ARB Construction, LLC v. Pinney Construction Corp.

815 A.2d 705, 75 Conn. App. 151, 2003 Conn. App. LEXIS 67
CourtConnecticut Appellate Court
DecidedFebruary 18, 2003
DocketAC 22233
StatusPublished
Cited by5 cases

This text of 815 A.2d 705 (ARB Construction, LLC v. Pinney Construction Corp.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ARB Construction, LLC v. Pinney Construction Corp., 815 A.2d 705, 75 Conn. App. 151, 2003 Conn. App. LEXIS 67 (Colo. Ct. App. 2003).

Opinion

[152]*152 Opinion

SCHALLER, J.

The defendant, Pinney Construction Corporation, appeals from the judgment rendered by the trial court in a breach of contract action awarding $149,616 to the plaintiff, ARB Construction, LLC. On appeal, the defendant claims that the court improperly (1) concluded that the contract between the parties was clear and unambiguous, (2) concluded that the defendant did not meet its burden of proof on its counterclaim that the plaintiffs work was unskillful, negligent or unworkmanlike and (3) prevented the defendant from introducing a site plan into evidence. We affirm the judgment of the trial court.

The court made the following factual findings in its memorandum of decision. “[The plaintiff] is owned and operated by Andrew Burnham. [The defendant] is owned and operated by Craig Pinney. On May 25, 1999, [the defendant] contracted with Silver Cove Associates, LLC (Silver Cove), to reconstruct and provide new construction at Silver Cove’s shopping plaza located at 150-210 Silas Deane Highway, Wethersfield, Connecticut (the plaza). Thereafter, on June 10, 1999, [the defendant], as general contractor, entered into a one page written contract with [the plaintiff], as subcontractor, for [the plaintiff] to perform a host of site excavation and preparation tasks at the plaza. When Burnham and Pinney met on June 10, 1999, to draw the contract, they had available to them a set of plans for the plaza, substantially as approved by the Wethersfield planning and zoning commission, including an existing conditions plan, a site plan, a grading and utility plan, a landscape plan, an erosion and sedimentation control plan, a roadway plan and two pages of construction details. By the terms of the written contract [the plaintiff] was to be paid in the lump sum amount of $430,000, less a credit of $80,000 for an unrelated job, for a total of $350,000. [The plaintiff] was to undertake and com[153]*153píete the following tasks in accordance with the site plan: reclaimed parking lot, bituminous curbing, cut/ repour front concrete curb at plaza, sidewalks, cuts and fills, drainage, sewer, gas trenching, water, sprinkler and hydrant, electrical trenching with pipe included, remove and replace light poles, demolition/excavation rear loading docks and foundations, demolition masonry at overhead doors in rear, demolition bank building and landscaping.”

The plaintiff subsequently commenced work on the project. The plaintiff entered into a contract with Empire Paving, Inc. (Empire), to perform both the reclaiming and paving of the parking lot. The plaintiff was to be responsible for payment to Empire for the reclamation costs, and the defendant was to be responsible for the paving costs. The court found that the plaintiff contracted with Empire on behalf of the defendant only as a convenience.

The court concluded that paving was not included in the contract between the parties because the contract was clear and unambiguous that only a reclaimed parking lot was required. Furthermore, the court determined that the term “reclaimed parking lot” did not encompass paving. This appeal followed.

I

The defendant’s first claim on appeal is that the court improperly determined that the contract was clear and unambiguous as to the inclusion of paving. The defendant argues that the contract term “reclaimed parking lot” was an ambiguous term that required paving to be done, and, therefore, the plaintiff was responsible under the contract for the paving of the parking lot.1 We do not agree.

[154]*154The defendant’s claim raises a mixed issue of fact and law. “A contract must be construed to effectuate the intent of the parties, which is determined from the language used interpreted in the light of the situation of the parties and the circumstances connected with the transaction. . . . [T]he intent of the parties is to be ascertained by a fair and reasonable construction of the written words and . . . the language used must be accorded its common, natural, and ordinary meaning and usage where it can be sensibly applied to the subject matter of the contract.” (Internal quotation marks omitted.) Putnam Park Associates v. Fahnestock & Co., 73 Conn. App. 1, 8, 807 A.2d 991 (2002). Where a technical or special meaning is intended by the language of the contract, that meaning, and not the language’s ordinary usage, shall be employed. See New England Petroleum Corp. v. Groppo, 214 Conn. 444, 450, 572 A.2d 970 (1990).

“Where the language of the contract is clear and unambiguous, the contract is to be given effect according to its terms. . . . Although ordinarily the question of contract interpretation, being a question of the parties’ intent, is a question of fact . . . [w]here there is definitive contract language, the determination of what the parties intended by their contractual commitments is a question of law.” (Citation omitted; inter[155]*155nal quotation marks omitted.) Putnam Park Associates v. Fahnestock & Co., supra, 73 Conn. App. 8. “When . . . the trial court draws conclusions of law ... we must decide whether its conclusions are legally and logically correct and find support in the facts that appear in the record.” (Internal quotation marks omitted.) Murphy, Inc. v. Remodeling, Etc., Inc., 62 Conn. App. 517, 522, 772 A.2d 154, cert. denied, 256 Conn. 916, 773 A.2d 945 (2001). Our standard of review, therefore, is plenary. See Aubin v. Miller, 64 Conn. App. 781, 790, 781 A.2d 396 (2001).

“Contract language is unambiguous when it has a definite and precise meaning about which there is no reasonable basis for a difference of opinion.” (Internal quotation marks omitted.) Christian v. Gouldin, 72 Conn. App. 14, 20, 804 A.2d 865 (2002). “A court will not torture words to import ambiguity where the ordinary meaning leaves no room for ambiguity, and words do not become ambiguous simply because lawyers or laymen contend for different meanings.” (Internal quotation marks omitted.) Mallozzi v. Nationwide Mutual Ins. Co., 72 Conn. App. 620, 628, 806 A.2d 97, cert. denied, 262 Conn. 915, 811 A.2d 1292 (2002). “[A] presumption that the language used is definitive arises when, as in the present case, the contract at issue is between sophisticated parties and is commercial in nature.” United Illuminating Co. v. Wisvest-Connecticut, LLC, 259 Conn. 665, 670, 791 A.2d 546 (2002).

Here, the court engaged in a two step process in construing the contract. First, the court concluded that the contract was clear and unambiguous because paving was not expressly listed as a task to be performed on the contract. The plaintiff, therefore, was responsible for only a reclaimed parking lot. We agree with the court. The contract clearly lists the jobs to be performed, and paving is not listed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Tax Funding, LLC v. First Eagle Corp.
196 Conn. App. 298 (Connecticut Appellate Court, 2020)
Whitney v. J.M. Scott Associates, Inc.
Connecticut Appellate Court, 2016
Detels v. Detels
830 A.2d 381 (Connecticut Appellate Court, 2003)
Advanced Financial Services, Inc. v. Associated Appraisal Services, Inc.
830 A.2d 240 (Connecticut Appellate Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
815 A.2d 705, 75 Conn. App. 151, 2003 Conn. App. LEXIS 67, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arb-construction-llc-v-pinney-construction-corp-connappct-2003.