Aptos Residents Ass'n v. Cnty. of Santa Cruz

229 Cal. Rptr. 3d 605, 20 Cal. App. 5th 1039
CourtCalifornia Court of Appeal, 5th District
DecidedFebruary 5, 2018
DocketH042854
StatusPublished
Cited by12 cases

This text of 229 Cal. Rptr. 3d 605 (Aptos Residents Ass'n v. Cnty. of Santa Cruz) is published on Counsel Stack Legal Research, covering California Court of Appeal, 5th District primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aptos Residents Ass'n v. Cnty. of Santa Cruz, 229 Cal. Rptr. 3d 605, 20 Cal. App. 5th 1039 (Cal. Ct. App. 2018).

Opinion

Mihara, J.

*609*1042Appellant Aptos Residents Association (ARA) challenges the superior court's denial of its petition for a writ of mandate under the California Environmental Quality Act (CEQA) ( Pub. Resources Code, § 21000, et seq. ). ARA's petition challenged the approval by respondent County of Santa Cruz (the County) of a microcell transmitter project proposed by real party Crown Castle (Crown). Crown's project originally proposed to install 13 microcell transmitters as part of a Distributed Antenna System (DAS). These *1043microcells would be placed on utility poles, primarily in the public right of way,1 in the Day Valley area, a rural portion of unincorporated Aptos. The County concluded that Crown's DAS project was categorically exempt from CEQA and rejected ARA's claim that an exception to the exemption applied.

On appeal, ARA contends the County abused its discretion by (1) finding that the exemption applied because it failed to consider the entire project and instead improperly segmented the project by considering each microcell individually, (2) failing to consider information submitted by ARA that AT & T was interested in putting cell transmitters in the Day Valley area and finding that the "cumulative impact" exception did not apply, (3) finding that the "location" exception did not apply, and (4) finding that the "unusual circumstances" exception did not apply. We reject ARA's contentions and affirm the judgment.

I. Background

Crown proposed to install a 13-microcell DAS system in the Day Valley area of Aptos for the purpose of providing wireless coverage for Verizon. Each microcell would consist of a two-foot by one-foot antenna mounted on an extender pole, which would be attached to an existing utility pole in the County's right-of-way or on private property, along with "related pole-mounted equipment." Crown submitted a separate permit application to the County's Zoning Administrator for each microcell.

Many residents of the Day Valley area signed a petition objecting to Crown's proposed project on the grounds that it would create "a health hazard" and "an aesthetic blight." ARA, which organized the opposition to Crown's project, submitted a letter contending that Crown's project was not exempt from CEQA because it fell within the "cumulative impact" exception or the "unusual circumstance" exception.2

Frank Barron, a planner for the County, prepared a staff report on the project for the Zoning Administrator. Barron characterized the microcells as "relatively visually inconspicuous" and determined that they fell within a categorical exemption from CEQA that applies to "small ... structures." ( Cal. Code of Regs., tit. 14, § 15303 [exemption for small structures].)3

*610Barron also concluded that no exceptions to the exemption applied. (Guidelines, § 15300.2 [exceptions to exemptions].)

*1044In October 2013, the Zoning Administrator considered Crown's applications for 11 permits. Although Crown had submitted separate permit applications for each microcell unit, the Zoning Administrator considered all 11 applications together. The Zoning Administrator rejected ARA's contentions and found that the project was exempt from CEQA.4

ARA appealed the Zoning Administrator's approvals to the County's Planning Commission on the same grounds that it had raised before the Zoning Administrator. ARA asserted that the County needed to consider the impact of Crown's project in conjunction with the impact of a PG & E project that proposed to replace some of the wood poles in the Day Valley area with 100-foot tubular steel poles.5

Barron prepared an extensive report for the Planning Commission addressing the nature of the project and ARA's contentions. Through site visits and photo-simulations, he concluded that the "addition of the microcell antennas and equipment boxes to the poles" would not create "a visual impact, either individually or cumulatively" and "would not result in visual or other environmental impacts." Barron noted that the PG & E project had already undergone CEQA review and had been found to have no significant visual impact. Even taking the PG & E project into consideration along with Crown's project, he found "no cumulative impacts would occur." Barron also determined that Crown's DAS project was "the least visually intrusive means" of providing cell service in the area.

In February 2014, the Planning Commission considered Crown's remaining 10 permit applications together and found that they qualified for a categorical exemption both individually and as a group.6 It found that the "visual impact" of the 10 microcells would be "negligible" "even when considered together and in conjunction with the PG & E" project and would not have "a significant cumulative visual impact." The Planning Commission approved the 10 permit applications, certified the categorical CEQA exemptions, and denied ARA's appeals.

ARA appealed the Planning Commission's decision to the County's Board of Supervisors (the Board). In March 2014, ARA sent a letter to the Board *1045regarding "new information" that, according to ARA, demonstrated that AT & T "will likely be installing their own cell transmitters" in the same Day Valley area where Crown's project would be installed. ARA urged the Board to consider the possible AT & T project in conjunction with the Crown project as part of a cumulative impact analysis. The "new information" provided by ARA was its attorney's declaration in which he recounted a March 2014 telephone conversation he had had with Barron. *611ARA's attorney declared: "Barron stated that he had been contacted by AT & T and that they expressed their desire to install cell transmitters in the Day Valley Aptos area. He told me that they advised that they would likely wait to see whether Verizon's [sic ] application for the DAS units in issue in this appeal were [sic ] upheld before they installed their own version, or that they would wait to see if the County's proposed 'Broadband Initiative' was passed and then proceed."7

In April 2014, the Board considered whether to take jurisdiction over ARA's appeals of the 10 permits. The Board considered the 10 permits as a group. It had before it "multiple staff reports," "photo simulations," and letters from both ARA and Crown. ARA's attorney gave a 20-minute presentation to the Board.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
229 Cal. Rptr. 3d 605, 20 Cal. App. 5th 1039, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aptos-residents-assn-v-cnty-of-santa-cruz-calctapp5d-2018.