Ardoin v. Michigan Wisconsin Pipeline Co.

224 So. 2d 172, 34 Oil & Gas Rep. 366, 1969 La. App. LEXIS 6121
CourtLouisiana Court of Appeal
DecidedJune 12, 1969
DocketNo. 2688
StatusPublished
Cited by3 cases

This text of 224 So. 2d 172 (Ardoin v. Michigan Wisconsin Pipeline Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ardoin v. Michigan Wisconsin Pipeline Co., 224 So. 2d 172, 34 Oil & Gas Rep. 366, 1969 La. App. LEXIS 6121 (La. Ct. App. 1969).

Opinions

HOOD, Judge.

This is a suit for damages instituted by the undivided owners of a large tract of land in Acadia Parish against Michigan Wisconsin Pipeline Company. Plaintiffs contend that defendant constructed a pipeline across six tracts or fields of rice farmland owned by them, and that as a result of that construction it has become necessary for them to relevel the entirety of each such tract, including the part which lies outside the right of way. They seek to recover the cost of this releveling. Judgment on the merits was rendered by the trial court in favor of plaintiffs, awarding them the full amount claimed, aijd defendant has appealed.

The principal question presented is: Did the construction of this pipeline so disturb [173]*173the surface of the land that it became necessary to relevel the whole of each tract traversed by the pipeline, including all of the acreage lying outside the right of way

On May 25, 1967, plaintiffs granted to defendant a right of way to construct a pipeline across their property, the right of way traversing six separate tracts or fields of rice land owned by them. These tracts of land varied in size, ranging from 14 to 65.6 acres in area, and the total acreage involved amounted to an aggregate of 226.3 acres. The right of way agreement provides that the grantee was to have a working area 100 feet wide, with the proposed pipeline as the center line, and that after construction was completed, the servitude granted was to revert to a permanent right of way 25 feet wide, with the pipeline being in the center. The right of way agreement also recites that a consideration of $336.00 was paid for that servitude, and that the grantee agrees:

“1. To restore to the condition in which found, all contour levees present in the tract through which the right of way herein granted passes, and off the right of way; and which are affected and/or destroyed.”
* * * * * *
“3. To build and provide all levees necessary along both sides of the right of way herein granted in order to retain the rice irrigation water now present or to be used on the tract of land through which this right of way passes, and thereafter to restore the land so used to the condition in which found.”
* * * * * *
“9. To restore to the condition in which found the land contained in the working area grant made herein and in the permanent right of way grant granted herein; as well as any damages off the right of way, including land leveling, both on and off the right of way.”

On the day the above mentioned right of way was granted, plaintiffs also executed two “advance releases” in favor of defendant. One recites that in consideration of the sum of $3024.00 paid to plaintiffs, they release defendant from all damages, except damages to livestock and crops, which may occur upon the right of way as a result of the construction of the pipeline. The other release recites that in consideration of $7040.00, plaintiffs release defendant from any further claims of damages to the land, crops, timber, fences and improvements resulting from the construction of the pipeline on this right of way. Each of these releases specifies that the release is restricted to damages “on the right of way,” and that it does not apply to “off the right of way” land leveling which may be made necessary.

The pipeline was constructed during the months of June and July, 1967. When the construction was completed defendant re-leveled the property included within the right of way, but it did not reconstruct and reconnect the rice levees which had been severed or destroyed.

Plaintiffs contend that in constructing this pipeline across these six tracts of rice farmland, the surface of each tract was disturbed to the extent that it became necessary to relevel the entire tract. They contend that the cost of releveling land for raising rice amounts to $25.00 per acre, and that the cost of releveling the entire 226.3 acres affected by the pipeline thus amounts to $5657.50. Defendant concedes that the construction of a pipeline disturbs the surface of land located within the right of way. It contends, however, that the area within the right of way can be and was restored to its former condition, and that plaintiffs have already granted a release for all damages which may be due for damages to the land on the right of way. It takes the position that the construction of the pipeline did not make it necessary to relevel any part of plaintiffs’ land lying outside of that right of way, and thus that plaintiffs are not entitled to recover.

A common and accepted practice in farming rice is to level the land and then [174]*174construct levees so that each levee will be located on and along a contour line which varies only about two inches in elevation from the bases of the levees which are on either side of it. A rice farmer usually rotates his crops so that after rice has been raised on a tract of land one year, the land is then permitted to lie idle or it is planted in wheat or soybeans the next crop season. Plaintiffs observed that practice generally, but they testified that “with this quota this year, it made us plant two years in a row on some pieces.” All witnesses apparently agree that the levees must be “knocked down” and that the land must be releveled when rice land is used for planting the interim crops of wheat or soybeans, and that the entire field must then be releveled and the levees must be rebuilt before the same land thereafter can be planted to rice.

In the instant suit, plaintiffs planted five of the six affected tracts of land to wheat or to soybeans during the 1968 crop season. The contour levees were knocked down on these tracts and the land was releveled before these interim crops were planted. There is nothing in the evidence to show that the construction of the pipeline made it necessary for plaintiffs to rotate these crops that year, or to change from rice to soybeans or wheat on those five tracts that crop season, and we conclude that that was done in accordance with their regular practice of rotating the crops on these tracts.

The releveling of these five tracts of land within a few months after the construction of the pipeline was completed, therefore, was done solely because of the need to rotate crops that year, and not because of the laying of the pipeline. And, since the levees on this land were knocked down and the land was prepared for raising beans or wheat in 1968, then for that reason, and regardless of whether a pipeline was constructed in 1967, it will be necessary for plaintiffs to relevel all of the same land before they again will be able to plant it to rice. The construction of the pipeline, therefore, did not cause or compel plaintiffs to relevel these five tracts of land.

One of the six tracts of land traversed by the pipeline was planted to rice during the 1968 crop season. That tract comprised a total of 65.6 acres. Plaintiff Edmond LeDoux testified that this tract was leveled in the latter part of 1966 or 1967, and that it was planted to rice during the 1967 crop season. The pipeline was constructed about the middle of that year. LeDoux stated that after the pipeline had been laid he and his brother tried to plant rice on the same tract the following year, that is during the 1968 crop season, without releveling the entire tract, but that “it didn’t work,” and that they then releveled the entire 65.6 acre tract before planting and raising rice on it that year. It was stipulated that Jack S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fred Merritt Farms, Inc. v. Columbia Gulf Transmission Co.
248 So. 2d 600 (Louisiana Court of Appeal, 1971)
McClelland v. Ford, Bacon & Davis Construction Corp.
234 So. 2d 541 (Louisiana Court of Appeal, 1970)
Ardoin v. Michigan Wisconsin Pipe Line Co.
227 So. 2d 145 (Supreme Court of Louisiana, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
224 So. 2d 172, 34 Oil & Gas Rep. 366, 1969 La. App. LEXIS 6121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ardoin-v-michigan-wisconsin-pipeline-co-lactapp-1969.