Armada Oil Company LLC v. Barrick Enterprises Inc

CourtMichigan Court of Appeals
DecidedSeptember 22, 2015
Docket321636
StatusUnpublished

This text of Armada Oil Company LLC v. Barrick Enterprises Inc (Armada Oil Company LLC v. Barrick Enterprises Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armada Oil Company LLC v. Barrick Enterprises Inc, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

ARMADA OIL COMPANY LLC d/b/a AOG UNPUBLISHED TRUCKING, September 22, 2015

Plaintiff-Appellant,

v No. 321636 Oakland Circuit Court BARRICK ENTERPRISES, INC., LC No. 2013-134391-CK

Defendant-Appellee.

Before: K. F. KELLY, P.J., and CAVANAGH and MURRAY JJ.

PER CURIAM.

Plaintiff appeals as of right an order granting defendant’s motion for summary disposition and dismissing its several claims premised on an alleged agreement between the parties. We affirm.

Plaintiff, AOG Trucking, is a motor fuel hauling company that has been co-managed by Allie Berry and Ali Jawad since October 1, 2009. Berry and Jawad were also the shareholders and corporate officers of a non-party entity called Armada Oil & Gas Company, which was a wholesale distributor of BP-branded gasoline. Defendant is a wholesale distributor of BP- branded gasoline also, and was a competitor of Armada Oil & Gas Company. On September 11, 2009, non-party Armada Oil & Gas Company assigned all of its product supply agreements to defendant. Thereafter, defendant sent a letter to Armada Oil & Gas Company’s former customers advising them that defendant would be servicing their accounts and that it would “use Armada as a common carrier to deliver your fuel.”

On October 17, 2009, plaintiff and defendant allegedly entered into the written agreement that gives rise to this lawsuit. Plaintiff claims that this written agreement was premised on a prior verbal agreement that was reached when the assignment was entered into by non-party Armada Oil & Gas Company and defendant. More particularly, plaintiff claims that defendant promised to use plaintiff as its exclusive fuel hauler for former customers of Armada Oil & Gas Company, and to split the resulting profits equally with plaintiff. The alleged written agreement states:

(1) Armada to haul product pursuant to contract

(2) AJ & Allie to provide all dealer contracts to Barrick on Monday 10-19-09

-1- (3) On all transfer customers Barrick & AOG split profit 50-50 after costs

The parties agree that subsequent attempts to enter into a formal “Common Carrier Agreement” failed. But defendant used plaintiff as a fuel hauler on occasion between October 23, 2009 and May 2, 2010. Defendant claimed that it stopped doing so after it acquired 51 former customers of Armada Oil & Gas Company at the cost of $1.5 million—which was paid to Armada Oil & Gas Company—through the terms of a May 11, 2010 Global Settlement Agreement that was reached in four federal lawsuits involving Armada Oil & Gas Company. Plaintiff admits that it took no action to enforce the alleged October 17, 2009 agreement until May 2013, when it sent a “demand letter” to defendant regarding the breach of that agreement.

This case was filed on June 6, 2013. On September 5, 2013, plaintiff’s second amended complaint was filed. In Count I, plaintiff alleged breach of contract with regard to the October 17, 2009 “agreement.” In Count II, plaintiff alleged a breach of contract claim as a third-party beneficiary of the October 17, 2009 “agreement.” In Count III, plaintiff alleged fraud and intentional misrepresentation, claiming that defendant falsely represented that it would use plaintiff as its fuel hauler and split the profits with plaintiff. In Count IV, plaintiff alleged promissory estoppel, claiming that (1) it entered into the October 17, 2009 agreement with defendant, (2) defendant promised to use plaintiff to haul all of the fuel to Armada Oil & Gas Company’s former customers and to pay plaintiff fifty percent of the profit, but (3) defendant failed to perform as promised. In Count V, plaintiff alleged unjust enrichment, claiming that (1) plaintiff entered into the October 17, 2009 agreement with defendant, (2) defendant promised to use plaintiff to haul all of the fuel to Armada Oil & Gas Company’s former customers and to pay plaintiff fifty percent of the profit, but (3) plaintiff was not used to haul fuel and defendant kept all of the profit for itself. In Counts VI and VII, plaintiff alleged statutory and common-law conversion, claiming that defendant did not use plaintiff to haul fuel as promised and kept the profit for itself. In Count VIII, plaintiff asserted a claim for specific performance, requesting that defendant be ordered to use plaintiff for hauling duties as specified in the October 17, 2009 agreement. And in Count IX plaintiff sought an accounting premised on defendant’s use of a third-party fuel hauler instead of plaintiff to service Armada Oil & Gas Company’s former customers.

