ARCO Construction Company, Inc. v. Americon Services Company, Inc.

CourtCourt of Appeals of Texas
DecidedMay 15, 2008
Docket01-06-00846-CV
StatusPublished

This text of ARCO Construction Company, Inc. v. Americon Services Company, Inc. (ARCO Construction Company, Inc. v. Americon Services Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ARCO Construction Company, Inc. v. Americon Services Company, Inc., (Tex. Ct. App. 2008).

Opinion

Opinion issued May 15, 2008





In The

Court of Appeals

For The

First District of Texas





NO. 01-06-00846-CV





ARCO CONSTRUCTION COMPANY, INC., Appellant


V.


AMERICON SERVICES COMPANY, INC., Appellee





On Appeal from County Civil Court at Law No. 2

Harris County, Texas

Trial Court Cause No. 825,594





MEMORANDUM OPINION


          Appellant, general contractor ARCO Construction Company, Inc., hired appellee, subcontractor Americon Services Company, Inc., to perform site work on a commercial construction project, pursuant to a written contract. When Americon did not receive payment as expected, it sued ARCO for breach of contract, failure to comply with payment obligations under Texas Property Code section 28.002 (“the Prompt Payment Act”), quantum meruit, sworn account, and trust fund violations. A jury found that ARCO violated the Prompt Payment Act by failing to timely pay sums due and awarded Americon: $61,417.70, plus interest and attorney’s fees. See Tex. Prop. Code Ann. § 28.002 (Vernon 2000). The jury found that Americon breached the contract but that its breach was excused, and the trial court rendered judgment that ARCO take nothing by its counterclaims.

           In five issues, ARCO contends that the trial court erred (1) by granting relief under the Prompt Payment Act; (2) by “fail[ing] to award ARCO the damages awarded by the jury for Americon’s breach of contract”; (3) by “allowing Americon to draw adverse inferences” from ARCO’s redactions to its admitted bills for attorney’s fees; (4) by failing to properly apply the parties’ stipulated attorney’s fees; and (5) by concluding that Americon was entitled to recover on its alternative theories.

          We affirm.

Facts and Procedural History

          In 2003, TMT Properties hired ARCO, a Missouri-based commercial general contractor, to construct offices and a warehouse on property owned by TMT in Houston, Texas, for $5,100,000 (“the Project”). ARCO subcontracted with Americon to perform the site work on the Project for $359,000.

          Pursuant to the terms of the subcontract between ARCO and Americon (the “Contract”), Americon was required to, inter alia, identify its subcontractors and material suppliers; to provide valid lien waivers prior to payment; and to “protect and fully indemnify [TMT and ARCO] against all liability for claims and liens for labor, materials, appliances, equipment, and supplies whatsoever, including any costs, attorney’s fees, and incidental and consequential damages resulting therefrom.”

          Americon subcontracted with C.M. Nunez Trucking Company (“Nunez”) to haul dirt for the Project. At the conclusion of the Project, in November 2003, Americon submitted payment to Nunez in exchange for a lien waiver. Americon drafted the lien waiver for $72,096, the amount it owed Nunez on the Project; however, Americon drafted its check to Nunez for only $55,800. Americon took a set-off of $16,296 from its payment to Nunez because Nunez allegedly owed this sum to Americon on a prior, unrelated project. Nunez signed the lien waiver and then discovered the discrepancy in the amount of the check. On December 29, 2003, Nunez sent to ARCO a notice of intent to file a lien on the TMT property.

          Nunez had obtained the dirt it hauled to the Project from Prime Tree & Landscaping, Inc., d/b/a Mulch Matters (“Mulch”). Americon was unaware of Mulch’s participation in the Project and therefore did not identify Mulch as a subcontractor in the Contract. ARCO and Americon believed that Nunez was providing the dirt for the Project. By the end of the Project, Nunez had failed to pay Mulch the sum of $53,161.48. On January 6, 2004, Mulch sent to ARCO a notice of intent to file a lien on the TMT property.

          By January 15, 2004, both Nunez and Mulch had filed liens with Harris County on the TMT property. On January 26, 2004, Mulch filed suit against ARCO and TMT to foreclose its lien.

          On February 19, 2004, ARCO sent written assurances to TMT that ARCO would defend and indemnify TMT against the liens and lawsuit, pursuant to the general contract. In addition, ARCO, through its Missouri legal counsel, sent a demand to Americon that Americon protect and indemnify ARCO from the liens and lawsuit, pursuant to the Contract. ARCO also notified Americon that it was incurring legal expenses and that these expenses would substantially increase over time.

          On February 20, 2004, Americon, through its counsel, Christian, Smith, & Jewell (“Christian”), responded that it was “evaluating whether [it] will assume the defense of ARCO in those matters involving Mulch Matters and Nunez Trucking.”

          On March 4, 2004, ARCO, through its Texas counsel, Beirne, Maynard & Parsons, L.L.P. (“Beirne”), answered the Mulch lawsuit. On March 8, 2004, ARCO, requested “bond-around relief” from Americon, in addition to the defense and indemnity under discussion. On March 16, 2004, ARCO sent a letter to Mulch confirming that Mulch would not attempt extra-judicial foreclosure of its lien. On March 17, 2004, ARCO emailed Americon to confirm that Americon had everything it needed to assume the defense of ARCO and again requested bond-around relief. On March 30, 2004, ARCO demanded written notification that Americon would assume the defense of ARCO and would provide indemnity and bond-around relief. In addition, ARCO inquired regarding where to send Beirne’s fee billing.

          On March 31, 2004, Americon notified ARCO that it was “not disputing its obligation to indemnify or to defend under the [Contract],” that it was working to resolve the matter, and that it anticipated that it would be able to resolve the matter by April 5, 2004.

          On April 6, 2004, Americon sent a letter to Nunez, indicating that Americon would send payment for the $16,296 that had been withheld, to be held in trust by Nunez’s counsel, in exchange for the release of the Nunez and Mulch liens and the dismissal of the Mulch suit. In addition, Americon notified ARCO that the liens would be released “within ten days.”

          

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Southwestern Bell Mobile Systems, Inc. v. Franco
971 S.W.2d 52 (Texas Supreme Court, 1998)
Burgmann Seals America, Inc. v. Cadenhead
135 S.W.3d 854 (Court of Appeals of Texas, 2004)
Smith v. Smith
112 S.W.3d 275 (Court of Appeals of Texas, 2003)
City of San Antonio v. City of Boerne
111 S.W.3d 22 (Texas Supreme Court, 2003)
Holland v. Wal-Mart Stores, Inc.
1 S.W.3d 91 (Texas Supreme Court, 1999)
Uniroyal Goodrich Tire Co. v. Martinez
977 S.W.2d 328 (Texas Supreme Court, 1998)
Randy v. Squires Construction, Inc.
188 S.W.3d 396 (Court of Appeals of Texas, 2006)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Hassell Const. Co., Inc. v. Stature Commercial Co.
162 S.W.3d 664 (Court of Appeals of Texas, 2005)
Cytogenix, Inc. v. Waldroff
213 S.W.3d 479 (Court of Appeals of Texas, 2007)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
Ostrow v. United Business MacHines, Inc.
982 S.W.2d 101 (Court of Appeals of Texas, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
ARCO Construction Company, Inc. v. Americon Services Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/arco-construction-company-inc-v-americon-services--texapp-2008.