Arch Insurance Company v. The Graphic Builders LLC

CourtDistrict Court, D. Massachusetts
DecidedFebruary 12, 2021
Docket1:19-cv-12445
StatusUnknown

This text of Arch Insurance Company v. The Graphic Builders LLC (Arch Insurance Company v. The Graphic Builders LLC) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arch Insurance Company v. The Graphic Builders LLC, (D. Mass. 2021).

Opinion

United States District Court District of Massachusetts

) Arch Insurance Co., ) ) Plaintiff, ) ) v. ) ) Civil Action No. The Graphic Builders LLC ) 19-12445-NMG ) Defendant. ) ) ) )

MEMORANDUM & ORDER

GORTON, J.

This case arises out of an alleged breach by The Graphic Builders LLC (“TGB” or “defendant”) of a Performance Bond issued by Arch Insurance Company (“Arch” or “plaintiff”) in connection with a commercial construction contract. Plaintiff seeks a judgment declaring that it is discharged from liability under the surety bond based on TGB’s failure to comply with an express and unambiguous condition precedent. Defendant, the general contractor, on the other hand, seeks a judgment declaring that Arch, as the surety, has an obligation under the bond to indemnify TGB independent from any condition precedent and that its failure to do so constitutes a breach of the Performance Bond and unfair and deceptive conduct in violation of M.G.L. c. 93A, §§ 2 & 11 (“Chapter 93A”). Pending before this Court are 1) defendant’s motion to amend its counterclaim and 2) plaintiff’s motion for summary judgment on its claim for declaratory relief and all

counterclaims asserted by defendant. For the reasons that follow, defendant’s motion will be denied and plaintiff’s will be allowed. I. Background Arch is a Missouri corporation with its principal place of business in New Jersey. It claims this Court has diversity jurisdiction over this action for a declaratory judgment against TGB, a Massachusetts limited liability company. A. The Agreements In or about May, 2017, TGB entered into a contract with 32 Cambridge Street, LLC to construct an apartment building in the Charlestown section of Boston, Massachusetts (“the Project”). A

few months later, TGB executed a subcontract with R.C.M. Modular Inc. (“RCM”) for certain modular construction work in connection with the Project. The subcontract required RCM, inter alia, to fabricate, deliver and assemble modular components of the apartment building, warrant that all work by RCM will be free from defects and indemnify TGB for any cost or damage arising from that work. In November, 2017, Arch issued a Performance Bond (“Performance” or “Surety” Bond) covering RCM’s work on the Project.1 That agreement provided that RCM and Arch agree to, “jointly and severally, bind themselves . . . to [TGB] for the performance of the [subcontract]” which has been incorporated

therein by reference. Relevant to the pending motions, Section 3 of the bond adds that the obligations thereunder of the surety (Arch) arise only after: 1) [TGB] provides notice to [RCM] and the Surety that [TGB] is considering declaring a Contractor Default . . .;

2) [TGB] declares a Contractor Default, terminates the Construction Contract and notifies the Surety; and

3) [TGB] has agreed to pay the Balance of the Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract.

By May, 2018, RCM had fabricated, delivered and begun installing the modular units for the Project. Soon thereafter, TGB complained that the units were defective, namely, that more than 260 windows were leaking and the exterior of the modules were misaligned, among other things. Despite the defects, TGB did not, however, terminate the subcontract with RCM because, in its own words, doing so “would be the equivalent of shooting [itself] in the face”. TGB, instead, unilaterally arranged for various third-party subcontractors to remediate RCM’s work at a

1 The Performance Bond issued by Arch is the 2010 version of an American Institute of Architect form known as the A-312 performance bond. cost of more than $2.8 million and subsequently sent several requests to Arch and RCM seeking indemnification therefor. B. Communications Between the Parties

Between October, 2018, and April, 2019, TGB issued several letters to Arch and RCM notifying them that TGB was considering declaring RCM in default of the subcontract and requesting contractual warranty and indemnification payments. In April, 2019, representatives of all three entities met to discuss matters relating to RCM’s non-performance but were unable to resolve the dispute. Later that month, TGB sent to RCM and Arch another letter which, pursuant to Section 3.1 of the Performance Bond, declared RCM in default of the subcontract but noted that TGB was “not yet terminating its subcontract with RCM”. Arch sent a written response 1) to confirm its receipt of the notice, 2) to refuse

