Arkwright Mills v. Aultman & Taylor Machinery Co.

145 F. 783, 76 C.C.A. 347, 1906 U.S. App. LEXIS 4024
CourtCourt of Appeals for the First Circuit
DecidedJanuary 26, 1906
DocketNo. 605
StatusPublished
Cited by4 cases

This text of 145 F. 783 (Arkwright Mills v. Aultman & Taylor Machinery Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arkwright Mills v. Aultman & Taylor Machinery Co., 145 F. 783, 76 C.C.A. 347, 1906 U.S. App. LEXIS 4024 (1st Cir. 1906).

Opinion

BROWN, District Judge.

This writ of error is for review Of the ruling of. the Circuit Court that the plaintiff was not entitled to go to the jury on the first, second, and third counts of the plaintiff’s declaration, and for review of certain rulings on questions of evidence.

The contract made May 19, 1897, concerning the sale of boilers, contained the following warranty:

“We furthermore guaranty that these boilers will show an evaporation of 10% lbs. of water from and at 212° per lb. of dry Pocahontas coal, 1 inch draft, Prof. George H. Barrus to make the test.”

The burden was upon the Arkwright Mills, as plaintiff suing upon this warranty, to prove that the required test was made by Prof. Barrus, and that under such test the boilers did not show the required evaporation.

It was in proof that the boilers were set during the fall and winter of 1897-1898, and that steam was put on them in February or March, 1898. The plaintiff offered evidence that a test was made by Prof. Barrus, the engineer named in the warranty, April 12 to 15, 1899. The Circuit Court was of the opinion that this test.was too late, and also that the test proved was not such a test as was called for by the contract.

The Circuit Court was of the opinion that the law required the plaintiff, if it desired to act upon the warranty, to act promptly, and to call Mr. Barrus down to make a test as soon as it reasonably could be done; and, if the boilers did not answer the test, to notify the de[785]*785fendant promptly, and let the defendant take out the boilers while they were worth something for some other purpose. In fact, the rulings of the Circuit Court upon the question of reasonable, promptness seem to be based entirely upon the consideration that, if the boilers did not fulfill the requirements, the defendant should be given an opportunity to take them out while in good condition and practically new. In deciding, however, whether this test was made within a reasonable time, it should be borne in mind that the purchaser of the boilers had an option, upon a breach of the warranty, to return the boilers, or to retain them, and to claim as damages the difference between the value of the boilers actually received and the value of the boilers contracted for. It was obvious in this case that the plaintiff had elected to retain the boilers, and to seek compensation in damages for breach of warranty. Upon this view, the test would be made in a reasonable time, provided the boilers were then in such a condition that they could be fairly" tested.

Our attention has been called to no evidence in'the case having a tendency to show that a test under the warranty could not have been made as fairly in April, 1899, as a year earlier. In fact, the plaintiff produced evidence, which was not contradicted, to the effect that a battery of boilers a year old, if kept in good condition, ought to run a little better than it would right after it was set up. It is very clear, we think, that it should not have been ruled, as a matter of law, that a test was not made within a reasonable time. Furthermore, there was evidence tending to show a request made by the plaintiff for, a test under the contract, and compliance by the defendant with this request. There was also evidence that a test of the boilers was made:, and was paid for equally by plaintiff and defendant.

That a test was agreed upon in the warranty, to be made by a certain person, that complaints were made as to the efficiency of the boilers, that a test was requested, that the expert named in the warranty did make an elaborate test costing $300, that the expense of this was borne equally by both parties, was, in our opinion, substantial evidence that the test required in the warranty, or, at least, a test which was regarded by the parties as a test under the warranty, had been made.

Prof. Barrus, defendant’s witness, testified that he made a certain test, saying:

“The test which I made there was a commercial test to determine the evaporative efficiency of these boilers under commercial conditions, by which 1 mean ordinary working conditions. My report states the evaporative efficiency of 1 líese boilers under ordinary working conditions.”

An elaborate report in writing was made by Barrus, dated May 19, 1899, copies of which were sent both to the plaintiff and defendant. In this report, under the head of .“Results,” is this statement:

“45. ICquiv. evap'n per lb. of dry coal from and at 212°, not including economizer, lbs.. Apr. 14, 9.497.”

Concerning this entry, Barrus testified:

“The statement iliaf the boiler evaporated 9.497 pounds of water from and at 212 degrees per pound of dry coal was a statement of fact which I deter[786]*786mined. It was a test. I did determine the working efficiency; that is. the efficiency of the boilers under working conditions, under ordinary working conditions.”

The plaintiff also introduced the evidence of Charles H. Bartlettv a consulting engineer, that the test described in the Barrus report was a proper test under the guaranty, except as to draft, and that the boilers used about one-tenth more fuel by reason of their evaporating only 9y2 pounds of water than they would have used if they had evaporated 10yi pounds of water. Evidence was offered showing that the draft was proper.

It is contended by the defendant .that the test made by Barrus was not a test under the warranty. In support of this contention, it argues that the object of the test, as stated in the report, was: First, to determine the general economy of the plaintiff’s plant under its usual working conditions; and, second, to ascertain what loss of steam or fuel, if any, was going on, and how to remedy-it and thereby reduce the fuel consumption. There was also evidence for the defendant tending to show that Barrus was not informed of the terms of the warranty, and was not requested to make a test under the warranty.

Barrus himself distinguished between kinds, of tests of the efficiency of a boiler; one being a working or commercial test, which he made, and the other an efficiency or guaranty test, which he says he did not make. He testifies that the test that he made did. not conform to the recognized rules of engineers in making a guaranty test. Mr. Barrus said:

“My position is that by tuning the boilers up, by having an expert fireman, and by running them and giving them every advantage, they might be made to evaporate more water than is shown there. I should want, for a guaranty test, an expert fireman.”

It is contended by the defendant that, as a matter of law, the warranty is to be interpreted as calling for an efficiency test or guaranty test, as distinguished from a test of working conditions. There is evidence, however, for the plaintiff, that at the time the test was made there was no distinction recognized in engineering practice between commercial tests and guaranty tests'.

Ordinarily, a business contract is to be construed in view of the business relations of the parties; but it is quite possible that, in a business contract, the parties may require á guaranty of maximum efficiency in order to secure a safe margin, and that a test of maximum efficiency under the best possible conditions may be agreed to by those who require for practical use a less degree of efficiency.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott v. Guschov
202 N.E.2d 241 (Massachusetts Supreme Judicial Court, 1964)
McNeal-Edwards Co. v. Frank L. Young Co.
43 F.2d 99 (First Circuit, 1930)
National Surety Co. v. United States
29 F.2d 92 (Ninth Circuit, 1928)
Southern Pac. Co. v. Fore River Shipbuilding Co.
219 F. 378 (First Circuit, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
145 F. 783, 76 C.C.A. 347, 1906 U.S. App. LEXIS 4024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arkwright-mills-v-aultman-taylor-machinery-co-ca1-1906.