Arborway Committee v. Executive Office of Transportation & Construction

25 Mass. L. Rptr. 404
CourtMassachusetts Superior Court
DecidedMay 27, 2009
DocketNo. SUCV200700675E
StatusPublished

This text of 25 Mass. L. Rptr. 404 (Arborway Committee v. Executive Office of Transportation & Construction) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arborway Committee v. Executive Office of Transportation & Construction, 25 Mass. L. Rptr. 404 (Mass. Ct. App. 2009).

Opinion

Macdonald, D. Lloyd, J.

Before the Court is a summary judgment motion predicated on the claim that the plaintiffs failed to bring their claim within the three-year statutory period for contract claims brought against the Commonwealth. G.L.c. 260, §3A. For the reasons below, the Court ALLOWS the motion and orders judgment to enter in favor of the defendants.

Pertinent Facts and Positions of the Parties

The complaint arises from an alleged failure by the defendant Massachusetts Executive Office of Transportation and Construction (“EOTC”) and the defendant Massachusetts Department of Public Works (collectively, the “State Defendants”) to comply with its contractual obligations to restore light rail service to the former Forest Hills terminus of the MBTA’s Arborway line. The underlying agreement was a memorandum of understanding (“MOU”) entered into between the Conservation Law Foundation (“CLF”) and EOTC in 1990. The agreement was entered at an early stage of the Central Artery Tunnel/Third Harbor Tunnel Project a/k/a “The Big Dig” (the “the Big Dig Project”).

The MOU’s ostensible purpose was to mitigate the anticipated air quality impacts of the Big Dig Project by providing for the construction and/or restoration of mass transit service in the metropolitan Boston area. The plaintiffs The Arborway Committee and its individually named members (“Plaintiffs”) include residents and merchants of the Jamaica Plain and Mission Hill Districts of the City of Boston. They allege that they are third-party beneficiaries of the MOU and that they have been harmed by the EOTC’s failure to complete the Arborway Rail Restoration Project in breach of the MOU.

For purposes of the present motion only, the State Defendants do not dispute the Plaintiffs’ standing, and they assume arguendo that they breached the MOU. However, they submit that the subject assumed breach occurred at the latest on December 31, 1997, the time by which Arborway LRV service was to have begun operation pursuant to the MOU. With the breach having happened then, the limitations period for the Plaintiffs’ action expired on December 31, 2000, the State Defendants submit.

The Plaintiffs concede that the Arborway LRV restoration was supposed to have been completed by December 31, 1997, but they assert that by its actions the EOTC extended the time for performance. The Plaintiffs assert that the EOTC did not finally renounce its commitments under the MOU until December 1, 2006. On that date the Commonwealth’s Department of Environmental Protection (“DEP”), faced -with the EOTC’s withdrawal of support for the project, amended its regulations to no longer include the Arborway Rail Restoration Project as part of DEP’s responsibility in the implementation of the MOU. By the Plaintiffs’ calculation, the limitations period extended for three years thereafter, and the filing of this present action on February 13, 2007 was thus well within it.

Discussion

As noted, the Plaintiffs bring their action as alleged third-party beneficiaries of the MOU. For purposes to the present motion, the Court accepts the Plaintiffs’ standing as such. Further, the Court accepts for purposes of the motion that the MOU was an enforceable agreement.1

By the terms of the MOU, the restoration of LRV service to Forest Hills was to be completed at the latest by December 31, 1997. All parties concede that it was not. Thus, an action against the State Defendants would need to have been filed by December 31, 2000 to avoid being barred by the statute of limitations. The plaintiffs’ filing date of February 13, 2007, therefore, is over six years out of time unless there is a basis for their being relieved of their obligation to file before then.

The plaintiffs assert that the time for performance was extended to December 31, 2000 by operation of the MOU and was further extended thereafter by the lulling actions of the State Defendants such as to equitably estop them from reliance on the statute of limitations. These arguments are considered in turn.