Eventually, defendant filed a motion for summary disposition pursuant to MCR 2.116(C)(7), (8), and (10). In brief, defendant argued that the alleged October 17, 2009 agreement relied upon by plaintiff for most of its claims was unenforceable for several reasons, including that there was no meeting of the minds. The alleged agreement was missing several essential terms such as duration, exclusivity, and manner of termination. And, by review of the express terms, defendant clearly did not agree to use plaintiff as its exclusive fuel hauler for an indefinite term which could not be terminated at will. If anything, defendant argued, the alleged October agreement was merely a letter of intent to enter into a formal contract at a later date as demonstrated by the parties’ conduct. For example, defendant argued, an October 26, 2009 email by plaintiff’s counsel, Mr. Swatosh, confirms that he was specifically instructed by plaintiff “to table the discussion regarding a contract between Barrick and AOG.” The email further indicated that plaintiff was “hopeful” that defendant would use it on an as-needed basis as its fuel hauler in the future and that the matter would be revisited at a later time. And it was undisputed that plaintiff was used by defendant on an as-needed basis to haul fuel, for which plaintiff billed defendant two cents per gallon hauled. Further, defendant argued, all of

-2- plaintiff’s claims should be dismissed either because they relied on the alleged invalid agreement, were barred, or were unsupported by evidence.

Subsequently, the trial court agreed with defendant that the alleged October 17, 2009 agreement was not enforceable because it lacked “many material and necessary terms to form a meeting of the minds.” Further, the terms that were present were unclear. The court concluded that the alleged “agreement is so lacking that the trier of fact could do nothing more than guess at the intent of the parties.” At best, the court held, the agreement was a letter of intent to later enter into a formal agreement. Accordingly, the trial court dismissed plaintiff’s breach of contract claim. And because the alleged October 17, 2009 agreement was not enforceable, Counts II (third-party beneficiary), IV (promissory estoppel), V (unjust enrichment), VIII (specific performance), and IX (accounting) were also dismissed. Plaintiff’s conversion claims, Counts VI and VII, were dismissed as time-barred or, in the alternative, because plaintiff failed to allege that defendant was obligated to return specific money entrusted to it. Count III, the fraud claim, was dismissed because plaintiff failed to establish that a genuine issue of material fact existed on the issue whether defendant made a promise with no intent to perform. Accordingly, the trial court granted defendant’s motion for summary disposition and dismissed plaintiff’s complaint in its entirety. This appeal followed.

This Court reviews de novo the trial court’s decision on a motion for summary disposition. Spiek v Dep’t of Transportation, 456 Mich 331, 337; 572 NW2d 201 (1998). Similarly, “[t]he construction and interpretation of a contract present questions of law that we review de novo.” Saint Clair Medical, PC v Borgiel, 270 Mich App 260, 264; 715 NW2d 914 (2006).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Auto Club Ins. Ass'n
751 N.W.2d 443 (Michigan Supreme Court, 2008)
Lawsuit Financial, LLC v. Curry
683 N.W.2d 233 (Michigan Court of Appeals, 2004)
Spiek v. Department of Transportation
572 N.W.2d 201 (Michigan Supreme Court, 1998)
Morosini v. Citizens Insurance Co. of America
568 N.W.2d 346 (Michigan Court of Appeals, 1997)
State Bank of Standish v. Curry
500 N.W.2d 104 (Michigan Supreme Court, 1993)
Hess v. Cannon Township
696 N.W.2d 742 (Michigan Court of Appeals, 2005)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
Yerkovich v. AAA
610 N.W.2d 542 (Michigan Supreme Court, 2000)
Foreman v. Foreman
701 N.W.2d 167 (Michigan Court of Appeals, 2005)
Domas v. Rossi
217 N.W.2d 75 (Michigan Court of Appeals, 1974)
Burkhardt v. Bailey
680 N.W.2d 453 (Michigan Court of Appeals, 2004)
Jaye v. Tobin
202 N.W.2d 712 (Michigan Court of Appeals, 1972)
Derderian v. Genesys Health Care Systems
689 N.W.2d 145 (Michigan Court of Appeals, 2004)
Hi-Way Motor Co. v. International Harvester Co.
247 N.W.2d 813 (Michigan Supreme Court, 1976)
Higgins v. Monroe Evening News
272 N.W.2d 537 (Michigan Supreme Court, 1978)
Ardt v. Titan Insurance
593 N.W.2d 215 (Michigan Court of Appeals, 1999)
Danto v. Charles C. Robbins, Inc.
230 N.W. 188 (Michigan Supreme Court, 1930)
Lawsuit Financial, LLC v. Curry
261 Mich. App. 579 (Michigan Court of Appeals, 2004)
St Clair Medical, PC v. Borgiel
715 N.W.2d 914 (Michigan Court of Appeals, 2006)
White v. Taylor Distributing Co.
798 N.W.2d 354 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Armada Oil Company LLC v. Barrick Enterprises Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armada-oil-company-llc-v-barrick-enterprises-inc-michctapp-2015.