TGB’s request for contractual warranty and indemnification payments and 3) to acknowledge that TGB had not terminated its subcontract with RCM. In the following months, TGB sent Arch several notices of default with respect to Arch’s performance under the Performance Bond and declared that Arch owed TGB $3 million, the purported cost of remediating RCM’s work. Arch, in response, rejected TGB’s demand and denied liability under the Performance Bond based on TGB’s failure to terminate the subcontract with RCM. C. Procedural History In December, 2019, Arch filed this suit seeking a declaration that TGB has materially breached the Performance

Bond by failing to terminate RCM as a subcontractor, a condition precedent, thereby rendering the bond null and void and discharging Arch from liability thereunder. In January, 2020, TGB counterclaimed that Arch, independent from any condition precedent, is required by the Performance Bond to cure RCM’s defective work, indemnify TGB and issue it warranty payments. TGB asserts three counts: breach of the Performance Bond (Count I); unfair and deceptive conduct in violation of Chapter 93A (Count II) and a claim for declaratory judgment (Count III). On June 5, 2020, TGB moved to supplement its counterclaim pursuant to Fed. R. Civ. P. 15. It seeks to add factual allegations which arose after it filed its counterclaims,

namely, that Arch retaliated against TGB for asserting a Chapter 93A claim by threaten[ing] TGB that absent withdrawal of the [Chapter 93A] Counterclaim, it would terminate its surety relationship with Tocci (TGB’s parent company).

(parentheses in original). TGB did not withdraw the claim and, “in retaliation of TGB’s refusal”, Arch allegedly terminated its surety relationship with TGB’s corporate parent (Tocci) which purportedly caused Tocci to lose out on a $35 million project. Finally, TGB submits that Tocci has assigned all of its rights against Arch to TGB. A few weeks later, Arch moved for summary judgment,

contending that Section 3 of the Performance Bond unambiguously provides conditions precedent to its obligation to perform under the bond agreement. Arch submits that terminating the subcontract with RCM is one such condition which TGB has not satisfied. That failure, Arch avers, discharges it from liability under the Performance Bond and warrants entry of summary judgment in its favor. TGB disagrees, rejoining that there is no condition precedent to Arch’s obligation to indemnify and issue a warranty to TGB for defects in RCM’s work because Section 1 of the Performance Bond renders Arch jointly and severally responsible for all of RCM’s obligations under the subcontract. TGB submits

that the Performance Bond distinguishes between 1) claims that require the surety to complete work on the Project, for which termination of the subcontract is a condition precedent and 2) claims that simply require the surety to reimburse TGB for damages caused by RCM’s breach of the subcontract, for which there is no condition precedent. That alleged distinction is purportedly based on the fact that the subcontract authorizes TGB to correct deficiencies of and seek indemnification from its subcontractor without termination. II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Penalbert-Rosa v. Fortuno-Burset
631 F.3d 592 (First Circuit, 2011)
Glassman v. Computervision Corp.
90 F.3d 617 (First Circuit, 1996)
Ocasio-Hernandez v. Fortuno-Burset
640 F.3d 1 (First Circuit, 2011)
Milissa Garside v. Osco Drug, Inc.
895 F.2d 46 (First Circuit, 1990)
Samuel Mesnick v. General Electric Company
950 F.2d 816 (First Circuit, 1991)
Patrick J. O'COnnOr v. Robert W. Steeves
994 F.2d 905 (First Circuit, 1993)
Haley v. City of Boston
657 F.3d 39 (First Circuit, 2011)
A.G. Ex Rel. Maddox v. Elsevier, Inc.
732 F.3d 77 (First Circuit, 2013)
Bank of Brewton, Inc. v. INTERN. FIDELITY INS. COMPANY
827 So. 2d 747 (Supreme Court of Alabama, 2002)
PMP Associates, Inc. v. Globe Newspaper Co.
321 N.E.2d 915 (Massachusetts Supreme Judicial Court, 1975)
MASSACHUSETTS MUNICIPAL WHOLESALE ELECTRIC v. Danvers
577 N.E.2d 283 (Massachusetts Supreme Judicial Court, 1991)
Stonington Water Street Assoc., LLC v. Hodess Building Co.
792 F. Supp. 2d 253 (D. Connecticut, 2011)
Structural Systems, Inc. v. Sulfaro
692 F. Supp. 34 (D. Massachusetts, 1988)
Enterprise Capital, Inc. v. San-Gra Corp.
284 F. Supp. 2d 166 (D. Massachusetts, 2003)
Sullivan v. Southland Life Insurance
854 N.E.2d 138 (Massachusetts Appeals Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Arch Insurance Company v. The Graphic Builders LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arch-insurance-company-v-the-graphic-builders-llc-mad-2021.