Areyana Group of Construction Company

CourtArmed Services Board of Contract Appeals
DecidedMay 11, 2018
DocketASBCA No. 60648
StatusPublished

This text of Areyana Group of Construction Company (Areyana Group of Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Areyana Group of Construction Company, (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Areyana Group of Construction Company ) ASBCA No. 60648 ) Under Contract No. W5J9LE-12-C-0013 )

APPEARANCE FOR THE APPELLANT: Mr. Zabit Khan President

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney James D. Stephens, Esq. Edward J. McNaughton, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Memphis

OPINION BY ADMINISTRATIVE JUDGE PAUL ON THE GOVERNMENT'S MOTION TO DISMISS

This is a timely appeal of a contracting officer's (CO's) final decision denying appellant Areyana Group of Construction Company's (AGCC's) request for a 188-day time extension and the return of liquidated damages withheld by the government in a total amount of $380,512. The Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, is applicable. The government filed a motion to dismiss, contending that AGCC failed to certify its request and that, accordingly, the Board lacked jurisdiction to review its allegations. 1

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 28 December 2011, the government entered into fixed-price contract, No. W5J9LE-12-C-0013, with AGCC in a total amount of $13,058,609.03 (R4, tab 3 at 1-2). Under the contract, AGCC was required to design and construct "the Open Bay Barracks for the Afghan National Civil Orders Police (AN COP) Patrol Battalion at Tarim K wot, Uruzgan Province, Afghanistan" (id. at 5).

2. The contract incorporated by reference several Federal Acquisition Regulation (FAR) clauses, including FAR 52.233-1, DISPUTES (JUL 2002) (R4, tab 3 at 11), which included in pertinent part:

1 This decision pertains only to ASBCA No. 60648, which is consolidated with ASBCA No. 60649. (c) Claim, as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter by right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract. However, a written demand or written assertion by the Contractor seeking the payment of money exceeding $100,000 is not a claim under the [CDA] until certified.

The contract also contained FAR 52.211-12, LIQUIDATED DAMAGES-CONSTRUCTION (SEP 2000), which provided for damages in the amount of $2,024 for each day of delay in completing the work. In addition, the contract included FAR 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), which stated:

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and ( c) complete the entire work ready for use not later than 460 calendar days from notice to proceed. The time stated for completion shall include final cleanup of the premises.

(Id. at 33)2

3. On 4 December 2012, the contracting officer's representative (COR) informed AGCC that she was withholding 5 percent of progress payment No. 7 due to unsatisfactory performance (R4, tab 12). On 12 December 2012, the CO informed AGCC that, although it should have achieved completion of 52 percent, it had only made progress in the amount of 30 percent. He asked AGCC to provide a remediation plan. (R4, tab 13 at 1) As of2 January 2013, AGCC had not produced the requested plan. On that date, the COR informed AGCC that it was over 10 percent behind schedule and that accordingly, 10 percent of progress payment No. 8 was being withheld. (R4, tab 14 at 1)

4. On 8 January 2013, the COR informed AGCC that it was "over 20% behind schedule." On this basis, she wrote that she was preparing "an interim unsatisfactory evaluation" with respect to AGCC's work on the contract. (R4, tab 15 at 1) On 4 February 2013, the COR informed AGCC that it was withholding 10 percent of progress payment No. 9 for unsatisfactory performance (R4, tab 17). On 17 April 2013,

2 On 28 January 2012, the CO advised AGCC that the notice to proceed date would be 18 February 2012 and that it had 460-calendar days from that date to complete the project (R4, tab 7 at 1-2). Thus, the contract completion date was 23 May 2013 (R4, tab 13 at 1).

2 the COR reminded AGCC that the contractual completion date was 23 May 2013 and that the project was only 63 percent complete. She sought a completion plan from AGCC and noted that liquidated damages would be assessed for "each calendar day of delay." (R4, tab 19 at 1)

5. AGCC did not complete the project in a timely manner. On 24 August 2013, it cited security problems and bad weather as part of a request for equitable adjustment (REA). Through its request, AGCC sought a "no-cost time extension of...120 calendar days." (R4, tab 20 at 1-5) On 6 September 2013, the CO returned the REA "without action as it does not comply with the requirement of your contract" (R4, tab 22 at 1).

6. On 11 November 2013, AGCC forwarded another REA to the CO in which it sought a "no-cost time extension of...176 calendar days due to delay." It once again referred to ''the security situation," as well as "bad weather." (R4, tab 23 at 1-5)

7. On 25 November 2013, the CO forwarded the following response to AGCC's second REA:

Reference is made to your Serial Letter H-0008 ... subject as above. The following information is provided concerning your REA. After a thorough review, the Government notes that REA H-0008 submission is identical to your previous submission, H-0006 .... The only difference between AGCC's REA H-0006 and H-0008 is that your first submission included delay related to Pre-Engineering Building (PEB) Subcontractor under section "C" ofH-0006 which has now been omitted from H-0008. In fact, all other narratives in both letters are identical. Essentially, AGCC has submitted the same exact REA without any changes besides the exception noted. Your justification for time extension to the Contract Completion Date remains unchanged; same justification that was rejected and found to be "non-compliant" with the Contract requirements per Government SL C-0014 ....

You are hereby advised once again that your REA is returned without action as it does not comply with the requirements of your Contract as well as making an equitable adjustment request that is specifically excluded by the contract. As submitted, neither of your REAs can be reviewed for merit and furthermore, AGCC's reasoning and justification of merit for additional time is without basis. You are strongly urged to review the Contract requirements

3 specifically identified in SL C-0014 and comply with those requirements accordingly. No further action will be taken by the Government concerning this matter pending receipt of an REA that is compliant with the requirements of your signed Contract.

Should you have further questions, concerns or need additional clarification on this matter, please do not hesitate to contact the PE/COR or the undersigned. Your acknowledgement of this notice shall be provided to the Government within twenty-four (24) hours of receipt.

(R4, tab 24 at 1)

8. On 4 December 2013, the COR wrote to inform AGCC of the following:

As a result of the prefinal inspection conducted on 27 November 2013 it has been determined that your construction progress is sufficiently complete to allow the Government use and possession of the facility effective 27 December 2013. In accordance with Clause 52.246-21, titled "Warranty of Construction," your warranty coverage shall commence from this date and continue for a period of one year.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W.M. Schlosser Co. v. United States
705 F.2d 1336 (Federal Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Areyana Group of Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/areyana-group-of-construction-company-asbca-2018.