Aqua Dredge, Inc. v. Stony Point Marina & Yacht Club, Inc.

183 A.D.2d 1055, 583 N.Y.S.2d 648, 1992 N.Y. App. Div. LEXIS 6872
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 14, 1992
StatusPublished
Cited by4 cases

This text of 183 A.D.2d 1055 (Aqua Dredge, Inc. v. Stony Point Marina & Yacht Club, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aqua Dredge, Inc. v. Stony Point Marina & Yacht Club, Inc., 183 A.D.2d 1055, 583 N.Y.S.2d 648, 1992 N.Y. App. Div. LEXIS 6872 (N.Y. Ct. App. 1992).

Opinion

Mercure, J.

Appeal (transferred to this court by order of the Appellate Division, [1056]*1056Second Department) from a judgment of the Supreme Court (Meehan, J.), entered October 19, 1990 in Rockland County, upon a decision of the court in favor of plaintiff against defendant AARK Construction Corporation.

Plaintiff and defendant AARK Construction Corporation (hereinafter defendant) entered into a written contract under the terms of which plaintiff was to dredge material from the bottom of the Hudson River in connection with the development of the area as a marina. Compensation was fixed at $250 per hour of operation in pumping, moving pipelines or equipment related to dredging, or servicing the dredging plant. The contract also provided for a maximum or "upset” price of $75,000 for the area described as "Phase I” and $60,000 for "Phase II”, and stated that in the event the cost computed on an hourly basis was less than the upset price, the parties would share the savings equally. Plaintiff began its dredging operations on December 22, 1988 and worked continually until March 3, 1989, when defendant directed that it discontinue operations due to lack of funds. Plaintiff subsequently commenced this action to recover for defendant’s breach of the contract. The matter ultimately came on for a nonjury trial, following which Supreme Court rendered judgment in favor of plaintiff in the amount of $105,724, together with interest from April 3, 1989. Defendant appeals, challenging only Supreme Court’s award of damages.

Had plaintiff been permitted to complete the contract, computation of its damages would have been an easy matter. The total number of hours expended on the project would be multiplied by $250, and the product (hereinafter the hourly price) would be compared to the total upset price. If the hourly price was equal to or exceeded the upset price, then the upset price would be paid. If the hourly price was less than the upset price, then plaintiff would be paid the hourly price plus one half of the difference between the upset price and the hourly price, to permit an equal sharing of the savings. However, with the contract only partially completed, Supreme Court was faced with the difficult task of prorating the upset price to the work actually performed.

Determining that plaintiff’s invoices furnished the most credible evidence on the issue (see, Dobert Constr. Corp. v Holser Excavating, 36 AD2d 1002, 1003), a finding which the record amply supports, Supreme Court first considered plaintiff’s February 8, 1989 invoice for the period December 28, 1988 to January 31, 1989, which showed that plaintiff had expended 228 hours of work and completed approximately [1057]*105745% of Phase I, Phase II and another area designated "Alternate 1”, computed by volume of materials removed. Next, Supreme Court considered plaintiff’s March 3, 1989 invoice, which charged for an additional 136 hours of work to the time of the stoppage. Although the latter invoice did not state the approximate percentage of the project which had been completed, Supreme Court imputed an additional 26.8%, based upon the rate of progress reflected in the first invoice. At this point, Supreme Court was able to determine that plaintiff had expended 364 hours of work and had completed 71.8% of the project. Multiplying the hours expended by $250 produces a $91,000 hourly price, and multiplying the $135,000 upset price for Phases I and II by 71.8% produces a prorated upset price of $96,930. The difference between the hourly price and the prorated upset price is $5,930; one half of that figure is $2,965,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bohnak v. Marsh & McLennan Companies, Inc.
79 F.4th 276 (Second Circuit, 2023)
Gold v. Ziff Communications Co.
748 N.E.2d 198 (Appellate Court of Illinois, 2001)
Jacobowitz v. Montano Specialty Auto
188 A.D.2d 720 (Appellate Division of the Supreme Court of New York, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
183 A.D.2d 1055, 583 N.Y.S.2d 648, 1992 N.Y. App. Div. LEXIS 6872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aqua-dredge-inc-v-stony-point-marina-yacht-club-inc-nyappdiv-1992.