Archer Western Contractors. LLC v. U.S. Department of Transportation

45 F.4th 1
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 26, 2022
Docket20-1520
StatusPublished
Cited by2 cases

This text of 45 F.4th 1 (Archer Western Contractors. LLC v. U.S. Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Archer Western Contractors. LLC v. U.S. Department of Transportation, 45 F.4th 1 (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued November 15, 2021 Decided July 26, 2022

No. 20-1520

ARCHER WESTERN CONTRACTORS, LLC, PETITIONER

v.

UNITED STATES DEPARTMENT OF TRANSPORTATION AND FEDERAL AVIATION ADMINISTRATION, RESPONDENTS

On Petition for Review of an Order of the Federal Aviation Administration

Jonathan J. Straw and Steven D. Meacham argued the causes for petitioner. On the briefs was Larry W. Caudle Jr.

Corinne A. Niosi, Senior Trial Counsel, U.S. Department of Justice, argued the cause for respondent. With her on the brief was Brian M. Boynton, Acting Assistant Attorney General.

Before: ROGERS and WALKER, Circuit Judges, and EDWARDS, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge WALKER. 2 WALKER, Circuit Judge: The Federal Aviation Administration hired Archer Western Contractors to build air traffic structures for an airport in Las Vegas. Archer completed the work, but there was some turbulence along the way. Archer now challenges the FAA’s resolution of three contract disputes.

On the first dispute, the FAA said that Archer waited too long to challenge the FAA’s failure to provide an equitable adjustment for a modification to the contract. For the second dispute, the FAA said that Archer’s claim regarding contract modifications’ “cumulative impact” was also untimely. As for the third dispute, the FAA found that Archer had failed to install proper rectangular airducts.

We hold that the FAA erred in dismissing as untimely Archer’s failure-to-provide-an-equitable-adjustment claim. We agree with the FAA on the other two issues.

I

Archer built an air traffic control tower, a terminal radar approach control building, a parking garage, and a guard shack at what was then called McCarran International Airport in Las Vegas. Over the course of the multi-year construction process, the FAA repeatedly changed the work that it had hired Archer to perform. Those contract modifications sometimes required Archer to stop work and incur delay costs.

After one of the delays, Archer requested an “equitable adjustment,” which is the compensation that the parties’ contract requires the FAA to pay Archer when contract changes “increase . . . the cost of, or time required for performing the work.” JA 136. 3 In December 2013, the FAA formally denied Archer’s requested equitable adjustment, opting instead to unilaterally adjust the contract and award Archer less for the delays than it asked for. A year and four months later, in April 2015, Archer filed a notice of contract dispute with the Office of Dispute Resolution for Acquisition (ODRA), which is the FAA’s dispute-resolution tribunal. The notice listed first among its claims the FAA’s breach of contract for “Failure to Provide Equitable Adjustment for Significant Design Modification.” JA 533.

Archer also brought other claims to the ODRA, including one related to its HVAC ductwork. Archer installed two types of airducts — round and rectangular. After installation, the contractually required antimicrobial coating in the round ducts began to flake off. There was also evidence of inadequate adhesion in the rectangular ducts. In response, the FAA rejected all the ducts as non-compliant with the contract and required Archer to replace them. Because Archer thought only the round ducts needed replacing, it sought reimbursement for the cost of replacing the rectangular ducts.

Four years later, in 2019, the ODRA received notice of a cumulative-impact claim. According to Archer, the FAA’s successive, significant changes to the contract rippled out to decrease the efficiency of the entire project. That cumulative impact, said Archer, generated additional, compensable costs, even for unchanged work.

The ODRA dismissed Archer’s failure-to-provide-an- equitable-adjustment claim as untimely, relying on contractual and regulatory provisions that require filing a claim within two years of its accrual. It reasoned that Archer’s claim accrued back in December 2012 when the FAA proposed the relevant contract change, not in December 2013 when the FAA denied 4 Archer’s requested equitable adjustment. Recall that Archer filed its failure-to-provide-an-equitable-adjustment claim in April 2015.

In addition, the ODRA dismissed Archer’s cumulative- impact claim as untimely because it had been raised for the first time in 2019, several years after the closing of the two-year window for filing claims.

Finally, the ODRA found that the FAA had reasonably rejected all of the rectangular airducts in addition to the defective round airducts.

The FAA adopted the ODRA’s findings and recommendations in a final order. Archer then petitioned this Court for review. See 49 U.S.C. § 46110.

II

“Our review is confined to determining whether the FAA’s order adopting the ODRA’s findings and recommendations is arbitrary or capricious or contrary to law.” Multimax, Inc. v. FAA, 231 F.3d 882, 886 (D.C. Cir. 2000); see also 5 U.S.C. § 706(2)(A) (arbitrary or capricious standard). The FAA falls short of that standard when its decision “is not supported by substantial evidence” or when it “has made a clear error in judgment.” Multimax, 231 F.3d at 886 (cleaned up).

A

We begin with the first of Archer’s claims — that the ODRA, and thus the FAA, incorrectly dismissed as untimely Archer’s claim for “Failure to Provide Equitable Adjustment for Significant Design Modification.” JA 533. 5 We agree with Archer.

Government contracts often require the government agency to compensate the contractor when the agency’s modifications to the contract cost the contractor time or money. That compensation is called an equitable adjustment. Archer’s contract with the FAA requires the FAA to make an “equitable adjustment” when certain unexpected changes to the contract “increase . . . the cost of, or time required for performing the work.” JA 136.

Government contracts also often provide for the adjudication of disputes that might arise between the agency and the contractor. In Archer’s contract with the FAA, the contract said of equitable adjustments that the “[f]ailure to agree to any adjustment shall be a dispute.” JA 137.

Finally, when disputes like that arise, government contracts often require a contractor to file claims based on those disputes in a certain forum and by a certain time. In Archer’s contract with the FAA, that forum is the “dispute resolution system at the” ODRA. JA 133. And that time is “within two (2) years of the accrual of the contract claim involved.” JA 133; see also 14 C.F.R. § 17.27(c) (“A contract dispute against the FAA shall be filed with the ODRA within two (2) years of the accrual of the contract claim involved.”). FAA regulations specify that a claim accrues when “all events relating to a claim have occurred, which fix liability . . . and permit assertion of the claim.” 14 C.F.R. § 17.3(b).

So to sum up so far, under the terms of Archer’s contract with the FAA, Archer is entitled to an equitable adjustment if a contract modification by the FAA costs Archer time or money. The parties’ failure to agree to that equitable adjustment is a contract dispute. And a claim based on that 6 dispute must be filed with the ODRA within two years of the claim’s accrual.

That’s what happened here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Colbert v. O'Malley
District of Columbia, 2025

Cite This Page — Counsel Stack

Bluebook (online)
45 F.4th 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/archer-western-contractors-llc-v-us-department-of-transportation-cadc-2022.