Extension of the MOU to 2000

It is unclear to the Court the basis on which the plaintiffs claim that the State Defendants overtly extended the time for performance. In an October 31, 1997 letter from the Deputy Director of Environmental Policy at the EOTC to the Commissioner of the DEP, the EOTC requested such an extension, but the DEP did not approve it. Instead, the DEP requested more information from the EOTC in support of its request. When the EOTC’s response thereafter was found wanting by the DEP, the DEP in May 1998 communicated to the EOTC that it had until December 31, 1998 to either commit to completing the project by December 31, 2000 or submit a formal request for a “project substitution,” i.e., a mass transit plan in lieu of the LRV restoration plan provided for in the MOU. In January 1999 the EOTC responded with a formal petition for project substitution. By its nature, such a position stated the EOTC’s intention at that time not to construct the LRV system on the Arborway.

Further, in September 2000 the DEP rejected the EOTC’s request for substitution and ordered it to substantiate further its conclusion that the LRV project was not feasible.

[406]*406In a development consistent with the conclusion that the State Defendants had failed to perform under the MOU at that juncture, on August 31, 2000 a number of the individual plaintiffs here filed with the EOTC a Notice of Intent to Sue (the “First Notice of Intent”). (The First Notice of Intent was filed to fulfill the sixty-day notice requirements of §304(b) of the federal Clean Air Act.) The First Notice of Intent “asserted that the EOTC and the MBTA have undertaken several steps to abandon the Arborway branch.” It was filed 32 months after the expiration of the MOU’s designated time for performance. As such, it was still within the limitations period.

However, no suit was brought at that time, and the three-year limitations period expired as of December 31, 2000. At that juncture, the LRV project was not operational, and the State Defendants had not committed to a tangible alternative to the LRV plan as provided for in the MOU.2

Equitable Estoppel

The Plaintiffs acknowledge the above chronology, but they argue that they should be relieved of the operation of the statute because the State Defendants “lulled” them into thinking that they would in fact perform and thus that the State Defendants are equitably estopped from raising the limitations defense. White v. Peabody Construction Co., Inc., 386 Mass. 121, 134 (1982).

“Under equitable estoppel, a plaintiff can ‘escape the consequences of his lack of diligence in bringing his action ... by way of proof that the defendants lulled the plaintiff into the delay.’ ” Kozikowski v. Toll Bros., Inc., 354 F.3d 16, 22 (1st Cir. 2003) (applying Massachusetts law and quoting Coady v. Marvin Lumber and Cedar Co., 167 F.Sup.2d 166, 171 (D.Mass. 2001). The First Circuit outlined the doctrine’s elements:

[T]he [plaintiffs] must satisfy a three-part test, showing: (1) that [the defendant] made representations that it knew or should have known would induce the [plaintiffs] to postpone bringing a suit; (2) that they did in fact delay bringing a suit in reliance on those representations; and (3) that reliance upon those representations was reasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kozikowski v. Toll Bros., Inc.
354 F.3d 16 (First Circuit, 2003)
White v. Peabody Construction Co., Inc.
434 N.E.2d 1015 (Massachusetts Supreme Judicial Court, 1982)
New England Power Co. v. Riley Stoker Corp.
477 N.E.2d 1054 (Massachusetts Appeals Court, 1985)
Knight v. Lawrence
118 N.E.2d 747 (Massachusetts Supreme Judicial Court, 1954)
Harrington v. Fall River Housing Authority
538 N.E.2d 24 (Massachusetts Appeals Court, 1989)
Gallant v. Federal Mutual Insurance
235 N.E.2d 810 (Massachusetts Supreme Judicial Court, 1968)
Boylston Development Group, Inc. v. 22 Boylston Street Corp.
591 N.E.2d 157 (Massachusetts Supreme Judicial Court, 1992)
Cellucci v. Sun Oil Co.
320 N.E.2d 919 (Massachusetts Appeals Court, 1974)
SECOND CHURCH IN DORCHESTER v. Boston
179 N.E.2d 598 (Massachusetts Supreme Judicial Court, 1962)
Ford v. Rogovin
289 Mass. 549 (Massachusetts Supreme Judicial Court, 1935)
Rhode Island Hospital Trust National Bank v. Varadian
647 N.E.2d 1174 (Massachusetts Supreme Judicial Court, 1995)
Clickner v. City of Lowell
422 Mass. 539 (Massachusetts Supreme Judicial Court, 1996)
Pagliarini v. Iannaco
440 Mass. 1032 (Massachusetts Supreme Judicial Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
25 Mass. L. Rptr. 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arborway-committee-v-executive-office-of-transportation-construction-masssuperct-2009.