghamton district engineer of the Department of Public Works wrote to the Department of Public Works at Albany:

This letter is to confirm isy telephone conversation with you in response to a request by the Depart rent of Labor that wage rates for the following proper classifications in resp > <it to tunnel work on the above identified contract be furnished to us. Position are:
[807]*807Liner Plate Tunnel (in free air)
1. Miner
2. Miner’s Helper
3. Mucker
4. Tunnel Laborer
5. Electrician
The tunnel work is being held up until these classifications are established and wage rates furnished.
Kindly advise as quickly as possible when rates are established so that the same can be posted on the project.

On October 24, 1952 the Department of Public Works in Albany wrote a letter to the Industrial Commissioner:

Will you please furnish us minimum hourly wage rates for Contract FAC 52-3, FASH 52-8, Proj. U-496(8), Broome Co., Prev. Rate Case No. 52-932, on the following occupations:
Miner
Miner’s Helper
Mucker
Tunnel Laborer
Electrician
This confirms our telephone conversation in which it was explained that local union oficiáis have caused a holdup of all work on this Contract until what they claim are the proper occupations and rates are used by the contractor on this work.

On October 27, 1952 the Industrial Commissioner reported to the Department of Public Works in Albany,

that the prevailing hourly wage rates for such work are as follows:
Miner $2.82
Miner’s Helper 2.14%
Mucker 2.14%
Tunnel Laborer 2.12%
Electrician 2.75

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glanzer v. . Shepard
135 N.E. 275 (New York Court of Appeals, 1922)
Ultramares Corp. v. Touche
174 N.E. 441 (New York Court of Appeals, 1931)
Armco Drainage & Metal Products, Inc. v. Moore
285 A.D. 236 (Appellate Division of the Supreme Court of New York, 1954)
Building Chemicals Corp. v. State
164 Misc. 407 (New York State Court of Claims, 1937)
Armco Drainage & Metal Products, Inc. v. State
1 Misc. 2d 94 (New York State Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
3 Misc. 2d 803, 156 N.Y.S.2d 90, 1956 N.Y. Misc. LEXIS 1504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armco-drainage-metal-products-inc-v-state-nyclaimsct-1956.