ARB, Inc. v. Luz Const., Inc.

972 F.2d 1336, 1992 U.S. App. LEXIS 27415, 1992 WL 164487
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 16, 1992
Docket91-55758
StatusUnpublished

This text of 972 F.2d 1336 (ARB, Inc. v. Luz Const., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ARB, Inc. v. Luz Const., Inc., 972 F.2d 1336, 1992 U.S. App. LEXIS 27415, 1992 WL 164487 (9th Cir. 1992).

Opinion

972 F.2d 1336

NOTICE: Ninth Circuit Rule 36-3 provides that dispositions other than opinions or orders designated for publication are not precedential and should not be cited except when relevant under the doctrines of law of the case, res judicata, or collateral estoppel.
ARB, INC., a California Corporation; ARB Fabricated
Systems, Inc.; et al., Plaintiffs-Appellants,
v.
LUZ CONSTRUCTION, INC.; Manufacturers Hanover Trust Company
of California, a California corporation; et al.,
Defendants-Appellees.

No. 91-55758.

United States Court of Appeals, Ninth Circuit.

Submitted July 9, 1992.*
Decided July 16, 1992.

Before SNEED and D.W. NELSON, Circuit Judges, and ROLL, District Judge.**

MEMORANDUM***

Arb, Inc. and Arb Fabricated Systems, Inc. (collectively "Arb"), major subcontractors involved in a project to build a solar electricity generating station, brought this breach of contract, fraud, and civil RICO action against Luz Construction, Inc. ("Luz"), the general contractor, and Manufacturers Hanover Trust Co. ("MHT"), the bank which held in escrow the construction funds in dispute. The district court granted summary judgment for MHT, and Arb appeals.1 We affirm.

FACTS

Luz contracted to build Solar Electricity Generating Systems IX ("SEGS IX"), a $270 million power plant near Barstow, California. It hired Arb and Arb Fabricated as subcontractors to supply some of the materials used in construction. The money for the plant was paid into an escrow account held by MHT. Luz, MHT, the job owners, and several other companies were parties to the escrow agreement. Arb was not a party.

In July 1990, Arb ceased work on SEGS IX, apparently because it feared that it would not get paid. To alleviate Arb's concerns, Luz sent disbursement directions to MHT instructing it to pay Arb $1.3 million in past invoices, and to hold another $2.3 million in escrow against future invoices. The latter amount was to be paid on or after September 15, 1990, subject to approval of the invoices by Luz and by R.W. Beck & Associates ("Beck"), an independent engineering firm.

MHT apparently did not segregate this $2.3 million from the general $270 million escrow account. When Arb discovered this on September 4, it filed this suit against MHT and obtained a temporary restraining order the same day requiring MHT to hold the $2.3 million separate.2 MHT complied on September 5. In the meantime, Luz disputed a number of Arb's billing invoices. As a result, Luz refused to approve those invoices, and MHT therefore did not pay Arb. The disputed money remained in escrow until March 12, 1991, when the district court ordered MHT to pay the money to Arb. MHT did so.

The district court then granted summary judgment in favor of MHT on Arb's remaining claims against it for consequential damages. The district court certified this order as a partial final judgment pursuant to Fed.R.Civ.P. 54, and Arb appealed.

STANDARD OF REVIEW

We review a grant of summary judgment de novo. Kruso v. International Tel. & Tel. Corp., 872 F.2d 1416, 1421 (9th Cir.1989), cert. denied, 110 S.Ct. 3217 (1990). We must determine whether, viewing the evidence in the light most favorable to Arb, there are any genuine issues of material fact and whether the district court correctly applied the relevant substantive law. Tzung v. State Farm Fire & Cas. Co., 873 F.2d 1338, 1339-40 (9th Cir.1989).

DISCUSSION

A. Proximate Cause

Under California law, recovery for breach of contract and fraud is limited to damages proximately caused by the allegedly wrongful act. Cal.Civ.Code § 3333. In this case, MHT's allegedly wrongful act was its failure to release to Arb the funds it held in escrow for Luz and the job owners. Before the district court, Arb sought to recover this money in payment for its work for Luz, and also sought consequential damages for lost business opportunities resulting from MHT's failure to provide the money in a timely fashion. The district court ordered MHT to disburse the disputed funds from escrow, and MHT has done so. On appeal, therefore, Arb is seeking to recover only consequential damages from MHT.

We conclude that Arb cannot possibly have suffered consequential damages as a result of MHT's actions. The escrow disbursement instructions required MHT to hold $2.3 million in escrow for payment sometime on or after September 15, 1990. As a result of the court order obtained by Arb, MHT reserved those funds in escrow on September 5, 1990. Because MHT in fact complied with the escrow instructions ten days before it was required to, Arb cannot have been injured by MHT's failure to segregate the funds immediately. As the district court concluded, "ultimately nothing really happened, the money went in, and there is, in my judgment, no proximate causation between the delay for the money going in and any damage." E.R. 144-45.

Arb advances two arguments to the contrary. First, Arb suggests that MHT's failure to segregate the funds in escrow in July made it more difficult for Arb to obtain financing between July and September. This argument is unavailing. Even were we to assume that MHT, contrary to the escrow disbursement direction, had a duty to segregate the funds beginning July 10, 1990, Arb's argument is undercut by the uncontradicted testimony of its own bank's loan officer. Mary Grider, a Vice President at Wells Fargo Bank and Arb's account executive, testified that no Arb financing was cancelled, delayed, or otherwise adversely affected by MHT's failure to segregate funds. Grider also testified that Arb never even approached Wells Fargo in an effort to obtain financing during this period. Arb has thus presented no evidence that it was injured in any way by MHT's failure to segregate the funds between July and September.

Arb's second argument is that it was injured by MHT's failure to release the funds to Arb on September 15, 1990. By this time, however, Luz had disputed Arb's invoices. The district court resolved this dispute and ordered MHT to disburse the funds to Arb on March 12, 1991. The problem with Arb's argument is that MHT acted properly in refusing to release the funds to Arb. The disbursement directions to MHT are unambiguous: MHT is "directed to reserve an additional amount, in escrow, pending [Luz's] audit and approval of ARB invoices in an amount not to exceed $2.3 million.... Outstanding ARB invoices will be paid from this disbursement subject to audit and approval by [Luz] and certification by R.W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hannon v. Western Title Insurance
211 Cal. App. 3d 1122 (California Court of Appeal, 1989)
Peterson Development Co. v. Torrey Pines Bank
233 Cal. App. 3d 103 (California Court of Appeal, 1991)
Schonfeld v. City of Vallejo
50 Cal. App. 3d 401 (California Court of Appeal, 1975)
Pasadena Unified School District v. Pasadena Federation of Teachers
72 Cal. App. 3d 100 (California Court of Appeal, 1977)
La Jolla Village Homeowners' Ass'n v. Superior Court
212 Cal. App. 3d 1131 (California Court of Appeal, 1989)
Price v. Wells Fargo Bank
213 Cal. App. 3d 465 (California Court of Appeal, 1989)
Jackson v. Bank of Hawaii
902 F.2d 1385 (Ninth Circuit, 1990)
Levine v. Diamanthuset, Inc.
950 F.2d 1478 (Ninth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
972 F.2d 1336, 1992 U.S. App. LEXIS 27415, 1992 WL 164487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arb-inc-v-luz-const-inc-ca9-1992.